Westmoreland-LG&E Partners v. Virginia Electric & Power Co.

47 Va. Cir. 130, 1998 Va. Cir. LEXIS 287
CourtRichmond County Circuit Court
DecidedSeptember 2, 1998
DocketCase No. LX-2859-1
StatusPublished

This text of 47 Va. Cir. 130 (Westmoreland-LG&E Partners v. Virginia Electric & Power Co.) is published on Counsel Stack Legal Research, covering Richmond County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westmoreland-LG&E Partners v. Virginia Electric & Power Co., 47 Va. Cir. 130, 1998 Va. Cir. LEXIS 287 (Va. Super. Ct. 1998).

Opinion

BY JUDGE MELVIN R. HUGHES, JR.

I have read and considered the materials both sides have submitted on the question of disclosure of the Brown letter, including, of course, the letter, which came with plaintiffs material under seal for in camera review. The question is whether the attorney-client privilege, which plaintiff asserts protects the letter from disclosure to defendant, applies. Brown wrote the letter in draft format then sent it to Folkes, who is with a different company, who in turn gave it to his company’s lawyer, Schenk, for review and comment. Schenk advised against sending the letter. This advice was followed and the letter was not sent.

It is interesting that Schenk is not Brown’s counsel but rather counsel for Folkes’ company and that the letter first went to Folkes without first being reviewed by Brown’s in-house counsel. The court must accept the reality of the situation, however, that the respective companies were partners on the project sharing a common concern. Brown’s and Folkes’ purpose in the transfer to counsel was to secure legal advice from counsel, Schenk, who, it turned out, advised against sending the letter. To hold otherwise would frustrate the purpose behind the attorney-client privilege — to encourage a client to confide in his lawyer and give a full disclosure and secure fully informed legal advice. See Fishery. United States, 425 U.S. 391, 403-404 (1976).

For the foregoing reasons the disclosure of the Brown letter will not be allowed.

[131]*131December 2,1998

BY JUDGE T. J. MARKOW

The court, sitting without a jury, heard the evidence and argument, and received memoranda on the issues joined. At issue is the interpretation of a contract between Westmoreland-LG&E Partners (“WLP”) and Virginia Electric and Power Company in which WLP undertook to construct a power generating plant and to produce electricity for Virginia Power in consideration of two types of payments. The first type (at issue here) are called “dependable capacity” payments. The second are the “energy purchase price.” WLP claims that Virginia Power breached the contract by withholding dependable capacity payments of some fourteen million eight hundred thousand dollars.

The dependable capacity payment is designed to compensate for providing a generating facility available for the delivery of electricity to Virginia Power upon call or “dispatch.” It is designed to cover construction and financing costs, as well as anticipated profits. The dependable capacity payment amounts to about two hundred thousand dollars a day.

The contract anticipates that there will be times when the plant will not be able to produce because of the need for maintenance of the equipment (“scheduled outage days”), for unforeseen impediments to production (“forced outage days”), and for “force majeure” events. There is no dispute that because of allowances in the contract, WLP receives the dependable capacity payments for “scheduled outage days” and nothing for “force majeure” days.

The issue here is whether it receives such payments when it experiences “forced outage days.” Interpretation of section 10.15(d) of the contract determines the answer to that question.

Based upon the decision of the Virginia Supreme Court in an appeal of a prior decision of this court, the purpose of this trial was to hear evidence “concerning the parties’ intent and understanding with respect to Forced Outage Days and capacity payments at the time they executed the contract.” Westmoreland-LG&E Partners v. Virginia Electric & Power Co., 254 Va. 1, 9, 486 S.E. 289, 296 (1997).

At trial, each side presented witnesses who were involved in negotiating the contract and who testified regarding their personal recollections of discussions and their objectives in the negotiations which led to this contract. Because of the lapse of time (the negotiations occurred in late 1988), personal motivations, the fiailty of memories, and the inherent difficulty of attributing the intent of a few to die act of several, this court as fact finder considered and gives some, but little, weight to the testimony of the personal intentions of a [132]*132particular witness or the witnesses collectively. Instead, the focus and greater weight is placed on more objective evidence such as the historical background of the contract, the circumstances surrounding the negotiations, and the language used and its relation to the contract as a whole. Accordingly, this opinion will focus little, if at all, on the testimony of any particular witness.

The analysis begins with the historical context of the contract, the negotiations, and, finally, the executed document.

In early 1988 Virginia Power decided to expand its power production through the use of independent power producers in lieu of building and operating its own plants. Requests for proposals for contracts were sent out in the spring of 1988. WLP responded with a proposal that culminated in this contract.

The original party in the proposal was a partnership comprised of three entities. After the contract was executed, two of the partners withdrew and the contract was amended and restated in 1990 and 1991. As the operative section was unchanged, the court is focusing on that section in the light of the 1988/89 circumstances. While WLP did not exist in 1988, this discussion will treat it as the original contracting party.

WLP’s proposal was based upon its use of “gob” coal, a low cost waste coal product. It proposed a very high dependable capacity payment (about twice that of other producers) and a very low production cost for the electricity produced.

In its request for proposals, Virginia Power included a model contract which formed the basis of the contract in question. It contemplated that dependable capacity payments would be made for “scheduled outage days” and for up to twenty-five “forced outage days.” Beyond these allowances, outages would cost the operator $2.2 million a day in liquidated damages.

In its proposal, WLP attempted to address several concerns. Because of the untried technology it planned to use to bum the gob coal, WLP was unsure that it would meet the twenty-five days per year allowable forced outage limit. It considered the $2.2 million per day liquidated damages excessive. WLP, therefore, wanted more forced outage days for the start-up period to “work the bugs out,” it wanted a higher dependable capacity payment, and it wanted reduced liquidated damages for outages beyond the allowed number.

Virginia Power’s primary objective was to provide incentives for WLP to operate as much as possible because Virginia Power was paying it very high capacity payments and very low production payments.

Neither side was satisfied with the contract until December 20, 1988, when one of WLP’s negotiators proposed the so-called “sliding scale” which found its way into what is now § 10.15(d) of the contract which states:

[133]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. United States
425 U.S. 391 (Supreme Court, 1976)
Westmoreland-Lg & E Partners v. Va. Elec.
486 S.E.2d 289 (Supreme Court of Virginia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
47 Va. Cir. 130, 1998 Va. Cir. LEXIS 287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westmoreland-lge-partners-v-virginia-electric-power-co-vaccrichmondcty-1998.