Western Surety Co. v. City of Devils Lake

58 F.2d 161, 1932 U.S. App. LEXIS 4666
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 11, 1932
DocketNo. 9332
StatusPublished
Cited by1 cases

This text of 58 F.2d 161 (Western Surety Co. v. City of Devils Lake) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Surety Co. v. City of Devils Lake, 58 F.2d 161, 1932 U.S. App. LEXIS 4666 (8th Cir. 1932).

Opinion

KENYON, Circuit Judge.

This is an appeal from a judgment of $17,220 against the Western Surety Company, appellant, surety on a bond to protect appellee under a contract made with one J. J. Larson to construct a well for the city of Devils Lake, a municipal corporation of North Dakota. The facts necessary to an understanding of the case are as follows:

March 16, 1927, pursuant to a proposal made to the city of Devils Lake, by said Larson to construct a well for said city in accordance with plans and specifications prepared by Toltz, King & Day, Inc., engineers and architects,' a contract was entered into between Larson, as contractor, and said city for the construction of said well. The specifications provided for a well some 1,500 feet deep to be delivered to the city clean and clear for the installation of pumping equipment and to be completed by July 1,1927.

Larson for the performance of the contract was to receive $17,220.

The diameter, as provided by the contract, which decreased as the depth of the well increased, was:

Top 100 ft.—16 inch O. D. casing Next 200 ft.—13 inch O. D. casing Next 1140 ft.—10 inch I. D. casing Next 40 ft.— 8 inch I. D. Perforated Pipe.

At the bottom, and forming a part of the casing, there was to be a screen 69 feet and 10 inches in length which went into the strata known as Dakota sandstone.

Larson commenced work on the project in March, 1927. A test well was first dug showing an abundance of water at the place selected to dig the well. There seems to have been no serious trouble with placing the cas[162]*162ing for about 1,460 feet, but, in connecting the screen, trouble commenced and from that time on continued. Tools were lost in the well and difficulty in extracting them ensued; obstructions were met with in drilling, and many difficulties experienced, which delayed finishing- the well, and the work continued under Larson until the spring of 1928, when he quit the same. The flow of the water was not satisfactory to the engineer because there was not a clear and free flow thereof. It was impeded by sand and mud. In March, 1929, one Caimcross, an experienced well digger, was employed by the board of city commissioners of the city of Devils Lake, under an agreement with Larson, to direct the completion of- the well, and authority was given Caimcross to gravel pack the well, if necessary, at an expense of $800 additional to Larson’s contract, to be paid from funds which might be due Larson upon completion of his contract. Caimcross testified as to the work he had done, claiming that satisfactory results were achieved, that the job was a good one as far as the drilling and the construction of the well was concerned, that at times he was pumping nearly a thousand gallons a minute. Matters ran on, there was much correspondence between King, the engineer in charge, and Larson, much complaint was made, and finally, about June 13, 1929, the engineer under section 59 of general conditions of the contract issued a certificate as follows:

“Devils Lake City Commission, Devils Lake, North Dakota.
“Gentlemen:—We "hereby certify that J. J. Larson has failed to complete his contract and that sufficient cause exists for the cancellation of the contract, as provided for in paragraph 59 of the specifications, page G— 10. We recommend that the City of Devils Lake shall serve written notice to J. J. Larson, as therein provided, that this contract is terminated and that the city thereupon proceed to complete the contract by other means. Toltz, King and Day, Inc.”

The following notice was sent to Larson and appellant by the city attorney of Devils Lake: “You and each of you will take notice that the City of Devils Lake, North Dakota, upon the expiration of seven days from the date hereof will terminate the employment of J. J. Larson, as contractor for the construction of a well at Devils Lake, North Dakota, under a contract dated March 6th, 1927, take possession of the premises and finish the work by whatever means the city may deem expedient.”

Thereafter the city, upon recommendation of King, retained the McCarthy Well Company of Minneapolis to work on the well. They commenced September 4, 1929, and worked until October 28,1929, when the project was abandoned.

King testified that the well did not meet the requirements of the contract because of the sand in the water and the inadequate flowage. At the close of the testimony defendant (appellant) moved for a directed verdict which was denied, and the court submitted the case to the jury under instructions hereafter discussed. The jury found for appellee for. the full amount of the bond.

Three points raised by assignments of error are argued by appellant: (1) Error of the court in not instructing a verdict for appellant at the close of the evidence; (2) error in the instructions of the court as to the measure of damages; (3) error in overruling objections to certain evidence.

Our conclusion as to error in the instructions of the court makes unnecessary the consideration of the question raised as to error in not directing a verdict.

As to the objections to questions asked the witness Bennett, and as to the motion to strike parts of his evidence, we may say that in our judgment the court’s rulings were correct. '

We therefore limit our consideration to the court’s instructions as to damages recoverable.

The complaint alleges a general breach of the contract as follows:

“V. That the said J. J. Larson has failed to perform the terms and conditions of said contract by him to be performed and has failed to deliver to the plaintiff the well provided for in said contract, and has abandoned the contract.”

No effort was made to make the complaint more specific.

The parties went to trial on this rather broad allegation. The court, referring to this in its instructions, said: “In its complaint the plaintiff alleges, rather in a general way, that Larson failed entirely to complete the well according to the specifications and abandoned the same. It does not set out in particular the manner of breach of his contract but in this trial the plaintiff claims that the contract was breached in four different ways; first, that the contractor, Larson, has failed to deliver to the City a well that would deliver the quantity of water it claimed he agreed to do in the contract, some [163]*163five hundred gallons per minute; second that he breached the contract in that he failed to deliver to the City a well that would deliver the quality of water it is claimed the contract provided, namely, clear water; and, third, that he breached the contract in that he failed to construct a well in accordance with the specifications, particularly with reference to a clear, clean, unobstructed hole from the top to the bottom; and lastly, for the first time to day in the trial of the case it claims a further breach in the neglect of the contractor to install the kind of screen provided for in the contract, namely, a closed screen at the bottom.”

The Court told the jury that the question of the quantity and quality of the water was not for them, and that the court had decided that Larson did not agree in the contract to furnish any particular quantity or quality of water, and that these claims of alleged breaches of the contract were out of the ease.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andriola v. Milligan
191 P.2d 716 (New Mexico Supreme Court, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
58 F.2d 161, 1932 U.S. App. LEXIS 4666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-surety-co-v-city-of-devils-lake-ca8-1932.