Western Surety Company v. Regions Bank

495 F. App'x 627
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 20, 2012
Docket11-6102
StatusUnpublished

This text of 495 F. App'x 627 (Western Surety Company v. Regions Bank) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Surety Company v. Regions Bank, 495 F. App'x 627 (6th Cir. 2012).

Opinion

GRIFFIN, Circuit Judge.

This appeal originated in an adversary proceeding in bankruptcy court brought by appellant Western Surety Company (“Western Surety”) against appellee Regions Bank (“the Bank”) for breach of contract. Western Surety appeals the district court’s affirmance of the summary judgment entered by the bankruptcy court in favor of Regions Bank. For the reasons set forth below, we affirm.

I.

In May 2005, the debtor, McKenzie Financial Center, LLC (“McKenzie”), entered into a contract with C & I Specialty Co., Inc. (“C & I”), a general contractor, to construct an office building in Cleveland, Tennessee. Western Surety issued performance bonds to guarantee C & I’s obligations under the construction contract. In September 2005, McKenzie contracted with Regions Bank’s predecessor-in-interest, Am South Bank, to finance the construction. Pursuant to the financing contract, Regions Bank loaned McKenzie over $4.6 million. McKenzie executed a promissory note in favor of the Bank, which was secured by a deed of trust to the real estate on which the office building was being built.

The financing contract set forth numerous conditions precedent to the disbursal of the loan proceeds and advances to McKenzie. Section 8.19 of the financing contract provided:

Liens; Setoff by Bank. Borrower hereby grants to the Bank a continuing lien, as security for the Note and all other indebtedness of the Borrower to the Bank, upon any and all of its moneys, securities and other property and the proceeds thereof, now or hereafter held or received by or in transit to, the Bank from or for the Borrower, and also upon any and all deposits (general or special, matured or unmatured, including, but not limited to, the construction checking account with the Bank for this Loan) and credits of the Borrower against the Bank, at any time existing. Upon the occurrence of any Event of Default as specified above, the Bank is hereby authorized at any time and from time to time, without notice to Borrower, to set off, appropriate, and apply any and all items hereinabove referred to against any or all indebtedness of the Borrower to the Bank.

*629 The financing agreement also required that “[a] retainage equal to ten percent (10%) of Construction Costs shall be deducted from each advance after the first Loan advance (the ‘Retainage’),” and further, that “[n]o Retainage funds shall be disbursed until all the conditions specified in Section B.B have been satisfied.” The three conditions listed in Section 3.3 called for evidence of the proper filing of a notice of completion, evidence that no notice of lien had been filed or received within thirty days after the filing of the notice of completion, and the production of “such other reasonable documents and items requested by the Bank.” In addition, Section 8.4 of the financing agreement provided:

Provisions for Exclusive Benefit of Bank. All conditions to the obligations of Bank to make disbursements hereunder are imposed solely and exclusively for the benefit of Bank, and its successors and assigns. No other person shall have standing to require satisfaction of such conditions in accordance with their terms or be entitled to assume that Bank will refuse to make advances in the absence of strict compliance with any or all of such terms and conditions. No other person shall, under any circumstances, be deemed to be a beneficiary of such conditions, any or all of which may be freely waived in whole or in part by Bank at any time if, in its sole discretion, it deems it advisable to do so.

With the financing contract in place, construction commenced and continued over a period of approximately two years, during which time the Bank disbursed the loan proceeds requested by McKenzie and increased the principal balance of the loan pursuant to the parties’ execution of a loan modification agreement. As the building neared completion, McKenzie exhausted its line of credit with the Bank, defaulted on the loan, and failed to satisfy the conditions precedent to disbursement of the re-tainage. As a result, the Bank exercised its contractual set-off rights and denied McKenzie’s final draw request to release the funds owed to C & I for its 100% completion of the construction project. The Bank offset McKenzie’s remaining line of credit under the financing contract, in the amount of $499,027.64, against McKenzie’s obligation to repay the Bank the principal amount of the construction loan.

Western Surety, as C & I’s assignee, obtained a state-court judgment against McKenzie in the amount of $575,228.02, the unpaid balance of the construction costs, but McKenzie filed for Chapter 7 liquidation bankruptcy relief. In the bankruptcy case, the Bank submitted an uncontested and secured proof of claim against the construction-site real property, asserting its deed of trust as a first-priority lien. Western Surety then initiated this adversary proceeding against the Bank for breach of contract. It asserted, inter alia, that as C & I’s assignee, it was a third-party beneficiary of the financing contract and was entitled to payment of the retain-age held by the Bank. And, although the financing contract itself did not require that the retainage be escrowed for the benefit of C & I or other subcontractors and laborers, Western Surety argued that TenmCode Ann. § 66-ll-144(a) (2004), which, during the relevant time period, imposed such an escrow requirement “in any contract for the improvement of real property” where “a certain amount or percentage of the contract price is held back by the owner or contractor,” should apply to the Bank’s retainage for public policy reasons. 1

*630 On the parties’ cross-motions for summary judgment, the bankruptcy court granted the Bank’s motion and denied Western Surety’s motion. See In re McKenzie Fin. Ctr. LLC, 53 Bankr.Ct. Dec. 285, 2010 WL 4670060 (Bankr. E.D.Tenn. Nov. 9, 2010) (unpublished). Noting Western Surety’s concession that McKenzie had not complied with the conditions precedent to final disbursement of the loan proceeds, the court held that the Bank was not contractually obligated to release the retainage because of the nonperformance and defaults of McKenzie, and that Western Surety, as an asserted third-party beneficiary, succeeded to no greater rights than McKenzie under the contract. The bankruptcy court further held that the Bank was not subject to the escrow requirements of Tenn.Code Ann. § 66-ll-144(a), because it was not an “owner” to whom the statute applied. See Tenn.Code Ann. § 66-11-101(11).

Western Surety appealed the bankruptcy court’s ruling to the district court, which affirmed the summary judgment in favor of the Bank. See Western Surety Co. v. Regions Bank, No. 1:10-cv339, 2011 WL 3516132 (E.D.Tenn. Aug. 11, 2011) (unpublished).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herrera v. Churchill McGee, LLC
680 F.3d 539 (Sixth Circuit, 2012)
United States v. Brent Vreeland
684 F.3d 653 (Sixth Circuit, 2012)
June Morris v. General Brown
489 F. App'x 890 (Sixth Circuit, 2012)
Reagan v. Higgins
88 S.W.3d 173 (Court of Appeals of Tennessee, 2002)
Goodner v. Lawson
232 S.W.2d 587 (Court of Appeals of Tennessee, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
495 F. App'x 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-surety-company-v-regions-bank-ca6-2012.