Western Casualty & Surety Co. v. United States

109 F. Supp. 422, 124 Ct. Cl. 156
CourtUnited States Court of Claims
DecidedFebruary 3, 1953
Docket48819
StatusPublished
Cited by2 cases

This text of 109 F. Supp. 422 (Western Casualty & Surety Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Casualty & Surety Co. v. United States, 109 F. Supp. 422, 124 Ct. Cl. 156 (cc 1953).

Opinion

MADDEN, Judge.

The plaintiff sues for $19,567.35, the admitted value of certain plumbing and heating materials purchased by the United States. The Government purported to purchase the materials from the Meyer Plumbing and Heating Company, a corporation hereinafter called Meyer, but the plaintiff says that it held a chattel mortgage on the materials at the time they were sold, and that Meyer, therefore, had no right to sell them to the Government. The plaintiff’s asserted chattel mortgage was not recorded, but the plaintiff says that that is immaterial because, it claims, the Government had notice of its interest in the materials, and also because the Government did not pay Meyer for them, but only set off the purchase price against taxes which Meyer owed to the Government.

In March 1942, one Blair, a contractor, made a contract with the Government to perform certain construction work at Camp Atterbury, Edinburg, Indiana. Blair gave two subcontracts for plumbing and heating work to Meyer, one for. $363,-978.00 for the work in divisions A-1C and A-1D of the project and the other for $390,000.00 for the work in divisions A-2C and A-2D. Meyer gave performance and payment bonds to Blair and the plaintiff became surety for Meyer on those bonds. As a part of the consideration to the plaintiff for becoming surety on the bonds, Meyer, in his application to the plaintiff, assigned to the plaintiff as collateral all of its right, title and interest in all machinery, equipment, plant, tools and materials which were then or might thereafter be about or upon the site of the work to be performed under the subcontracts. The assignment, by its terms, was to become effective upon the happening of any one of several described events, one of which was the abandonment, forfeiture or breach of the subcontracts, or of the bonds.

One of the terms of the payment bonds was that Meyer should promptly make payment to all persons supplying labor and materials for the performance of the subcontracts. Meyer went ahead with the work until September 4, 1942, at which time it was unable to meet its weekly payroll of $9,463.36. It requested Blair by telegram to pay the men. Blair owed Meyer some $85,000 at the time, some $66,000 of which was retained percentages, the balance being then due and payable to Meyer. Blair met the payroll, and on September 5 wrote the plaintiff demanding that the plaintiff complete Meyer’s subcontracts with Blair. The plaintiff investigated Meyer’s financial condition and found that it was bad. Meyer owed material-men approximately $100,000 and owed an individual $75,000 for money borrowed for the performance of the contract. It had no cash or bank credit. Meyer’s spokesman, however, protested the plaintiff’s proposed intervention, saying that Meyer had not defaulted and could finish the job at a small profit. Meyer’s superintendent on the job estimated that Meyer stood to lose approximately $200,000 on the job. The plaintiff anticipated that the work would be completed in two or three *424 weeks and did not wish to incur extra expense by formally taking over the completion of the contract.

An arrangement, agreeable to Blair, Meyer and the plaintiff, was made and confirmed in writing, under which the plaintiff was not to take over the job, but Blair was to make no payments to Meyer except upon the specific approval of the plaintiff. As to the disposition of surplus materials which Meyer had on the job, the arrangement was that Mr. Grover Sales, Meyer’s attorney, was to sell the property, taking in payment checks payable to Meyer which he would turn over to the plaintiff. Pursuant to the arrangement, needed materials were ordered in Meyer’s name, payrolls were submitted to the plaintiff for approval and, when approved, were paid by Blair out of sums due Meyer. Performance of the contract was completed, and the plaintiff incurred no liability to Blair on the performance bonds for nonperformance by Meyer. But the plaintiff did expend $131,984.04 under its payment bonds to pay unpaid bills for materials, and other amounts which brought its loss on its bond obligations to $135,915.70.

The surplus materials which Meyer had caused to be brought to the job were things which had been obtained under Government priorities and were in short supply. They were worth more in the open market than Meyer had paid or promised to pay for them. Two units of the Army Engineers were interested in purchasing them, the Camp Atterbury post engineers, and the Camp Atterbury area engineers. They negotiated with Meyer’s superintendent and purchased some of the materials in September and October 1942. Invoices in Meyer’s name were presented to the engineers, and purchase orders naming Meyer as seller were issued by the engineers. A check of the post engineers for $1,266.-51, payable to Meyer, in payment for some of the materials, was given to Meyer’s superintendent, and was deposited, pursuant to the arrangement described above, in a joint account of Meyer and the plaintiff. 1 Its disposition is not in question here.

On December 16, 1912, more than a month after the sales here involved had been made, the plaintiff notified the engineers of its interest in the payment for the surplus materials, and requested that checks in payment for them should be made payable to the plaintiff. Meyer’s attorney advised the engineers in 1945 that the amounts owing for the materials should be set off against Meyer’s taxes, and that if that was not done, the failure to do it would be used as a defense if the Government attempted to collect the taxes from Meyer. The Government has not paid either the plaintiff or Meyer $19,-627.92, the agreed price of surplus materials purchased by it. Meyer incurred tax liabilities for 1942 under the Federal Insurance Contributions Act, 26 U.S.C. § 1400 et seq. and the Federal Unemployment Tax Act, 26 U.S.C. § 1600 et seq. nearly all of which indebtedness arose out of the Camp Atterbury job. The taxes amounted to $24,825.68 and have not been paid, except by way of the set-off here asserted by the Government.

Meyer’s assignment to the plaintiff, recited above, of materials on the job, as collateral security for the fulfillment of its obligations to Blair, for which the plaintiff became surety, was a chattel mortgage under Indiana law. Maple v. Seaboard Surety Co., 117 Ind.App. 627, 73 N.E.2d 81. That assignment was to become effective upon stated conditions. We think the conditions were fulfilled. When the plaintiff investigated Meyer’s financial condition in September 1942, and discovered unpaid material bills for $100,000, a debt of $75,000 for money borrowed to carry out the contract, no cash and no bank credit, and some $76,000 owing to Meyer from Blair, it was evident that the plaintiff would suffer losses on its payment bonds. The plaintiff had a right to protect itself as far as possible against any increase in those losses by taking charge of all payments to be thereafter made by Blair to Meyer. It insisted on and obtained the arrangement described above whereby its approval was required for such payments. Its permitting the Meyer superintendent and working force to continue *425

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Car Rental v. Fox
500 P.2d 1148 (Court of Appeals of Arizona, 1972)
Deloney v. United States Fidelity & Guaranty Co.
133 So. 2d 203 (Supreme Court of Alabama, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
109 F. Supp. 422, 124 Ct. Cl. 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-casualty-surety-co-v-united-states-cc-1953.