Westfield, LLC v. IPC, Inc.

816 F. Supp. 2d 745, 2011 U.S. Dist. LEXIS 100924, 2011 WL 4008117
CourtDistrict Court, E.D. Missouri
DecidedSeptember 8, 2011
DocketCase No. 4:11CV00155 JCH
StatusPublished
Cited by3 cases

This text of 816 F. Supp. 2d 745 (Westfield, LLC v. IPC, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westfield, LLC v. IPC, Inc., 816 F. Supp. 2d 745, 2011 U.S. Dist. LEXIS 100924, 2011 WL 4008117 (E.D. Mo. 2011).

Opinion

MEMORANDUM AND ORDER

JEAN C. HAMILTON, District Judge.

This matter is before the Court on Defendant Consulting Engineers Group, Inc.’s Motion to Dismiss (ECF No. 21) and Defendant IPC, Inc.’s Motion to Dismiss (ECF No. 29). These matters are fully briefed and ready for disposition.

BACKGROUND

Plaintiff Westfield, LLC (“Westfield”) was the property manager and contractor for the shopping center construction for the mall and parking garage structures for West County Center mall in Des Peres, Missouri (the “Project”). (Petition (“Pet.”), ECF No. 6, ¶¶ 1,11,12). Plaintiff West County Center, LLC (“WCC”) was the owner of the Project. (Pet., ¶ 2). Part of the Project included building multiple parking structures. (Pet., ¶ 13). On June 24, 2000, Westfield entered into a design-build Standard Construction Subcontract with Raider Precast Concrete, Inc. (“Raider”) to design and build three precast parking structures for the Project (the [747]*747“Subcontract”). (Pet., ¶¶ 14, 15).1 Raider entered into a sub-subcontract with Consulting Engineers Group, Inc. (“CEG”), an engineering and design firm, under which CEG was to provide design drawings for the parking structures Raider contracted to design, fabricate and erect pursuant to the Subcontract. (Pet., ¶ 17). CEG designed the parking structures and the parking structures were constructed from 2000-2002 based upon the design drawings prepared by CEG for Raider. (Pet., ¶ 20).

In November 2006, WCC noticed concrete cracking, movement and water intrusion in the parking structures. (Pet., ¶ 22). In May 2007, Plaintiffs learned that the parking structures had multiple defects resulting from the poor workmanship and design flaws of Raider and CEG. (Pet., ¶ 23). CEG designed a fix for the problems and throughout 2008 and 2009 extensive structural remediation was required to address the design failures in the parking structures. (Pet., ¶¶ 25-26). Plaintiffs allege that the design and construction of the parking structures failed to meet industry standards and they incurred significant costs to repair the defects, in addition to outside engineering consulting fees. (Pet., ¶¶ 27-35).

In December 2010, Plaintiffs filed this Petition in the Circuit Court of St. Louis County, State of Missouri. Plaintiffs alleged causes of action for Breach of Contract against IPC (Count I), Negligence against IPC (Count II), and Professional Negligence against CEG (Count III). On January 21, 2011, CEG removed the case to this Court based upon diversity jurisdiction, 28 U.S.C. § 1332(a). (ECF No. 1). On March 7, 2011, CEG filed a motion to dismiss, and, on March 31, 2011, IPC filed a motion to dismiss.

STANDARD FOR MOTION TO DISMISS

In ruling on a motion to dismiss, the Court must view the allegations in the complaint liberally in the light most favorable to Plaintiff. Eckert v. Titan Tire Corp., 514 F.3d 801, 806 (8th Cir.2008) (citing Luney v. SGS Auto. Servs., 432 F.3d 866, 867 (8th Cir.2005)). Additionally, the Court “must accept the allegations contained in the complaint as true and draw all reasonable inferences in favor of the nonmoving party.” Coons v. Mineta, 410 F.3d 1036, 1039 (8th Cir.2005) (citation omitted). To survive a motion to dismiss, a complaint must contain “enough facts to state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007) (abrogating the “no set of facts” standard for Fed.R.Civ.P. 12(b)(6) found in Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)). While a complaint attacked by a Rule 12(b)(6) motion to dismiss does not need detailed factual allegations, a plaintiffs obligation to provide the grounds of his entitlement to relief “requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Twombly, 550 U.S. at 555, 127 S.Ct. 1955; Huang v. Gateway Hotel Holdings, 520 F.Supp.2d 1137, 1140 (E.D.Mo.2007).

[748]*748 DISCUSSION

1. Consulting Engineers Group, Inc.’s Motion to Dismiss2

A. Statute of Limitations

CEG claims that Plaintiffs’ cause of action for negligence against CEG is barred by the five (5) year statute of limitations for actions where damages are capable of ascertainment but the precise amount of damage is not known. See Mo.Rev.Stat. § 516.100.3 CEG asserts that the parking structures were completed in 2002, and the petition does not allege that the defects were hidden. (Memorandum, p. 3). Rather, CEG claims that Plaintiffs only allege “significant changes” four (4) years after CEG completed work on the Project. (Id.). Therefore, CEG claims that the fact of damages was capable of ascertainment before November 2006 and this lawsuit is barred by the statute of limitations. (Id.).

The Court finds that Plaintiffs’ negligence claims is not barred by the statute of limitations. Plaintiffs allege that the defects were “latent” and only became “visible” in November 2006. (Pet., ¶¶ 21-22). Therefore, at this stage of litigation, the Court finds that Plaintiffs’ Petition does not allege that the fact of damages was capable of ascertainment prior to the expiration of the statute of limitations period. State ex rel. Marianist Province of the United States v. Ross, 258 S.W.3d 809, 811 (Mo.2008) (“The capable of ascertainment standard is an objective one; therefore, when relevant facts are uncontested, the statute of limitations issue can be decided by the court as a matter of law.”). The Court denies CEG’s motion to dismiss on this basis.

B. Acceptance Doctrine

CEG next argues that Plaintiffs’ claims are barred by the acceptance doctrine, “which relieves contractors of liability to those not parties to the contract after the owner accepts the contractor’s work.” Fisher v. State Highway Comm’n, 948 S.W.2d 607, 611 (Mo.1997) (citing Gast v. Shell Oil Co., 819 S.W.2d 367, 370 (Mo. banc 1991)); Rogers v. Frank C. Mitchell Co., 908 S.W.2d 387, 388 (Mo.Ct.App.1995); Gruhalla v. George Moeller Construction Co., 391 S.W.2d 585, 597 (Mo.Ct.App.1965). “In the absence of formal acceptance, constructive or practical acceptance will suffice.” Roskowske v. Iron Mountain Forge Corp., 897 S.W.2d 67, 71 (Mo.Ct.App.1995) (citing Gruhalla v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
816 F. Supp. 2d 745, 2011 U.S. Dist. LEXIS 100924, 2011 WL 4008117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westfield-llc-v-ipc-inc-moed-2011.