Westburg Construction, Inc. v. Zuckerman

43 Va. Cir. 38, 1997 Va. Cir. LEXIS 324
CourtFairfax County Circuit Court
DecidedApril 30, 1997
DocketCase No. (Chancery) 139269
StatusPublished

This text of 43 Va. Cir. 38 (Westburg Construction, Inc. v. Zuckerman) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westburg Construction, Inc. v. Zuckerman, 43 Va. Cir. 38, 1997 Va. Cir. LEXIS 324 (Va. Super. Ct. 1997).

Opinion

By Judge Stanley P. Klein

This matter comes before the Court on cross-exceptions to a Commissioner's Report. The Court has thoroughly reviewed the Commissioner’s report, the record, the parties’ memoranda, and foe authorities cited therein. The Court has also considered foe argumente made by counsel at the two hearings. For foe reasons set forth hereinafter, both parties’ exceptions are overruled except for Defendants’ exception to the Commissioner’s calculation of damages and Plaintiff’s exception regarding pre-judgment interest.

This dispute arises out of a contract entered into between foe parties, Plaintiff Westburg Construction, Inc., and Defendant Lilly Zuckerman (“Zuckerman”).1 Plaintiff agreed to design and construct a custom home for the Zuckermans on a lot in Great Falls. Numerous changes were requested by the Zuckermans during the construction process. After Defendants refused to make foe sixth scheduled payment, Plaintiff ceased working on foe project. Plaintiff sued Defendants for foe $117,509 it claims it was never paid. Defendants filed a cross-hill alleging that Plaintiff had, among other tilings, breached the contract

[39]*39The Court appointed a Commissioner who conducted a seven day hearing. The Commissioner recommended that the Court award Westburg a personal judgment against Defendants in the amount of $74,474.41. Plaintiff filed eight exceptions to the Commissioner's Report while Defendants filed five general exceptions which included fifty-eight specific exceptions. Both parties have asked the Court to modify the Commissioner's award accordingly.

The appropriate standard of review for this Court is whether toe Commissioner’s findings are supported by toe evidence. While a court should defer to toe facts as found by toe Commissioner, toe legal conclusions are subject to an essentially de novo review. Hill v. Hill, 227 Va. 569, 576-77 (1984). In addition “[tjhe report of toe commissioner in chancery does not bind toe court like toe verdict of toe jury.... in suits in equity, toe chancellor is judge of boto toe law and facts, and is presumed to be more competent to pass upon toe evidence and draw correct conclusions from it than the commissioner.” Cannon v. Searles, 150 Va. 738 (1928) (quoting Hitt v. Smallwood, 147 Va. 775, 778 (1926)). In accordance with this standard, the Court has carefully studied toe Commissioner’s Report, toe documentary evidence, the transcript from the trial, the briefs, and the applicable law.

I. Defendants'Exceptions

A. Breach of Contract

Defendants contend that the Commissioner disregarded toe parties' contract when determining who breached toe contract. Defendants suggest that application of toe "first breach rule,” whereby toe first material breach terminates toe contract, ignores toe rights given to toe parties under the contract Defendants rely on Spotsylvania Sch. Bd. v. Seaboard Surety Co., 243 Va 202 (1992), for toe proposition that requiring a “material” breach sometimes alters toe parties’ contract. In that case, toe parties agreed that toe contract would terminate upon a "substantial” violation of it. The Supreme Court concluded that requiring a material breach to terminate toe contract imposed an added burden that toe parties did not bargain for. Id. at 212.

The Court concludes that Defendants’ reliance on Spotsylvania Sch. Bd. v. Seaboard Surety is misplaced. The Commissioner’s findings were not premised on who committed toe first material breach, but rather who committed toe first material or significant breach. See Commissioner’s Report, p. 8. The Commissioner determined that Defendants committed toe first breach by toiling to obtain toe construction loan in a timely fashion as required by toe contract. See Commissioner’s Report, p. 7. Defendants argue [40]*40that Westburg waived this breach by starting construction of tine house. Even if the Court were to agree with the Defendants’ position on the waiver issue, the evidence supports the Commissioner’s finding that Defendants committed the next significant breach of the contract when they withheld the sixth payment The Court overrules this exception.

