Western Municipal Construction of Wyoming, Inc. v. Better Living, LLC

2010 WY 92, 234 P.3d 1223, 2010 Wyo. LEXIS 94, 2010 WL 2574186
CourtWyoming Supreme Court
DecidedJune 29, 2010
DocketS-09-0116
StatusPublished
Cited by3 cases

This text of 2010 WY 92 (Western Municipal Construction of Wyoming, Inc. v. Better Living, LLC) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Municipal Construction of Wyoming, Inc. v. Better Living, LLC, 2010 WY 92, 234 P.3d 1223, 2010 Wyo. LEXIS 94, 2010 WL 2574186 (Wyo. 2010).

Opinion

HILL, Justice.

[T1] Appellant, Western Municipal Construction (Western), challenges the district court's order granting summary judgment in favor of the Appellee, Better Living, LLC (Better Living). We will reverse and remand for entry of summary judgment in favor of Western.

ISSUE

[T2] Western states this issue:

Did the district court improperly grant summary judgment for [Better Living] by failing to review the Settlement Agreement and improperly superimposing the Project Contract's dispute procedures?

Better Living restates the issue thus:

Did the trial court properly grant Better Living's motion to dismiss Western's complaint for declaratory judgment based on Western's undisputed failure to comply with an express condition precedent in the parties' contract?

FACTS AND PROCEEDINGS

[¶3] This appeal arises out of the dismissal of a Complaint for Declaratory Judgment. That complaint sought to declare the parties' rights under a settlement agreement resulting from a mediated dispute concerning a construction contract. Western is a Wyoming corporation which was the contractor for a residential infrastructure construction project in Sheridan. Better Living is a Wyoming LLC which was the owner of the project. A dispute arose concerning two items: (1) the amount of liquidated damages, for which Better Living had assessed a $345,000.00 deduction against the $1.4 million contract price, and (2) the amount due under a "Force Account" bid iter. The parties agreed to mediate that dispute and eventually they reached a settlement agreement.

[T4] On December 3, 2008, Western filed a Complaint for Declaratory Judgment asking the district court to review the parties' Settlement Agreement and enter an order enforcing the unambiguous language of that agreement to the effect that Better Living owed Western $250,000.00 as full and complete compensation for any and all amounts owed on the project. Western also asked that it be awarded its fees and costs for bringing this action, as provided for in the contract between the parties. Both parties filed motions for summary judgment. On May 1, 2009, the district court entered summary judgment in favor of Better Living on the bases set out in its Decision Letter filed of record on April 14, 2009.

[¶5] Prior to these proceedings, the parties had submitted the disputes between them to a mediator for resolution. The results of that mediation were memorialized in this agreement which was executed on September 29, 2008:

SKEELS ST/POPLAR GROVE PHASE I STREET AND UTILITY PROJECT CONTRACT AMENDMENT TO SETTLE DISPUTES REGARDING LIQUIDATED DAMAGES CLAIMS AND FORCE ACCOUNT BID ITEM
WHEREAS, the Parties, Better Living, LLC ("Owner") and Western Municipal Construction of Wyoming, Inc. ("Contractor") mutually desire to resolve their legal and equitable disputes arising under the above referenced Contract in the most timely and cost effective manner available to them; and
WHEREAS, the parties have participated in mediation in Casper, Wyoming, with their respective legal counsel and mediator Mark Gifford, Esq.; and
*1225 WHEREAS, the parties have agreed through mediation to settle their existing disagreements concerning amounts to be paid by Owner to Contractor under paragraph 3.2 of the June 11, 2007 Agreement for the Project and otherwise under the Project contract doeu-ments and concerning Project bid item # 145 on Schedule G of the Alternate 1 Project Contract Bid package and otherwise under the Project contract doeu-ments; and
WHEREAS, the parties desire to resolve these two items of dispute under the existing Project contract documents only as set forth herein and to otherwise go forward pursuant to the existing Project contract without any other amendments thereto.
WHEREFORE, IT IS HEREBY AGREED AS FOLLOWS:
1. Owner agrees to pay Contractor a final amount of $250,000.00 as full and complete compensation for any and all amounts owed to Contractor for work performed on the Project, including without limitation retainage and bid item amounts including Schedule G, Bid item #145 "Force Account" work. Contractor expressly agrees to accept said amount as the proper and agreed full and final amount owed by Owner to Contractor for all "Foree Account" work and materials. Contractor hereby expressly releases Owner from claims to any other or further claims concerning any "Force Account" work and materials and expressly waives and releases any claims, liens, or any similar claims against Owner or any Project property or improvements concerning liquidated damages payments or credits for delay in completion of the Project pursuant to paragraph 3.2 of the June 11, 2007 Agreement for the Project and otherwise under the Project contract documents.
It shall be an express condition precedent to the effectiveness and enforceability of the compromise promises set forth in paragraph 1 above that the Contractor shall cooperate in good faith with the Owner and HKM Engineering, Inc., to complete all punch list work on the Project on or before October 14, 2008 and shall otherwise comply with the Project contract requirements concerning the proper and timely application for Final Payment. If the Contractor does not complete all punch list work and submit timely, complete, proper, and fully executed Final Payment application paperwork pursuant to the Project contract, on or before October 14, 2008, then liquidated damages shall acerue at the rate of $600.00 per day as provided in the Project contract documents. Contractor will stipulate to the entry of judgment in favor of Owner and against Contractor for such liquidated damages accrual.
The parties' existing June 11, 2007 Project Contract shall otherwise remain in full force and effect. This agreement does not constitute any amendment of any terms in the parties existing Project Contract other than those expressly set forth in paragraphs 1 and 2 above.
This agreement shall not constitute any release or waiver of any kind by any party of any rights or claims arising out of the Project Contract or the Project other than those expressly set forth in paragraphs 1 and 2 above.
All parties executing this agreement do so knowingly, voluntarily, and with the full advice of counsel. This agreement shall be governed by the laws of the State of Wyoming in all respects.
This agreement shall be binding upon and shall inure to the benefit of the respect assigns, successors, heirs, agents, employees, officers and members of the parties.

[¶6] The record is not clear as to the date that Western submitted its request for the final payment, but it is not disputed that it was submitted before October 14, 2008. Indeed, it had to have been submitted before October 14, 2008, because it is also undisputed that HKM Engineering, Inc., sent out a "Memorandum" to both Western and Better *1226 Living on October 6, 2008, containing these very limited bits of information.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martinez v. Rocky Mountain Bank
540 F. App'x 846 (Tenth Circuit, 2013)
Shaw Construction, LLC v. Rocky Mountain Hardware, Inc.
2012 WY 60 (Wyoming Supreme Court, 2012)
Allen v. Anderson
2011 WY 94 (Wyoming Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2010 WY 92, 234 P.3d 1223, 2010 Wyo. LEXIS 94, 2010 WL 2574186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-municipal-construction-of-wyoming-inc-v-better-living-llc-wyo-2010.