Westchester Fire Insurance Company v. City of Brooksville

465 F. App'x 851
CourtCourt of Appeals for the Eleventh Circuit
DecidedMarch 8, 2012
Docket10-14075
StatusUnpublished
Cited by1 cases

This text of 465 F. App'x 851 (Westchester Fire Insurance Company v. City of Brooksville) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westchester Fire Insurance Company v. City of Brooksville, 465 F. App'x 851 (11th Cir. 2012).

Opinion

PER CURIAM:

This state-law case is about performance bonds and an abandoned single-family housing development in the City of Brooksville, Florida (the “City”). The City is attempting to recover $5.3 million from the Westchester Fire Insurance Company (“Surety”), which issued two performance bonds to indemnify the City from damage if the developer failed to complete agreed-upon infrastructure for the development. The developer filed for bankruptcy and failed to begin construction of the agreed-upon infrastructure; this dispute followed. Surety sought a declaratory judgment that the City is not entitled to the proceeds of the performance bonds; the City counterclaimed to collect the face value of the bonds.

On appeal from the district court’s grant of summary judgment for Surety, the City argues that Surety is required to pay the City the full value of the bonds even if no construction on the development began. We conclude that the bonds impose no obligation on Surety to pay the City to complete the agreed-upon infrastructure improvements because no construction of the pertinent improvements commenced. We affirm the district court’s granting summary judgment for Surety. 1

I. BACKGROUND

Levitt and Sons of Hernando County (“Levitt”), a developer, purchased property in Brooksville and planned to develop a five-phase, single-family residential subdivision known as the “Cascades.” Levitt and the City entered into a Utility Services Agreement, in which the City agreed to provide, among other things, potable water and sewer services to the Cascades. As part of the Utility Services Agreement, Levitt and the City agreed to a Development Schedule, which includes five phases for development of the Cascades. Construction of Phase One of the Development Schedule is nearly completed. This case is about Phase Two. The three remaining phases of the Cascades development have *853 not been platted, and no plans exist for development of these phases.

The City approved Levitt’s final plan for the construction of Phase Two (the “plat”), and the plat was recorded in March 2006. The plat requires Levitt (or its successors) to construct certain improvements on Phase Two, which would be necessary for the City to supply utility services promised to future residents of Phase Two. These improvements include storm lines, potable water lines, reclaimed water lines, sanitary sewer lines, earthwork, and roadways.

The City, before approving a final plat, must “be satisfied that all improvements ... have been constructed.” City of Brooksville Code of Ordinanoes § 129-3(c) (2006). But, “[i]n lieu of completion of the improvements, a bond ... shall be furnished” equal to the cost of constructing the improvements. Id. For Phase Two, in lieu of completing the improvements before obtaining the City’s approval of a final plat (and in accordance with the Brooks-ville Ordinance), Levitt furnished a bond to secure completion of the improvements. 2

Before beginning construction of the Phase Two improvements, and before the estimated completion date stated on the bonds, Levitt petitioned for bankruptcy and abandoned the Cascades. When Levitt filed for bankruptcy, Levitt had removed some trees and cleared some of the land for Phase Two. Levitt had begun no construction of the pertinent improvements, marketed and sold no lots in Phase Two, and built no home in Phase Two. 3

Shortly after Levitt abandoned the Cascades, the City demanded payment from Surety on the surety bonds. Surety denied payment. The City then sued Surety in state court to foreclose the bonds; the parties later voluntarily dismissed the state-court action and agreed to a one-year forbearance to allow for the possibility that a new developer would purchase the Cascades and begin construction. On the day the City planned to terminate the forbearance agreement, Surety filed this suit in district court for a declaratory judgment of its obligations to the City. The City counterclaimed to foreclose on the bonds. 4

The Phase Two property remains undeveloped land in a vegetated state. A principal of CaSHP2 stated that, if the City does not recover on the bonds, “there is no chance that the improvements will even be started in the foreseeable future” and, if the City does recover on the bonds, there is “maybe, [a] 50-50” chance that development will begin on a rolling basis “between 2013 and 2017.” The City has neither *854 attempted to construct the pertinent improvements nor solicited bids to establish a current expected cost of constructing the improvements nor asked CaSHP2 to construct the improvements. 5 No City resident has requested the construction of the improvements, and no existing home requires the utility services that would be provided by the improvements.

The district court granted summary judgment in favor of Surety and against the City, reasoning, among other things, that Surety’s obligation to pay the City on the bonds is subject to an implied condition that payment for the improvements is required only if construction commences.

II. DISCUSSION

A surety bond is a contract guaranteeing performance of an obligation owed by another party; we interpret surety bonds according to the standards that govern construction of contracts in general and according to the intent of the parties. See Amer. Home Assurance Co. v. Larkin Gen. Hosp., Ltd., 593 So.2d 195, 197 (Fla. 1992). The surety bonds in this case read, in part, this way:

[T]he Developer has agreed to complete certain on-site and/or off-site improvements in accordance with the Project Engineer’s Certified Cost Estimate for Completion of Improvements ... such that if the Developer promptly and faithfully completes the improvements as required by the City Approvals on or before the Estimated Date of Completion, then this obligation will be null and void; otherwise it will remain in full force and effect, subject only to the following conditions:
2. If the Developer fails to complete the required Improvements in accordance with the City Approvals, applicable regulations and this agreement, [Surety] must, upon written demand by the City, promptly pay over to the City the unreleased portion of the bond so that the City, or its agent, can complete the unfinished improvements in accordance with the terms and conditions of the City Approvals.

Pursuant to the City’s ordinance, and before the plat was recorded, Levitt purchased the bonds; Surety then issued the bonds. We construe the bonds in the light of that ordinance. See Glades Cnty. v. Detroit Fid. & Sur. Co., 57 F.2d 449, 451 (5th Cir.1932) (“The bond is plainly given under the [Florida] statute and to be construed in the light of it.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lexon Insurance v. County Council of Berkeley County, W. Va.
770 S.E.2d 547 (West Virginia Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
465 F. App'x 851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westchester-fire-insurance-company-v-city-of-brooksville-ca11-2012.