Western Contracting Corp. v. Titter

258 A.2d 600, 255 Md. 581
CourtCourt of Appeals of Maryland
DecidedNovember 19, 1969
Docket[No. 11, September Term, 1969.]
StatusPublished
Cited by3 cases

This text of 258 A.2d 600 (Western Contracting Corp. v. Titter) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Contracting Corp. v. Titter, 258 A.2d 600, 255 Md. 581 (Md. 1969).

Opinion

Barnes, J.,

delivered the opinion of the Court.

This appeal principally involves the rights of a riparian owner of land on navigable water in Cecil County to recover damages in the Circuit Court for Cecil County (Mackey, J.) resulting from an obstruction of access to. those waters by a contractor with the United States Army Corps of Engineers (Army Engineers), an agency of the Government of the United States, engaged in the improvement of navigation in those waters and the correctness of the charge of the trial judge to the jury.

The appellant, Western Contracting Corporation, (defendant below) was a successful bidder on a contract with the Army Engineers to do certain dredging work in the Chesapeake and Delaware Canal (C & D Canal). These operations began on March 22, 1966, and were completed on July 23, 1966. It took Western Contracting approximately one month after the conclusion of the dredging operation to assemble and mobilize its equipment and pipelines for transportation to its next job at Norfolk, Virginia.

*583 The dredging operations were conducted by the use of a floating hydraulic dredge which removed debris and mud from the bottom of the C & D Canal and then pumped the materials, assisted by boosters, through a 24-inch pipeline to a disposal area located on property of the United States. This pipeline consisted of 500 foot lengths of pipe. The Army Engineers had originally directed Western Contracting to pump the material into a disposal area on Welch Point, but because the dike surrounding this disposal area had developed longitudinal and horizontal cracks, the Army Engineers authorized Western Contractors to use United States Government Disposal Area “D” located on the C & D Canal, approximately one mile west of the bridge at Chesapeake City.

The land of the appellees, Richard M. Titter and Elizabeth R. Titter, his wife, adjoins Disposal Area “D”, and consists of 14.25 acres with a water frontage of approximately 680 feet on the south side of Back Creek (which is used as part of the C & D Canal Waterway), about one mile west of the Chesapeake City bridge.

During the early part of June, 1966, Western Contracting began to extend a single floating pipeline, resting on pontoons, from its dredge to Disposal Area “D” in order to dredge the area of the C & D Canal west of the Titter property. This floating pipeline was connected into pipes running into Disposal Area “D” on June 21 and pumped mud and debris through the lines from June 22 to July 23. This pipeline extended in the water across the front of the Titter property on Back Creek after it was connected with the disposal area pipes, but no part of the pipeline rested on the front land of the Titter property.

When Western Contracting terminated the dredging operations in order to transport the 500 foot long pipes by water to the new job near Norfolk, it was necessary to weld “blanks” or metal disks in the openings at each end of these pipes in order to make them watertight. The welding operation took place in a small mooring basin in front of land owned by the United States on the north *584 side of Back Creek approximately opposite the Titter property. Being unable to assemble all of the pipes in front of the Government property inasmuch as they would have protruded out into the channel of the C & D Canal and thus have impeded navigation, Western Contracting used the cove in front of the Titter property. Western Contracting deemed this cove to be the only available place in the vicinity where the pipes could be stored temporarily until there was sufficient room for them in the welding area, in that the other possible temporary assemblage area was at Welch Point some five or six miles west of the welding area.

The Titter property has a small screened-in one-story building, 16 feet by 12 feet, without heating, plumbing or electricity, and has no other improvements. The Titters, their family and friends, use this property from spring until autumn for swimming, fishing, boating, and picnicking. The Titters have never rented their property.

Mr. Titter testified that the pipeline and pipes denied the Titters the normal and peaceful enjoyment of their ‘.property and access to the water. There was a conflict in the evidence between the testimony of Mr. Titter and the testimony of Allen Dregg, a supervisor for Western Contracting, in regard to the number of pipes and pipelines, their location with reference to the Titter property and whether or not the pipelines were actually being used in the dredging operation.

Mr. Dregg testified that there was only a single pipeline placed in front of the Titter property which was in actual use üntil July 23 and that it was not until after that date, that pipes were stored in front of the property. Mr. Titter, on the other hand, testified that the single pipeline through which dredged materials were being pumped, did not go along the shoreline of the Titter property and that pipeline did not “bother him any,” but what did bother him was the storage of the pipes, there being five to seven pipelines involved and West *585 ern Contracting “left a bunch of pipes on the beach for the whole summer.” 1

Mr. Titter stated that he made numerous complaints to Mr. Dregg and requested the removal of the pipelines from in front of the Titter property and on each occasion was assured that they would be removed “right away.” Mr. Dregg admitted on cross-examination that he had received these complaints and that he had told Mr. Titter that he “would take care of it.” The pipes were not removed by Western Contracting until August 26 following a telephone call from the attorney for the Titters.

The only evidence in regard to damages was given by Mr. Titter, who estimated the damages at $2,000, and by James Reese Short, a real estate expert who testified for the Titters and who estimated the damages at $3,000. The jury rendered a verdict in favor of the Titters for $2,500, but the ad damnum clause in the declaration having claimed only $2,000, a remittitur was entered by the Titters for $500 and judgment was entered for $2,000 with interest and costs. After a motion by Western Contracting for a judgment N.O.V. or in the alternative for a new trial had been overruled by the trial court, judgment absolute was entered upon the verdict on January 28, 1969, from which Western Contracting took a timely appeal to this Court.

Western Contracting had moved for a directed verdict at the end of the plaintiff’s case and again at the end of the entire case. Both motions were denied by the trial court. In instructing the jury, the trial court told the jury that this was a tort case and that the alleged wrong *586 involved was not a trespass, but was an invasion of a qualified property right known as “riparian rights.” The trial court further instructed the jury that the right was not exclusive but did give the riparian owner the right of access to the water and a right to engage in normal pursuits, swimming, boating, fishing and so forth. It was pointed out that the claimed deprivation of right was a temporary one not extending beyond August 26, 1966.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
258 A.2d 600, 255 Md. 581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-contracting-corp-v-titter-md-1969.