B. Lost Profits

Defendants also object to the Commissioner’s award of lost profits of $7,005 to Westburg for work required by the contract which Plaintiffs were unable to complete due to Defendants’ non-payment Defendants argue that lost profits were not appropriate under the parties’ contract or Virginia law. Furthermore, Defendants claim that no evidence was presented at the Commissioner’s hearing to support this award.

"[DJamages are recoverable for loss of profits prevented by a breach of contract only to the extent that the evidence affords a sufficient basis for estimating their amount in money with reasonable certainty." Boggs v. Duncan, 202 Va. 877, 883 (1961). The parties agree fee Commissioner necessarily found feat, under fee contract, there was $70,056 worth of work remaining to be done on fee house. In addition to the documents received in evidence, which reflect a 10% profit margin, a witness from each side testified that there was to be a 10% markup for profit. See Transcript, pp. 1170,1499. The Commissioner, therefore, appropriately awarded lost profits of $7,005, to wit, 10% of fee additional work Westburg would have completed but for the Zuckermans’ breach. The Court overrules this exception as a reasonable basis did exist, as required by Virginia law, for fee Commissioner to calculate lost profits.

C. Calculation of Damages

Defendants object to fee formula used by fee Commissioner to calculate the damages owed to Westburg. As indicated in his report, *[y]our Commissioner is of fee opinion that Westburg is entitled to fee cost of work which is performed, less valid coste to correct deficiencies, and including a lost profit on a remainder of fee project, which is in fee amount of $74,474.41.” Commissioner’s Report, p.15. In addition, defendants argue that [41]*41die first nine items2 awarded by die Commissioner’s computation wore already required under die parties’ contract.

The calculation of damages Plaintiff is entitled to is a legal issue subject to this Court’s de novo review. Hill v. Hill, 227 Va. 569, 576-77 (1984). Based on die mathematical formula set forth in the Report, the Court is liable to discern how the Commissioner factored in payments Defendants made to Plaintiff. See Commissioner's Report, pp. 15-16. It appears as if the Commissioner may have utilized an item by item approach for the work Plaintiff claimed was unpaid. The Court sustains Defendants’ exception because the Commissioner apparently used a quantum meruit method of calculating Westburg’s damages rather than determining die amount Westburg was entitled to receive pursuant to die terms of the parties’ contract

The evidence clearly establishes that the original contract juice included completion of items for which the Commissioner awarded additional compensation. Therefore, Westburg is not entitled to an award for those items. See Footnote 1. The proper methodology under Virginia law for calculating Plaintiff’s damages is as follows:

$392,680 Original Contract Price

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosser v. Cole
379 S.E.2d 323 (Supreme Court of Virginia, 1989)
Hargraves v. Commonwealth
248 S.E.2d 814 (Supreme Court of Virginia, 1978)
Woodington Electric, Inc. v. Lincoln Savings & Loan Ass'n
385 S.E.2d 872 (Supreme Court of Virginia, 1989)
Hill v. Hill
318 S.E.2d 292 (Supreme Court of Virginia, 1984)
Virginia National Bank v. Harris
257 S.E.2d 867 (Supreme Court of Virginia, 1979)
Boggs v. Duncan
121 S.E.2d 359 (Supreme Court of Virginia, 1961)
Natrella v. Arlington Cty. Bd. of Zoning App.
345 S.E.2d 295 (Supreme Court of Virginia, 1986)
Dairyland Insurance v. Douthat
449 S.E.2d 799 (Supreme Court of Virginia, 1994)
Cooper v. Occoquan Land Development Corp.
377 S.E.2d 631 (Court of Appeals of Virginia, 1989)
Morris v. United Virginia Bank
377 S.E.2d 611 (Supreme Court of Virginia, 1989)
Dexter-Portland Cement Co. v. Acme Supply Co.
133 S.E. 788 (Court of Appeals of Virginia, 1926)
Cannon v. Searles
143 S.E. 495 (Court of Appeals of Virginia, 1928)
Johnson v. Tadlock
39 Va. Cir. 436 (Fairfax County Circuit Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
43 Va. Cir. 38, 1997 Va. Cir. LEXIS 324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westburg-construction-inc-v-zuckerman-vaccfairfax-1997.