Westmoreland Manganese Corporation v. United States

246 F.2d 351, 1957 U.S. App. LEXIS 4656
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 26, 1957
Docket15500_1
StatusPublished
Cited by6 cases

This text of 246 F.2d 351 (Westmoreland Manganese Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westmoreland Manganese Corporation v. United States, 246 F.2d 351, 1957 U.S. App. LEXIS 4656 (8th Cir. 1957).

Opinion

VAN OOSTERHOUT, Circuit Judge.

This is an appeal by Westmoreland Manganese Corporation, hereinafter called Westmoreland, from a judgment foreclosing mortgages given the Government by Westmoreland. The Government, pursuant to the Defense Production Act of 1950, 50 U.S.C.A.Appendix, § 2061 et seq., entered into a contract to lend Westmoreland $3,807,250 to aid it in acquiring and developing a manganese ore mining and processing plant, Westmoreland agreeing to sell the manganese ore, which was considered a strategic and critical metal, to the Government upon agreed terms. Mortgages were executed and delivered to secure the money to be loaned. Government funds totaling nearly $3,000,000 were advanced to Westmoreland. On October 23,1953, the Government, acting under the terms of Amendment No. 1 to the contract, terminated the contract, and on January 8, 1954, commenced this foreclosure action. The original contract and mortgage provided that, if Westmoreland defaulted in the performance of any of the obligations assumed by it in said instruments and if such default remained unremedied for 60 days after notice thereof, the Government would have the right to declare all indebtedness secured by the mortgage due and could foreclose the mortgage. It is conceded that the Government did not give Westmoreland the 60 days’ notice required by the original instruments. The Government asserts its right to foreclosure by virtue of Amendment No. 1 to the contract, dated April 2, 1953, set out in the footnote. 1

*353 It is not seriously questioned that the amendment gives the Government the right to terminate the contract at any time prior to commencement of production, or that Westmoreland has expressly waived the requirement that the 60 days’ notice of default be given as well as all other moratorium provisions of the original instrument. Westmoreland’s defense is that Amendment No. 1 is not supported by a valid consideration, and hence is not binding upon it. Westmoreland concedes that if Amendment No. 1 is supported by consideration, this foreclosure is authorized.

The trial court found that the amendment is supported by consideration and the Government was entitled to foreclose.

Westmoreland had also asserted in the trial court that the amendment was induced by fraud. The trial court rejected this contention. Westmoreland in its brief states it has abandoned the fraud issue.

The trial court summarizes the law applicable to the consideration issue as follows (134 F.Supp. 898, 910):

“With regard to consideration, the applicable principles of law are well settled and may be briefly stated: Parties who are capable of making a contract in the first instance are likewise capable of varying or modifying its terms, and their mutual agreements or undertakings in that connection furnish consideration for the modification; moreover, consideration for a contract may be found not only in benefits moving to the promisor (in this case Westmoreland), but also in legal detriment suffered by the promisee (here the *354 Government) in reliance upon the agreement. Another principle of contract law, invoked by Westmoreland, is that ordinarily an undertaking by a party to do something that he is already obligated to do is not sufficient to constitute consideration; that general rule, however, is subject to an exception in cases where ‘the very existence of the duty is the subject of honest and reasonable dispute.’ 17 C.J.S. Contracts § 110.”

Westmoreland in its brief states that it does not disagree with the law as above stated by the trial court, but that it does disagree with the court’s application of the law to the facts of this case.

It is, of course, the function of the trial court acting without a jury to determine disputed questions of fact. We are not authorized to try this case de novo. In reviewing the trial court’s findings we must examine the evidence in the light most favorable to the prevailing party. A reversal is warranted only if the trial court’s findings are clearly erroneous.

The trial court carefully explains in his opinion, reported at 134 F.Supp. 898, the basis of his findings that Amendment No. 1 was supported by a consideration. We agree with the trial court’s analysis of the evidence and are convinced that he reached a permissible conclusion.

The original contract required Westmoreland to commence production of manganese ore in substantial quantities by April 7, 1953. In the whereas clauses of the amendment set out in footnote 1 Westmoreland conceded that production of manganese ore would not be commenced within the period re qu.'.red by the contract, and that it was without funds to complete the project contemplated by the contract, and that it had outstanding obligations it could not meet. The Government had severely criticized the management of Westmoreland prior to Stringham’s appointment as acting manager in December 1952. In January of 1953 Stringham learned that the proceeds of the Government’s loan would be inadequate to place the Westmoreland plant in operation, and that upwards of $500,000 additional money would be needed to complete the project. Prior to that time all reports and flow sheets had indicated that the project would be completed with the funds provided by the original loan. Negotiations for an additional loan from the Government were opened, and a formal request for $545,-800 additional money was made, the application stating private funds were not available. While some evidence was introduced to the effect that private financing for the additional funds required might be possible, the court, on the evidence as a whole, was fully justified in reaching the conclusion.that “Westmoreland knew that it could not complete construction within the time limited by the original agreement or without further funds from the Government, and it also knew that its management had been seriously criticized by the Government; how under such circumstances the directors could have seriously believed that they were in good standing with the Government with respect to their contract is hard to conceive; and we do not consider that they did so believe.” After several days of conferences between the Government officials and Westmoreland’s directors and attorneys, Westmoreland’s board of directors authorized the signing of Amendment No. 1 on behalf of the corporation. Later, upon recommendation of the directors and Westmoreland’s attorneys, the stockholders ratified the execution of Amendment No. 1.

The original contract provides that each request for an advance of funds be supported by a flow sheet. Shortly after the execution of the contract, at a conference between officials representing the Government and Westmoreland, a flow sheet was worked out and agreed upon showing the estimated cost of each major component of the contemplated construction work. A countersignature system was worked out whereby the Dallas, Texas, comptroller of the General Services Administration was to sign checks drawn against ad *355 vanees. Evidence introduced by the Government discloses that the comptroller was to satisfy himself that each voucher or check was legitimately charged against one of the components shown on the flow sheet, and that the total checks for any component part did not exceed the total amount estimated therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No.
Arkansas Attorney General Reports, 1990
Hall & Hall
202 Ct. Cl. 1107 (Court of Claims, 1973)
American President Lines, Ltd. v. United States
224 F. Supp. 187 (N.D. California, 1963)
United States v. Latrobe Construction Company
246 F.2d 357 (Eighth Circuit, 1957)
United States v. Latrobe Construction Co.
246 F.2d 357 (Eighth Circuit, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
246 F.2d 351, 1957 U.S. App. LEXIS 4656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westmoreland-manganese-corporation-v-united-states-ca8-1957.