Western Technologies, Inc. v. All-American Golf Center, Inc.

139 P.3d 858, 122 Nev. 869, 122 Nev. Adv. Rep. 77, 2006 Nev. LEXIS 101
CourtNevada Supreme Court
DecidedAugust 17, 2006
DocketNo. 41930
StatusPublished
Cited by6 cases

This text of 139 P.3d 858 (Western Technologies, Inc. v. All-American Golf Center, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Technologies, Inc. v. All-American Golf Center, Inc., 139 P.3d 858, 122 Nev. 869, 122 Nev. Adv. Rep. 77, 2006 Nev. LEXIS 101 (Neb. 2006).

Opinion

OPINION

By the Court,

Hardesty, J.:

In this appeal, we decide whether a party against whom a judgment is rendered in a breach of contract and warranty action may offset that judgment by the amount the prevailing party obtained in a settlement with other parties. We conclude that Nevada decisional law, the Uniform Joint Obligations Act (UJOA)1 and the Restatement (Second) of Contracts2 provide a basis for an offset when no express agreement exists for offset, indemnification, or contribution.

FACTS AND PROCEDURAL HISTORY

Respondent All-American Golf Center, Inc. (AA), constructed Calloway Golf Center’s nine-hole golf course in Las Vegas. AA hired Bentar Development, Inc., as the general contractor, Swisher [871]*871& Hall as the architect, and appellant Western Technologies, Inc. (WT), as the project’s engineer and soil tester.

When the construction was completed, it became apparent that several constructional defects existed. Primarily, the retaining wall for the upper deck tee line of the golf center’s driving range was defective. In addition, poorly compacted soil behind the retaining wall caused soil subsidence, which resulted in excessive cracking along the retaining wall.

AA brought suit against Bentar, Swisher & Hall, and WT for breach of contract, breach of express warranty, negligence, and unjust enrichment for the constructional defects. Bentar joined other third-party defendants, alleging various theories of liability, contribution, and indemnification. Before trial, Bentar, Swisher & Hall, and all third-party defendants reached a settlement with AA in the amount of $880,000. Subsequently, the district court granted the settling parties’ motion for a determination of a good-faith settlement under NRS 17.245. The parties did not, however, request the district court to allocate the settlement amount among the various constructional defects.

Following the district court’s good-faith determination and approval of the settlement, AA withdrew its causes of action for negligence and unjust enrichment and proceeded to trial against WT on its breach of contract and breach of warranty claims concerning the defective retaining wall only. During pretrial hearings, the parties and the district court agreed that AA could present evidence of all damages it sustained as a result of the defective retaining wall, the jury should not apportion damages between WT and the settling defendants, and the jury could hear evidence of actions by the settling defendants concerning the retaining wall but would only decide WT’s liability. No evidence of the settlement, however, could be introduced at trial. At trial, the parties presented evidence of the settling parties’ conduct with respect to the retaining wall, and AA presented its damages in excess of $3,000,000, which included costs to repair the retaining wall, loss of the facility’s use caused by the defective wall, and lost profits during the retaining wall’s repair. WT contested the amount of each damage claim.

At the close of trial, the jury was instructed on the elements of AA’s claims for breach of express warranty and breach of contract. The jury was instructed to determine WT’s liability only. On the issue of damages, the jury was instructed that if it found that WT had breached the contract, it could award AA damages for its cost of repair, loss of use, and lost profits.3 There was, however, no instruction limiting the award of damages to just those amounts [872]*872caused by WT. The parties and district court agreed to a special verdict form that required the jury to specify, in the event it found liability, AA’s damages for its costs to repair, loss of use of the facility, and lost profits.

The jury found for WT on AA’s breach of contract claim but found WT liable for breach of the express warranty. Accordingly, the jury awarded AA damages of $350,000 for the cost to repair, $250,000 for the loss of the facility’s use, and $60,000 for lost profits during the repair period, for total damages of $660,000.

Thereafter, WT moved to offset the $660,000 jury verdict by AA’s $880,000 settlement with the other defendants. WT argued that AA presented its total retaining wall damages to the jury, while pointing out that no apportionment was allowed. As a result, WT asserted, instructing the jury to determine its liability did not result in an apportionment of damages attributable to WT. Thus, WT maintained that an offset was warranted.

The district court found that the jury was instructed to determine only WT’s liability and that the settlement, when added to the amount of the jury award, was consistent with the total amount of damages alleged by AA. The district court entered an amended judgment on the jury award of $660,000, denying WT’s motion for offset and awarding attorney fees, costs and prejudgment interest to AA as the prevailing party. This appeal, challenging the offset denial, followed.

DISCUSSION

The question of whether a party, in a contract action, is entitled to have amounts from codefendants’ and other third parties’ settlements with the plaintiff deducted from a jury verdict for total damages levied against it is one of first impression for this court. We conclude that, based on Nevada decisional law, the UJOA, and theories described in section 294(3) of the Restatement (Second) of Contracts, the offset rule may be applied in contract actions.

First, Nevada decisional law has acknowledged that the offset rule is an equitable remedy4 based on policies rooted in contract principles. In Greco v. United States,5 this court explained that the offset rule has origins in the “expectancy rule” of damages in contract law. The purpose behind the expectancy rule is ‘ ‘to place the plaintiff in the position he or she would have been in had the contract been performed,”6 which in turn prevents double recovery.7 [873]*873The offset of a jury award of total damages by a settlement amount with other parties serves to prevent excess recovery by the plaintiff.

Second, a provision of the UJOA, NRS 101.040, deals with payments credited to co-obligors in situations where joint obligations exist, providing:8

The amount or value of any consideration received by the obligee from one or more of several obligors, or from one or more of joint, or of joint and several obligors, in whole or in partial satisfaction of their obligations, shall be credited to the extent of the amount received on the obligations of all coobligors to whom the obligor or obligors giving the consideration did not stand in the relation of a surety.

Questions of statutory construction are reviewed de novo.9 The language of this particular section does not expressly state whether it applies in tort, in contract, or in both. When analyzing an ambiguous statute, the court should “read [it] as a whole to give meaning to all of its parts.”10 NRS 101.020

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
139 P.3d 858, 122 Nev. 869, 122 Nev. Adv. Rep. 77, 2006 Nev. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-technologies-inc-v-all-american-golf-center-inc-nev-2006.