Western Mfg. Co. v. Kingman & Co.

112 F. 246, 1901 U.S. App. LEXIS 4090
Court of Appeals for the Eighth Circuit·Decided November 25, 1901·No. No. 1,545·Published

Opinion

ADAMS, District Judge,

after stating the case as above, delivered the opinion of the court.

The evidence introduced by both parties, on the issues of waiver, default, and rescission is mainly confined to certain correspondence, which appears in the record, and to certain interviews between L. M. Welch, who was plaintiff’s agent, and Martin Kingman, who was president of the defendant corporation. Welch testifies that he had an interview with Kingman soon after October i, 1S93, at Chicago, in which he reminded him that he had not sent orders as he promised for the mowers, and that the time within which he was to do so, under the contract, had expired, and he says he insisted on his complying with the terms of the contract and taking the mowers. Welch testifies that Kingman said he would go home and write to his different branch Houses, and see if they could store them, and he would send orders for them. He says he thinks he mentioned to Kingman at that time that, if he did not care to order them away, his company, the plaintiff, was a licensed warehouse, and that the defendant might leave the mowers with it on storage, taking warehouse receipts therefor, and settle for the mowers as on actual delivery. lie says King-man responded that he did not care to have the mowers stored except in his own building, and that he had plenty-of room in which to store his own goods. He says he told Kingman that that was all right; that he had simply suggested that course for his convenience; and that Kingman then said, “I will take the mowers and send you the orders.”

[248] ■ It appears that the plaintiff afterwards, on November 9th, wrote the following letter to the defendant:

“Lincoln, Nebraska, Nov. 9th, 1893.
“Kingmah & Co., Peoria, Illinois—Gentlemen: Your Mr. Kingman, whom the writer met in Chicago on the 26th inst. [? nit.], stated that we would hear from you in a short time relative to the disposition of the balance of mowers due on your contract. We hope you can give us shipping directions at once. On account of the fire we had, we are very much cramped for room, and need the room these mowers occupy for a paint shop. Please favor us by return mail. We have the following Defiance shellers on hand, partly completed: 394, no fan; 397. with fan,-—and we will begin .work on these next week, and complete them as rapidly as possible, and would be pleased to have you order now for two or three, cars, so we can ship them out as fast as finished.”

To this letter, the defendant, on November 18, 1893, made the following answer:

“Western Manufacturing Company, Lincoln, Nebraska—Gentlemen: Yours of the 9th, requesting shipping instructions for mowers, is received and noted. We have been considering the same, as to what we could do as to taking these mowers, and write to say that it is out of the question for us to do so, and do not see any way -but you will have to store them. We note as to shellers, and were obliged to order a car from other parties, to fill the place of car ordered to Des Moines. We have now written Omaha asking if they are about ready to place an order for another car, and giving them the number of shellers you have on hand. We expect an order in'a few days, and will forward same to you. The writer was at Omaha last week, and while-there talked over matters with Mr. Oarson. He says there is but little demand for shellers in Nebraska; that the trade is very light, but that he will need some shellers soon. We will write him again concerning your stock, and will try and draw from you soon.”

The foregoing shows that the manufacturing company waived the provision of the contract requiring Kingman & Co. to order before October 1, 1893, the full complement of 160 mowers. For some reason, unexplained by the evidence, orders had been made before that day for only 54 mowers; but the parties treated the obligation of the contract with respect to the mowers as in effect and binding upon them thereafter. The trial proceeded on that theory. The pourt charged the jury that the facts showed a waiver of the element of time, and said: “The mere failure to order the mowers on or before the 1st of October does not constitute an actionable breach of the contract for which the plaintiff can recover in this action.” There was no exception to this charge. Accordingly we may treat the element of time within which the mowers were to be ordered'as eliminated from the contract sued on, leaving the obligation, in respect thereto, to order the same within a reasonable time.

We can now intelligently consider the first and second assignments of error.

The plaintiff requested the trial court to give the jury the following instruction:

Free access — add to your briefcase to read the full text and ask questions with AI

Western Mfg. Co. v. Kingman & Co., 112 F. 246, 1901 U.S. App. LEXIS 4090 (8th Cir. 1901).

112 F. 246 (Western Mfg. Co. v. Kingman & Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kingman & Co. v. Western Mfg. Co.
92 F. 486 (Eighth Circuit, 1899)