Western States Construction Company, Inc., a Wyoming Corporation, Counter-Defendant v. The Boeing Company, a Delaware Corporation, Counterclaimant, Western States Construction Company, Inc., a Wyoming Corporation, Counter-Claim v. The Boeing Company, a Delaware Corporation, Counterclaimant

28 F.3d 114
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 8, 1994
Docket93-1073
StatusPublished

This text of 28 F.3d 114 (Western States Construction Company, Inc., a Wyoming Corporation, Counter-Defendant v. The Boeing Company, a Delaware Corporation, Counterclaimant, Western States Construction Company, Inc., a Wyoming Corporation, Counter-Claim v. The Boeing Company, a Delaware Corporation, Counterclaimant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western States Construction Company, Inc., a Wyoming Corporation, Counter-Defendant v. The Boeing Company, a Delaware Corporation, Counterclaimant, Western States Construction Company, Inc., a Wyoming Corporation, Counter-Claim v. The Boeing Company, a Delaware Corporation, Counterclaimant, 28 F.3d 114 (10th Cir. 1994).

Opinion

28 F.3d 114

NOTICE: Although citation of unpublished opinions remains unfavored, unpublished opinions may now be cited if the opinion has persuasive value on a material issue, and a copy is attached to the citing document or, if cited in oral argument, copies are furnished to the Court and all parties. See General Order of November 29, 1993, suspending 10th Cir. Rule 36.3 until December 31, 1995, or further order.

WESTERN STATES CONSTRUCTION COMPANY, INC., a Wyoming
corporation, Plaintiff, Counter-Defendant, Appellant,
v.
The BOEING COMPANY, a Delaware corporation, Defendant,
Counterclaimant, Appellee.
WESTERN STATES CONSTRUCTION COMPANY, INC., a Wyoming
corporation, Plaintiff, Counter-Claim Defendant, Appellee,
v.
The BOEING COMPANY, a Delaware corporation, Defendant
Counterclaimant, Appellant.

Nos. 93-1073, 93-1092.

United States Court of Appeals, Tenth Circuit.

July 8, 1994.

ORDER AND JUDGMENT*

Before KELLY and SETH, Circuit Judges and OWEN, District Judge**.

Appellant Western States Construction Company ("Western") commenced an action in the United States District Court for the District of Colorado seeking recovery of amounts due as a result of a contract termination and of other liquidated amounts allegedly due from Appellee The Boeing Company ("Boeing"). Boeing counterclaimed for monies allegedly owed by Western for the sale of certain equipment by Western. At the conclusion of the trial, the district court entered judgment in favor of Boeing in the amount of approximately $240,000.00. Western appeals, and Boeing cross-appeals.

In 1986 Western and Boeing entered into a "Teaming Agreement" under which they jointly developed an overall bid to be submitted to the United States Air Force for a project known as the Hardened Intersite Cable System, Phase II ("HICS II"). This project involved the excavation and reconditioning of the Air Force's underground electronic cable systems at six minuteman missile launch facilities, which were designated as Wings I-VI. According to the Teaming Agreement, Boeing was the general contractor, and Western was a subcontractor responsible for the excavation and backfill portions of the project.

After the Teaming Agreement was accepted by the Air Force, Boeing and Western entered into a formal subcontract. This was subsequently amended on January 14, 1988 by a Memorandum of Agreement ("MOA") which is the subject of this lawsuit. The MOA established a phased construction plan with projections that Wings II and III ("Basic Work") would be completed in 1988; Wings I and VI ("Option 1") would be completed in 1989, if Option 1 were activated by Boeing; and Wings IV and V ("Option 2") would be completed in 1990, if Option 2 were activated by Boeing.

