Western Extralite Co. v. Safeco Insurance Co.

301 S.W.3d 527, 70 U.C.C. Rep. Serv. 2d (West) 585, 2009 Mo. App. LEXIS 1666, 2009 WL 4250520
CourtMissouri Court of Appeals
DecidedDecember 1, 2009
DocketWD 70260
StatusPublished
Cited by2 cases

This text of 301 S.W.3d 527 (Western Extralite Co. v. Safeco Insurance Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Extralite Co. v. Safeco Insurance Co., 301 S.W.3d 527, 70 U.C.C. Rep. Serv. 2d (West) 585, 2009 Mo. App. LEXIS 1666, 2009 WL 4250520 (Mo. Ct. App. 2009).

Opinion

JOSEPH M. ELLIS, Judge.

Western Extralite Company appeals from a judgment entered in the Circuit Court of Boone County in favor of Freise Construction Company in an action on account filed by Western Extralite. For the following reasons, the trial court’s judgment is reversed.

Freise was the general contractor on the Hatch Hall Residence Project at the University of Missouri at Columbia. Freise subcontracted the electrical work on that project to Ruzieka Electric, which ordered supplies, on account, from Western Extral-ite, a distributor of electrical products. In April 2007, Western Extralite delivered to Ruzieka an order of light fixtures along with lighting and electrical outlets and receptacles that had been manufactured by Celex. Western Extralite subsequently received payment of $360,850.00 for that shipment.

In June 2007, Freise terminated Ruzieka from the project for failing to comply with the terms of the subcontracting agree *529 ment. Later that month, Freise entered into an account agreement directly with Western Extralite allowing it to order any further electrical equipment on account directly from Western Extralite.

In early August 2007, after the light fixtures delivered to Ruzicka in April 2007 were installed and wired, Freise discovered that the ballast transformers on the majority of the light fixtures were either defective or missing. Freise notified Western Extralite after discovering this problem. Western Extralite, in turn, notified Adam Ward of Ward & Jacobs, the manufacturer’s representative for Celex, of the problem with the ballast transformers. Subsequently, because Ruzicka had not ordered a sufficient number of light fixtures for the residence hall project, Freise ordered an additional $16,285.00 worth of light fixtures from Western Extralite.

Ward contacted Freise, visited the worksite on August 20, and confirmed that the ballasts were defective or missing. Ward agreed to ship 160 replacement ballasts to Freise. Andy Walden, the project manager for Freise, told Ward that, because of time constraints on the project, it would be necessary for the new electrical subcontractor to start swapping out ballasts immediately and to purchase necessary replacement ballasts locally until the shipment arrived. Freise did not convey that information to Western Extralite. Had Western Extralite been informed that Ward could not get the replacement ballasts to Freise in a timely manner, it could have timely provided conforming ballasts from another supplier.

On August 22, the additional light fixtures ordered by Freise were delivered. It was later determined that some of the ballasts on the fixtures in that shipment were also defective or missing. Freise did not notify Western Extralite of the problems with this most recent shipment. Replacement of the ballasts on all of the fixtures was completed by September 13 when the shipment of replacement ballasts from the manufacturer for the April shipment arrived and was rejected by Freise.

After receiving the final invoice from Western Extralite for $16,284.00, in October 2007, Freise paid $6,507.70 of that bill. Along with that payment, Freise included a letter stating that it was “back charging” Western Extralite $9,776.10 for the cost of purchasing and installing new ballasts in the fixtures from both the April shipment to Ruzicka and the August shipment to Freise.

On February 13, 2008, Western Extral-ite filed a petition in the Circuit Court of Boone County seeking to recover the $9,776.10 remaining due on the invoice for the August shipment. The petition asserted an action on account for the one and only August shipment of light fixtures ordered by Freise from Western Extralite. Both the petition and Freise’s answer relate solely to that August shipment from Western Extralite to Freise, and neither even mentions the fixtures that Ruzicka bought from Western Extralite in April. The case was tried to the court on August 29, 2008, and the court subsequently entered judgment in favor of Freise.

In its sole point on appeal, Western Extralite claims that the trial court erroneously applied the law in entering judgment in favor of Freise in its action on account because Freise had admitted entering into an account agreement with Western Extralite, admitted that Western Extralite had complied with the terms of that agreement, and admitted breaching the terms of the account agreement. Western Extralite further contends that Freise failed to establish a valid defense to its claim.

*530 As in any court-tried civil case, our review is governed by the standard of review established in Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976). Furne v. Dir. of Revenue, 238 S.W.3d 177, 180 (Mo.App. W.D.2007). “Accordingly, the trial court’s decision will be affirmed unless it is not supported by substantial evidence, it is against the weight of the evidence, or it misstates or misapplies the law.” Id. at 179 (internal quotation omitted). “This standard requires us to accept the trial court’s credibility determinations and view the evidence in the light most favorable to the judgment, while disregarding all contrary evidence and permissible inferences.” Capital Bank v. Barnes, 277 S.W.3d 781, 782 (Mo.App. S.D.2009). “We defer to the factual findings of the trial court, which is in a superior position to assess credibility. However, this Court independently evaluates the trial court’s conclusions of law.” G.H.H. Invs., L.L.C. v. Chesterfield Mgmt. Assocs., L.P., 262 S.W.3d 687, 691 (Mo.App. E.D.2008) (internal citation omitted).

Neither party requested that the trial court make findings of fact and conclusions of law under Rule 73.01(a), and the trial court did not enter any of its own accord. “In a court-tried case, where there are no findings of fact or conclusions of law, all issues are deemed found in accordance with the result reached and the judgment affirmed if it could be rendered on any reasonable theory.” Gifford v. Geosling, 951 S.W.2d 641, 643-44 (Mo.App. W.D.1997).

“An action on account is an action at law, based in contract.” Berlin v. Pickett, 221 S.W.3d 406, 410 (Mo.App. W.D.2006). “To make a submissible case, the plaintiff must prove that (1) defendant requested plaintiff to furnish merchandise or services, (2) plaintiff accepted defendant’s offer by furnishing such merchandise or services, and (3) the charges were reasonable.” Dyna Flex Ltd. v. Charleville, 890 S.W.2d 413, 414 (Mo.App. E.D.1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rissler v. HEINZLER
316 S.W.3d 533 (Missouri Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
301 S.W.3d 527, 70 U.C.C. Rep. Serv. 2d (West) 585, 2009 Mo. App. LEXIS 1666, 2009 WL 4250520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-extralite-co-v-safeco-insurance-co-moctapp-2009.