Western Resources, Inc. v. Federal Energy Regulatory Commission

9 F.3d 1568, 304 U.S. App. D.C. 9
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 9, 1993
DocketNos. 92-1319, 92-1324
StatusPublished
Cited by1 cases

This text of 9 F.3d 1568 (Western Resources, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Resources, Inc. v. Federal Energy Regulatory Commission, 9 F.3d 1568, 304 U.S. App. D.C. 9 (D.C. Cir. 1993).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

In this consolidated case, two parties to a natural gas transportation contract petition for review of a rate-setting order of the Federal Energy Regulatory Commission (“FERC” or “Commission”). Western Resources, Inc. (“Western”),1 a Kansas intrastate pipeline, contracted with Panhandle Eastern Pipe Line Company (“Panhandle”), a large interstate pipeline, for “forward haul” transportation of gas during the summer off-peak season from Kansas to Michigan storage sites and “backhaul” return of the gas to Kansas during the peak winter season under Rate Schedule T-53. Western seeks review of the Commission’s order approving an increase in the forward-haul rate for off-season transportation. Western argues that FERC’s decision runs counter to its regulations, fails to recognize the significant systemic advantages accorded by off-peak forward-haul service and the limitations of the parties’ contract, and deviates from the parties’ agreement specifying that transportation rates should increase commensurately with sales rates. Panhandle seeks review of the Commission’s order requiring backhaul rates to be set at one-half of forward-haul rates in order to reflect the seasonal benefits of decreased capacity constraints. Panhandle contends that the Commission failed to bear its burden of proof in devising this rate structure, made an unwarranted departure from the terms of the parties’ settlement agreement, breached its own regulations, and impermissibly extended its order retroactively. We remand the Commission’s order as to the forward-haul rate so that the Commission may more fully explain its decision, remand as to the backhaul rate so that the Commission may reexamine whether it wishes to proceed under § 4 or § 5 of the Natural Gas Act (“NGA”), 15 U.S.C. §§ 717c(e), 717d(a) (1988), and remand for reconsideration of the refund order in light of the foregoing.

I. Background

A Factual Context

Western entered into a transportation agreement2 with Panhandle on May 17,1982 for the “forward haul” of natural gas from Reno County, Kansas to storage in Michigan during the off-peak summer months and the “backhaul” return of gas to Reno County, Kansas for sale during the peak winter months. The contract included a strict seasonal limitation, permitting forward hauls only in the summer off-peak months, fixed points of receipt, and firm, nondiseountable rates. Since gas flows on Panhandle’s system from west to east, the forward-haul service required the introduction of gas into the system at the upstream point, Reno County, and the removal of gas at the downstream point in Michigan. The backhaul service, in contrast, involved the removal of gas at the upstream point and the introduction of gas at the downstream point3 Thus, the backhaul [1571]*1571service, but not the forward-haul service, involved a reduction in the amount of gas flowing between the upstream point and the downstream point. Because of the contract’s seasonal limitations, forward hauls only occurred during the period in which the pipeline was used least, and backhauls, which alleviated the burden on the system between the upstream and downstream points, only occurred when the capacity of the pipeline was most constrained. In recognition of the distinctions between these forms of transportation, the parties’ contract employed two different methodologies in calculating rates. The forward-haul rate for Rate Schedule T-53 service was based on Panhandle’s system unit cost per 100 miles, which worked out to approximately 20.05 cents per Mcf,4 and the backhaul rate was set at a fixed one cent per Mcf. See Joint Appendix (“J.A”) at 104-05.

B. Procedural History

On August 31, 1987, Panhandle filed revised tariff sheets in Docket No. RP87-103-000. Among other adjustments, the new tariff sheets proposed to change Rate Schedule T-53 by requiring a full allocation of costs for all services, thus increasing the rates for backhaul and forward-haul services to a level equivalent to that for forward-haul open access transportation service under Rate Schedule PT.5 On September 30, 1987, the Commission issued an order accepting for filing and suspending certain of the tariff sheets, with the result that the increased T-53 rates became effective March 1,1988 subject to refund. See Panhandle Eastern Pipe Line Co., 40 F.E.R.C. ¶ 61,369, reh’g granted in part, 41 F.E.R.C. ¶ 61,170 (1987). On September 30, 1988, Panhandle filed another rate increase petition with the Commission pursuant to § 4 of the NGA in Docket No. RP88-262-000. These rates became effective on April 1, 1989. See Panhandle Eastern Pipe Line Co., 45 F.E.R.C. ¶ 61,145 (1988), reh’g granted in part, 46 F.E.R.C. ¶ 61,268 (1989). As a result, the rates at issue in this case apply only to a thirteen-month “locked-in” period from March 1,1988 to March 31, 1989.

The Commission held a hearing between March 17 and April 29,1988 on the propriety of the locked-in rate hike. On March 22, 1990, the parties filed a settlement agreement with the Commission that sought to resolve several of the issues litigated in the hearing. Simultaneously, the parties filed a Stipulation and Agreement in the superseding rate proceeding, Docket No. RP88-262-000, with the expectation that each settlement offer would be contingent on the other. On May 22, 1990, the presiding Administrative Law Judge (“ALJ”) declined to certify the settlement in Docket No. RP88-262-000. The parties agreed on June 26,1990 to allow certification of the settlement in this docket while continuing litigation in Docket No. RP88-262-000. The settlement, approved by the Commission on November 26, 1991, reserved one issue for the Commission’s disposition in Article III:

Whether the rates for service to [Western] under Rate Schedule T-53[,] which is performed pursuant to section 7 authorization[,] which predate the issuance of Order 436 shall be equivalent to the maximum rates for services provided under Rate Schedule PT.

Panhandle Eastern Pipe Line Co., 57 F.E.R.C. ¶ 61,265, ¶ 61,858 (1991). Article III § 5 set forth the procedures by which the parties agreed to litigate the reserved issue, specifically contemplating the contingency that the Commission might determine that Western was entitled to a refund. See J.A. at 296.

In its initial order, FERC approved the forward-haul rate increase as “entirely consistent with the Commission’s regulations,” but determined that “a reasonable maximum charge for the backhaul portion of the Rate Schedule T-53 service is a rate equal to one half the forward haul rate[,] because a back-[1572]*1572haul service benefits Panhandle by creating capacity that may be used by other shippers.” 57 F.E.R.C. 161,265, ¶ 61,863. The Commission ordered Panhandle to refund monies paid by Western in excess of the adjusted backhaul rate, “as provided for in article III of the settlement.” Id. Both Western and Panhandle filed timely requests for rehearing, Western urging that the Commission decrease the forward-haul rate, and Panhandle requesting that the Commission reverse its determination with respect to the adjusted backhaul rate.

The Commission rejected both petitions for rehearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
9 F.3d 1568, 304 U.S. App. D.C. 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-resources-inc-v-federal-energy-regulatory-commission-cadc-1993.