Westmont Development Group v. Township of Haddon

373 F. App'x 310
CourtCourt of Appeals for the Third Circuit
DecidedApril 13, 2010
Docket09-2885
StatusUnpublished
Cited by1 cases

This text of 373 F. App'x 310 (Westmont Development Group v. Township of Haddon) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westmont Development Group v. Township of Haddon, 373 F. App'x 310 (3d Cir. 2010).

Opinion

OPINION OF THE COURT

DAVIS, District Judge.

Plaintiff Westmont Development Group, LLC appeals the order of the District Court entering summary judgment in favor of Defendants Township of Haddon, Mayor Randall W. Teague, Commissioner John C. Foley, and Commissioner Paul Dougherty pursuant to Federal Rule of Civil Procedure 56. The District Court’s order also entered judgment on Plaintiffs pleadings in favor of Defendant Camden County Improvement Authority pursuant to Federal Rule of Civil Procedure 12(c). We will affirm the District Court’s decision in full.

I. FACTUAL AND PROCEDURAL BACKGROUND

This litigation arises from a failed contract. Westmont Development Group, LLC (“WDG”), a Pennsylvania limited liability company whose principal is Joanna Pang, and the Township of Haddon, a municipality in Camden County, New Jersey, entered into a Redevelopment Agreement on May 26, 2004 (“Agreement”), for the development of a live entertainment venue and other commercial uses at the West-mont Theater, located at 49 Haddon Avenue in Haddon, New Jersey. WDG did not comply with the Agreement and on December 13, 2007, the Township terminated the Agreement.

The Township of Haddon is governed by a Board of Commissioners, one of whom is designated as the Mayor. The Township also has a Planning Board, which is an independent governmental body from the Township. The Camden County Improve *312 ment Authority (“CCIA”) is an entity created by the Camden County Board of Freeholders, which is authorized to assist municipalities with financing public projects.

The Westmont Theater redevelopment pz'ojeet began when the Township and the CCIA entered into a November 1, 1998 Lease-Purchase Agreement for the West-mont Theater property. Under that agreement, the Township transferred title to the Westmont Theater property to the CCIA and in return, the CCIA provided financing to the Township for improvements to the property. The CCIA funded the redevelopment project by issuing $700,000 in bonds. The CCIA leased the property back to the Township, giving the Township physical possession and control of the premises. Since 1998, the CCIA has held title to the Westmont Theater property.

In the May 26, 2004 Agreement between the Township and WDG, the parties agreed that any alteration, amendment, or modification was invalid unless memorialized in writing. They also agreed that failure of either party to insist upon strict perfonnance of any term or obligation under the Agreement was not to be construed as a waiver or relinquishment of any terms or rights under the Agreement.

The Agreement, along with its attached Agreement of Sale, set the contractual parameters for an eventual conveyance of title to the Westmont Theater to WDG. That contemplated conveyance was contingent on consummation of the transaction in the Agreement. Also, WDG was required to obtain preliminary and final site plan approval from the Township before conveyance of title. Termination of the Agreement for any reason would nullify the Agreement of Sale.

The Agreement provided WDG with a sixty day due diligence period, commencing on May 26, 2004, during which period WDG could conduct any inspections or investigations it desired to determine whether it wished to go forward with the Agreement. If a condition was found that was unsatisfactory to WDG in its sole discretion, it was permitted to terminate the Agreement. If WDG did not terminate the Agreement during the due diligence period, WDG was required to prepare and submit to the Township a proposed “Redevelopment Project Plan,” as defined in the Agreement, by September 23, 2004. The Township Commissioners were required to review WDG’s Project Plan within thirty days of receipt. The Commissioners were required to either approve the Project Plan, in which case WDG would proceed with the project, or advise WDG why the plan was inadequate and meet with WDG to resolve any differences.

WDG did not exercise its right to terminate the Agreement during the due diligence period that took place May 26, 2004, through July 25, 2004. Therefore, WDG was contractually required to prepare and submit to the Township a proposed Project Plan by September 23, 2004. WDG did not submit a Project Plan by that deadline or at any time thereafter.

WDG’s failure to timely submit a Project Plan constituted a default under the Agreement. The Township explained the Plan’s inadequacies, but did not place WDG in default. Instead, as the District Court correctly found, “a practice began that would persist throughout the term of the contract — time frames articulated therein were not adhered to, and the Township liberally granted WDG extensions of contractual deadlines.... Those extensions were not memorialized in writing.” Slip op. at 9-10, June 15, 2009 (Ire-nas, J.).

*313 Under the Agreement, WDG was required to first obtain the Township’s approval of WDG’s Project Plan and then obtain the Planning Board’s preliminary site plan approval. Instead, in March 2005, WDG began the process of obtaining the Planning Board’s approval of WDG’s conceptual site plans for the Westmont Theater, without having first submitted a proposed Project Plan to the Township. Over the following months, WDG and its engineers, Bach Associates, P.C., submitted voluminous documents to the Planning Board, including a site plan, a traffic impact study, and drainage calculations. There is no evidence WDG delivered any of these submissions to the Township for consideration by the Commissioners.

Pang appeared before the Planning Board on a number occasions, seeking approval for WDG’s site plan. During Pang’s appearance before the Board on July 7, 2005, the Board expressed concern with WDG’s application primarily because it failed to adequately address parking for the Westmont Theater. WDG never submitted a revised application for site plan approval and never submitted a Project Plan to the Township for review and approval. There is no evidence the Planning Board ever reached a decision on the merits of WDG’s site plan.

From the inception of the Agreement, both WDG and the Township were aware that WDG anticipated a volume of theater patrons that far exceeded the capacity of the theater property’s existing parking lot. Both WDG and the Township were aware that finding a solution to WDG’s parking needs posed a challenge. Pang acknowledged she knew parking was going to be an issue before she signed the Agreement. She also knew parking was the responsibility of WDG, not the Township, under the Agreement.

Pang and her counsel explored a number of possible, but unsuccessful solutions to WDG’s parking needs. They focused their efforts on acquming a neighboring vacant lot, known as the Russell Cast Stone property, to provide parking for the Westmont Theater. The Walters Group, through a related entity, Rose Hill Associates, LLC (“Rose Hill”), owned the Russell property. Rose Hill declined to sell or lease the property to WDG.

WDG anticipated that the Township would take the Russell property by eminent domain for public use, including WDG’s use.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First American Development Group/Carib, LLC v. WestLB AG
55 V.I. 316 (Superior Court of The Virgin Islands, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
373 F. App'x 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westmont-development-group-v-township-of-haddon-ca3-2010.