Western Pipe & Steel Co. v. Tuolumne Gold Dredging Corp.

146 P.2d 61, 63 Cal. App. 2d 21, 1944 Cal. App. LEXIS 907
CourtCalifornia Court of Appeal
DecidedFebruary 24, 1944
DocketCiv. 12553
StatusPublished
Cited by20 cases

This text of 146 P.2d 61 (Western Pipe & Steel Co. v. Tuolumne Gold Dredging Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Pipe & Steel Co. v. Tuolumne Gold Dredging Corp., 146 P.2d 61, 63 Cal. App. 2d 21, 1944 Cal. App. LEXIS 907 (Cal. Ct. App. 1944).

Opinion

*23 NOURSE, P. J.

Three actions to enforce individual liens were filed in the superior court against Tuolumne Gold Dredging Corporation, the owner of certain gold-bearing lands, the Johnson Company, the holder of a contract with the Tuolumne Company for the construction of a gold dredge, and the Fidelity and Deposit Company, the surety on a faithful performance bond covering that contract.- The lien claimants were all subcontractors of the Johnson Company and they performed practically all the work and furnished the materials for the construction of the gold dredge. The three actions were consolidated for trial, judgments were duly entered in favor of the three lien claimants, and against the surety. During the course of the trial the claims of these lien holders, and the unsecured claim of Moore Machinery Company, which is not involved in the appeal, were established without any material contest, but the main issues involved, and with which this appeal relates, were tried on the respective cross-complaints of the Tuolumne Company and the Johnson Company. A judgment favorable to the Johnson Company and the Fidelity and Deposit Company was entered against the Tuolumne Company, from which the latter has appealed, naming all other parties respondents. After the appeal was perfected a stipulation was filed herein reciting that the lien claimants had been joined as nominal respondents only, that no relief was sought affecting the judgments in relation to their liens, and that they need not appear or file briefs herein. The issues on the appeal are thus narrowed to the controversy between the owner of the premises and the original contractor concerning the performance of the contract. There is also the issue of the liability of the surety on the original contract.

The Johnson Company filed a cross-complaint against the codefendant, the Tuolumne Company, claiming a certain amount due under the terms of the original contract. The Tuolumne Company filed a cross-complaint against the Johnson Company and its surety claiming damages for failure to perform the conditions of the contract. Prior thereto the Tuolumne Company had filed in the same superior court an independent action against the same parties pleading the same matters and seeking the same relief. That action had been removed upon motion of Johnson Company to the United States District Court where it was still pending at all the time during these proceedings. After all the evidence *24 was in the Johnson Company was permitted to amend to plead the pendency of the action in the federal court. This plea having been sustained the Tuolumne Company made an offer to prove the facts alleged in its answer and cross-complaint and this offer was rejected. These rulings present two of the grounds urged here by appellant. Upon the trial of the issues raised by the cross-complaint of the Johnson Company it offered evidence tending to prove the satisfactory completion of its contract with the Tuolumne Company, the full acceptance and taking possession of the dredge, the payments made on account thereof, and the balance alleged to be due. The Tuolumne Company introduced no substantial evidence to controvert this and the findings of the trial court on that issue are not subject to attack. No explanation is made of the failure of the Tuolumne Company to controvert this evidence, but, when it came to the issues raised in its cross-complaint and answer to the eross-eomplaint of the Johnson Company it made a qualified tender of proof that after full acceptance and complete possession for several months it discovered certain minor defects in its plans and specifications which made the dredge unworkable under certain conditions, and the form of the offer presents one of the questions for decision.

Preliminarily it should be stated that the objection to the offer of proof of the affirmative allegations of the cross-complaint of the Tuolumne Company was sustained upon the ground that another action was pending in the federal court for the same relief. The objection to the offer of proof of the allegations of its answer to the cross-complaint of the Johnson Company, and of the defensive matters pleaded in its own cross-complaint, was sustained upon the ground that it was too general and insufficient in law to constitute a valid offer of proof.

