Western Watersheds Project v. Steve Ellis

697 F.3d 1133, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20205, 2012 WL 4784207, 2012 U.S. App. LEXIS 20918
Court of Appeals for the Ninth Circuit·Decided October 9, 2012·No. 11-35464·Published

Opinion

OPINION

SCHROEDER, Circuit Judge:

This appeal involves an attorneys’ fee dispute that added a rancorous coda to long-running grazing permit litigation in Idaho that was all ably overseen by the district court. The plaintiff, Western Watersheds Project (“WWP”), originally filed this action in 2004 challenging the Bureau of Land Management’s (“BLM”) renewal of grazing permits in the Jarbidge Resource Area (“JRA”), covering a large expanse of Southern Idaho. In 2005, the district court ruled in a published opinion that WWP’s challenge had merit and that the BLM had violated federal statutes by inadequately protecting habitat of threatened, endangered, or sensitive species. See Western Watersheds Project v. Bennett (WWP I), 392 F.Supp.2d 1217, 1227-29 (D.Idaho 2005).

The parties in 2006 entered into what they thought was a settlement of the en *1135 tire dispute, but in July of 2007 a massive fire changed the situation dramatically. The BLM then allowed grazing on unburned areas to continue, and after taking several months to regroup, began issuing new grazing authorizations. WWP successfully challenged the post-fire grazing decisions and authorizations as inadequately protecting wildlife habitat, but the district court denied WWP’s claim for fees, and this appeal followed. The issue before us is thus whether the district court erred in denying plaintiff WWP fees under the Equal Access to Justice Act (“EAJA”), 28 U.S.C. § 2412(d)(1)(A).

WWP’s position is that the district court considered only the reasonableness of the underlying agency decision to issue grazing authorizations after the fire, and did not adequately consider the reasonableness of the litigation strategy defending that decision. Our review of the record convinces us that the district court did consider both factors, and we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

The background of the dispute is more fully explained in the district court’s 2005 opinion. WWP I, 392 F.Supp.2d at 1220-1222. The BLM has divided the public lands it manages into administrative segments it calls Resource Areas. See 43 C.F.R. § 1601.0-5. Each Resource Area is required to have a Resource Management Plan (“RMP”). See 43 U.S.C. §§ 1701-84; see also 43 C.F.R. § 1610.1(b). The BLM has managed the Jarbidge Resource Area, an area of approximately 1.7 million acres of land in Southern Idaho, pursuant to the RMP completed in 1987. A key issue in managing the JRA has been preventing further environmental deterioration caused by excessive grazing. A related concern has been damage to the habitat for listed species and candidates for listing under environmental statutes like the Endangered Species Act. Of particular concern have been the habitats for the sage grouse and pygmy rabbit, species whose numbers have dramatically declined during the last century.

In 2004, WWP challenged the BLM’s renewal of grazing permits for 28 of the allotments managed under the 1987 plan. WWP contended that the permits conflicted with the RMP’s provisions to protect wildlife habitat. The BLM responded that such provisions were aspirational rather than mandatory. The district court ruled otherwise, holding that the provisions spoke “in terms of requirements, not suggestions.” WWP I, 392 F.Supp.2d at 1227. The district court enjoined grazing on the challenged allotments pending the BLM’s completion of a new environmental analysis. These rulings are not at issue here.

The 2005 rulings resulted in the parties forming their Settlement Agreement. It established interim grazing restrictions that were to apply during the time frame the Agreement set for the BLM to complete a new RMP for the Jarbidge Area, together with a supporting Environmental Impact Statement. The Settlement Agreement also contemplated that the new RMP would be completed in 2009. The Settlement Agreement resolved all of the issues concerning attorneys’ fees and costs up through that stage of the litigation.

All these well-laid plans were frustrated, however, when a massive wildfire, termed by the district court “catastrophic,” swept through the area in 2007. The fire, known as the Murphy Complex Fire, burned more than 400,000 acres, destroying most of the known pygmy rabbit habitat and sage grouse nesting habitat. It also destroyed much of the grazing land.

In early 2008 the BLM began issuing authorizations for grazing on the unburned *1136 areas. The fire’s habitat destruction and the new grazing authorizations caused WWP to file a motion to reopen the litigation in order to seek an injunction against grazing on many of the remaining unburned allotments. Although the district court declined to alter the permits covered by the Agreement, it ruled in favor of WWP with respect to the remaining allotments. The district court held that the government had to reduce the grazing in the unburned areas to provide needed wildlife habitat. The court observed, however, that the government would act in good faith to reduce grazing and therefore denied as unnecessary WWP’s request for a formal injunction against all grazing pending the required reexamination of the grazing authorizations.

None of those 2009 district court rulings are at issue in this appeal. What is at issue is WWP’s subsequent motion for attorneys’ fees as the prevailing party. Under the EAJA, a prevailing party is generally entitled to fees against the government unless the position of the government was substantially justified. 28 U.S.C. § 2412(d)(1)(A); see Gonzales v. Free Speech Coalition, 408 F.3d 613, 618 (9th Cir.2005). The district court denied WWP attorneys’ fees and WWP appeals, contending the district court ignored one of the factors it was required to consider in determining whether the government’s position in this case was substantially justified.

DISCUSSION

In an action brought by or against the United States, the EAJA requires the court to award fees and costs to the “prevailing party other than the United States ... unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust.” 28 U.S.C. § 2412(d)(1)(A). In determining whether the position of the United States was substantially justified under the EAJA, a court must look “both to the government’s position during litigation and to ‘the action or failure to act by the agency upon which the civil action is based.’ ” United States v. Marolf, 277 F.3d 1156, 1161 (9th Cir.2002) (quoting 28 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Western Watersheds Project v. Steve Ellis, 697 F.3d 1133, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20205, 2012 WL 4784207, 2012 U.S. App. LEXIS 20918 (9th Cir. 2012).

697 F.3d 1133 (Western Watersheds Project v. Steve Ellis) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related