It was understood by the parties that during construction Western would purchase equipment, e.g. backhoes, vehicles and rolling stock ("Vehicles"), for the particular phase of the project. Once that phase was completed, Western would move the Vehicles to the next site and combine them with newly acquired Vehicles for use in the next phase of construction. At all times Western held title to and insured the various Vehicles. After Western purchased a Vehicle, it would submit a request to Boeing for reimbursement. It appears that the amount of reimbursement had been previously negotiated as a fixed amount depending on the type of Vehicle purchased, regardless of the Vehicle's actual price.

Upon completion of the work detailed in the MOA, Boeing was entitled to a fixed credit of approximately $1.5 million for the money it had provided to Western for the purchase of the Vehicles. This credit was calculated by assessing a residual value to each type of Vehicle and summing together the residual values for all of the Vehicles that Western anticipated buying during the entire course of the project. Unfortunately, HICS II was not completed because the Air Force terminated the contract after Western had completed the first five Wings but before Western began excavating the last Wing of Option 2. As a consequence Boeing terminated the MOA for convenience which directly led to the primary dispute before this court: what is the precise credit owed to Boeing for the Vehicles purchased by Western?

For our purposes, the pertinent provisions of the subcontract and MOA are the Special Agreement on Vehicles ("Special Agreement") and sections 49.2 and 49.7 of the General Terms and Conditions. The Special Agreement on Vehicles provides:

"It is understood and agreed that the price of this subcontract includes an amount for Subcontractor's (Western States Construction) purchase of vehicles which will be used in performing this subcontract at Minuteman Operation Wings. At the conclusion of the subcontract, title shall vest in the Subcontractor. The Subcontract Price also includes recognition of a credit amount which takes into consideration Subcontractor's intent to sell the vehicles upon conclusion of their use on this subcontract.

"No further contractual action will be required as the resale amount due to Boeing has already been considered in the firm subcontract price in Option II, providing all options are activated. Should Options I and II not be activated, the credit will be subject to re-negotiation."

Section 49.2 provides in relevant part:

"After receipt of a Notice of Termination and except as otherwise directed by Boeing, Contractor [Western] shall:

....

"(f) transfer title and deliver to Boeing or the Government, in the manner, at the time and to the extent, if any, directed by Boeing, (1) the fabricated or unfabricated parts, work in process, completed work, supplies and other material produced as a part of, or acquired in connection with the performance of, the work terminated by the Notice of Termination ...;

"(g) use his best efforts to sell, in the manner, at the times, to the extent and at the price or prices directed or authorized by Boeing, any property of the types referred to in (f) above; provided, however, that Contractor (1) shall not be required to extend credit to any purchaser, and (2) may acquire any such property under the conditions prescribed and at a price or prices approved by Boeing, and provided further that the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by Boeing to Contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as Boeing may direct...."

Section 49.7 states:

"In arriving at the amount due Contractor [Western] under this clause there shall be deducted (a) all unliquidated advance or other payments on account theretofore made to Contractor, applicable to the terminated portion of this contract (b) any claim which Boeing may have against Contractor in connection with this contract and (c) the agreed price for, or the proceeds of sale of, any materials, supplies or other things kept by Contractor or sold, pursuant to the provisions of this clause, and not otherwise recovered by or credited to Boeing."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salsbury Industries v. The United States
905 F.2d 1518 (Federal Circuit, 1990)
Green Shoe Manufacturing Co. v. Farber
712 P.2d 1014 (Supreme Court of Colorado, 1986)
Montclair Towers, Ltd v. First Interstate Bank of Denver N.A.
767 P.2d 792 (Colorado Court of Appeals, 1988)
York Plumbing & Heating Co. v. Groussman Investment Co.
443 P.2d 986 (Supreme Court of Colorado, 1968)
MILLERS'MUT. INS. v. Iowa Nat. Mut. Ins. Co.
618 F. Supp. 301 (D. Colorado, 1985)
Key v. Liquid Energy Corp.
906 F.2d 500 (Tenth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
28 F.3d 114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-states-construction-company-inc-a-wyoming-corporation-ca10-1994.