In this portion of the opinion we will refer to the Tuolumne Company as appellant and to the Johnson Company as respondent. The basis of the attack upon the ruling on the question of the pendency of another action is that it led to the finding and conclusion of the trial court that appellant was “barred” from presenting evidence under its cross-complaint “for affirmative recovery thereon” whereas, the appellant argues, if the plea were good the action should have been abated and not barred.

The circumstances under which the question arises are *25 these—while a witness called by appellant was testifying, the respondent requested leave of the court to amend its answer to appellant’s cross-complaint to plead the pendency of another action. Appellant stipulated that the amendment could be filed at that time, but reserved objection that it did not plead a valid defense. From that time forward the plea was treated as one coming under sections 430 and 433 of the Code of Civil Procedure — “another action pending between the same parties for the same cause.” At no time was it treated as a “bar” to the cause of action, and, though the word was used in the findings, it is followed immediately by the expression “from presenting evidence . . . for affirmative recovery . . . because of the pendency of another action. ...” It is apparent that there was no intention to bar the appellant from prosecuting its cause at the proper time and in the proper tribunal, but that the true meaning of the finding was in accord with the intention of the parties—that appellant’s cause of action for “affirmative” relief was abated under the terms of the code section.

It was made equally clear by the trial court, and by the statements of respective counsel at the time, that the ruling upon appellant’s offer of proof was made separately; that, as to the affirmative matter pleaded in appellant’s cross-complaint, the objection was sustained upon the ground that another action was pending for the same relief; that, as to any defensive matter to the cause of action pleaded in respondent’s cross-complaint, the offer of proof was too general. Appellant does not contend that it was error to suspend proceedings upon the cross-complaint for the reasons stated. Cases cited by appellant support the ruling. (Conner v. Bank of Bakersfield, 174 Cal. 400, 404 [163 P. 353]; Hilton v. Reed, 46 Cal.App.2d 449, 454 [116 P.2d 98]; National Auto Ins. Co. v. Winter, 58 Cal.App.2d 11, 15 [136 P.2d 22]; 1 Cal.Jur. 23.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gill v. Royal Ruby, Inc. CA1/3
California Court of Appeal, 2023
(PS) Schmitz v. Asman
E.D. California, 2020
ZF Micro Devices v. TAT Capital Partners
California Court of Appeal, 2016
ZF Micro Devices, Inc. v. TAT Capital Partners, Ltd.
5 Cal. App. 5th 69 (California Court of Appeal, 2016)
California-American Water Co. v. Marina Coast Water District
2 Cal. App. 5th 748 (California Court of Appeal, 2016)
Boyer v. Jensen
28 Cal. Rptr. 3d 124 (California Court of Appeal, 2005)
Luna Records Corp., Inc. v. Alvarado
232 Cal. App. 3d 1023 (California Court of Appeal, 1991)
Moorpark Unified School District v. Superior Court
223 Cal. App. 3d 954 (California Court of Appeal, 1990)
Liberty Mutual Insurance v. Fales
505 P.2d 213 (California Supreme Court, 1973)
Trindade v. Superior Court
29 Cal. App. 3d 857 (California Court of Appeal, 1973)
Jones v. Russ Davis Ford
247 Cal. App. 2d 725 (California Court of Appeal, 1967)
Lewis v. Merrill
365 P.2d 1052 (Oregon Supreme Court, 1961)
Adolph v. Municipal Court
181 Cal. App. 2d 198 (California Court of Appeal, 1960)
San Martin v. Superior Court
169 Cal. App. 2d 14 (California Court of Appeal, 1959)
Luther v. Foster
310 P.2d 655 (California Court of Appeal, 1957)
Reconstruction Finance Corp. v. Tuolumne Gold Dredging Corp.
137 F. Supp. 855 (N.D. California, 1953)
Peterson v. Montgomery Holding Co.
202 P.2d 365 (California Court of Appeal, 1949)
Tuolumne Gold Dredging Corp. v. Walter W. Johnson Co.
61 F. Supp. 62 (N.D. California, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
146 P.2d 61, 63 Cal. App. 2d 21, 1944 Cal. App. LEXIS 907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-pipe-steel-co-v-tuolumne-gold-dredging-corp-calctapp-1944.