Westway Const., Inc. v. Benton County
This text of 151 P.3d 1005 (Westway Const., Inc. v. Benton County) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
WESTWAY CONSTRUCTION, INC., and Billy Phelps, Appellants,
v.
BENTON COUNTY and Terry Mardens and Jane Doe Mardens, and their marital community, and Michael Shuttleworth and Jane Doe Shuttleworth, and their marital community, Respondents.
Court of Appeals of Washington, Division 3.
*1007 Joanne G. Comins Rick, Halstead & Comins Rick PS, Prosser, WA, for Appellants.
Mark Robert Johnsen, Attorney at Law, Seattle, WA, for Respondents.
KATO, J.
¶ 1 Westway Construction, Inc. (Westway), applied for and received a special use permit from Benton County to mine and crush rock on Billy Phelps's property. The permit prohibited mining or crushing from March 1 through August 15 because of the existence of a ferruginous hawk nest. Westway and Mr. Phelps sued Benton County for damages under chapter 64.40 RCW, as well as tort and due process claims. Benton County's motion for summary judgment was granted. Westway and Mr. Phelps appeal. We affirm.
¶ 2 On March 30, 2000, Westway applied for a special use permit from Benton County to mine 23,000 tons of rock and operate a 200 ton-per-hour rock crusher on Billy Phelps's property. Westway Constr. Inc. v. Benton County, noted at 117 Wash.App. 1089, 2003 WL 21761953 (2003). Westway needed the rock to perform on a contract for a Benton County road project.
¶ 3 In considering Westway's application, the Planning Department found the site was in a Fish and Wildlife Conservation area. Mark Teske of the Department of Fish and Wildlife told the Planning Department that a ferruginous hawk nest was adjacent to the site and Westway's mining and crushing operation would harm the nest.
¶ 4 On May 16, 2000, the Planning Department imposed a date restriction on the special use permit barring operations from March 1 through August 15, so as not to disturb the hawk's nesting in its mitigated determination of nonsignificance (MDNS). Westway disputed the restriction.
¶ 5 On June 1, 2000, the Benton County Board of Adjustment (Board) held a public hearing on the special use permit and the MDNS. Jason West of Westway told the Board the August 15 date would interfere with at least one of the contract dates. Mr. Teske stated hawks were susceptible to disturbances and would probably abandon their nests and their young if the Board permitted the special use before August 15, when the young would be ready to leave on their own. He also said he had visited the site recently and saw a hawk.
¶ 6 The Board approved the special use permit with the restrictions and rejected Westway's appeal of the MDNS. Westway and Mr. Phelps appealed to the superior court. They sought review under chapter 36.70C RCW, the Land Use Petition Act (LUPA), alleging the Board had violated its right to due process and the decision was not supported by substantial evidence. They also included claims for tortious conduct, unlawful government acts under chapter 64.40 RCW, and civil rights violations.
¶ 7 Westway and Mr. Phelps requested the court to stay enforcement of the Board's *1008 special use restrictions pending its decision. The Benton County Superior Court held a hearing. State biologists conducted an inspection of the site and concluded there was no nest on the site. The court granted a stay of the mitigation conditions on July 26, 2000. The rock crushing operation began and was completed on time.
¶ 8 Westway nevertheless continued with its appeal seeking reversal of the Board's decision. On August 20, 2001, the court affirmed the Board because substantial evidence supported its decision. The court rejected Westway's claim that it had been denied due process in the Board's hearing. Westway and Mr. Phelps appealed to this court, which found substantial evidence did not exist to support the Board's findings. The opinion was issued in July 2003; a mandate was thereafter issued.
¶ 9 On July 9, 2004, Westway and Mr. Phelps filed an amended complaint for damages, alleging the County violated chapter 64.40 RCW because its actions in issuing the permit were arbitrary and capricious. They also sued under various tort theories.
¶ 10 Benton County filed a motion for summary judgment. Rather than responding to this motion, Westway and Mr. Phelps filed an objection to the motion, claiming it was premature. The motion for summary judgment was granted. Westway and Mr. Phelps filed a motion for reconsideration that included new evidence. The court denied the motion on both substantive and procedural grounds. This appeal follows.
¶ 11 We review summary judgment rulings de novo. Grundy v. Thurston County, 155 Wash.2d 1, 6, 117 P.3d 1089 (2005). Summary judgment is appropriate only if the pleadings, affidavits, depositions, and admissions in the record on review demonstrate (1) the absence of any genuine issues of material fact; and (2) the moving party is entitled to judgment as a matter of law. CR 56(c). "`[T]he court must consider all facts submitted and all reasonable inferences from the facts in the light most favorable to the nonmoving party.'" Grundy, 155 Wash.2d at 6, 117 P.3d 1089 (quoting Highline Sch. Dist. No. 401 v. Port of Seattle, 87 Wash.2d 6, 15, 548 P.2d 1085 (1976)).
¶ 12 At the threshold, Benton County claims Westway waived any substantive arguments opposing the entry of summary judgment dismissal because it failed to raise those arguments at the trial court. A summary judgment argument not pleaded or argued to the trial court cannot be raised for the first time on appeal. Sneed v. Barna, 80 Wash.App. 843, 847, 912 P.2d 1035, review denied, 129 Wash.2d 1023, 919 P.2d 600 (1996). Westway did not advance the arguments now made on appeal in any written pleading prior to the summary judgment hearing. The record of the summary judgment arguments, however, establishes that it did make its arguments orally to the trial court. Since the court considered them below, we will consider them on appeal.
¶ 13 Westway and Mr. Phelps claim the court erred by dismissing their claim under chapter 64.40 RCW. That chapter provides an action for property owners aggrieved by a decision on a permit application. Smoke v. City of Seattle, 132 Wash.2d 214, 221, 937 P.2d 186 (1997). RCW 64.40.020(1) provides:
Owners of a property interest who have filed an application for a permit have an action for damages to obtain relief from acts of an agency which are arbitrary, capricious, unlawful, or exceed lawful authority, or relief from a failure to act within time limits established by law: PROVIDED, That the action is unlawful or in excess of lawful authority only if the final decision of the agency was made with knowledge of its unlawfulness or that it was in excess of lawful authority, or it should reasonably have been known to have been unlawful or in excess of lawful authority.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
151 P.3d 1005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westway-const-inc-v-benton-county-washctapp-2007.