Westage Development Group, Inc. v. White
Opinion
Appeal from a judgment of the Supreme Court (Hughes, J.), entered May 17, 1988 in Albany County, which, in a proceeding pursuant to CPLR article 78, granted respondents’ motion to dismiss the petition as time barred.
Petitioners, seeking to commercially develop an approximately 94-acre parcel of property located in the Town of Fishkill, Dutchess County, requested site plan approval for the project in March 1985 from the town’s Planning Board. The property is at the northwest corner of the intersection of State Route 9 and Interstate Route 84. Route 9 runs north-south along the eastern boundary of the parcel and Route 84 runs east-west along its southern boundary. A westbound on-ramp connects Route 9 to Route 84 at this location.
[791] On October 30, 1986, the Planning Board issued its approval of petitioners’ site plan. The approval, however, contained the condition that "[i]f required by [respondent Department of Transportation], [petitioners] shall relocate the existing ramp in the northwest quadrant of the Route 9/1-84 interchange”. Petitioners then began construction of the development. On July 24, 1987, they applied to the Department of Transportation (hereinafter DOT) for a permit to construct, inter alia, access driveways. On September 14, 1987, DOT granted the application but stated that it was "contingent upon the receipt and approval of construction plans to realign the westbound Interstate 84 entrance ramp”. Thereafter, petitioners, on or about January 12, 1988, commenced this CPLR article 78 proceeding challenging the contingency imposed by DOT in its grant of petitioners’ permit application. Supreme Court dismissed the petition as time barred under CPLR 217 and petitioners have appealed.
Initially, the question before _us is what determination petitioners are in fact seeking to have reviewed (see, Matter of Wing v Coyne, 129 AD2d 213, 216). The true accrual point of petitioners’ cause. of action is determined by ascertaining the "focus” of their legal challenge (see, supra, at 217). Petitioners claim that they are challenging the September 14, 1987 decision by DOT, while respondents argue that, in reality, petitioners are challenging the provisions of the site plan approval which was issued on October 30, 1986. If petitioners are correct, they are within the four-month time limitation provided for in CPLR 217; if respondents are correct, then petitioners have not timely commenced their proceeding.
While the petition on its face challenges only DOT’s determination, it is the requirement that petitioners realign the westbound entrance ramp that they are contesting. Petitioners had already been notified of this requirement previously in the Planning Board’s site plan approval wherein it specifically conditioned the approval by stating that "[i]f required by [DOT], [petitioners] shall relocate” the westbound entrance ramp. Therefore, the focus of petitioners’ challenge is in reality on the site plan approval.
Furthermore, the site plan approval became "final and binding” (CPLR 217) on petitioners on the date it was issued. It was at that point that it had its "impact” on petitioners (see, Matter of De Groat v New York State Higher Educ. Servs. Corp., 90 AD2d 616, 617), and it was then that petitioners became "aggrieved” (see, Matter of Martin v Ronan, 44 NY2d 374, 380). The fact that the site plan approval was conditioned [792] upon DOT’s possibly later requiring that petitioners install the westbound ramp does not make the determination any less final or conclusive (see, Matter of Public Serv. Commn. v Rochester Tel. Corp., 55 NY2d 320; Matter of Palmer v New York State Dept. of Envtl. Conservation, 132 AD2d 996). The site plan approval put petitioners on notice that the Planning Board was requiring them to construct the ramp if DOT decided that it was petitioners’ responsibility to do so. Additionally, contrary to petitioners’ claim, simply because the initial determination was made by the Planning Board while the second determination was made by DOT, a different agency, does not warrant a different conclusion. Supreme Court, therefore, properly found the proceeding time barred since it was not commenced within four months of the Planning Board’s October 30, 1986 decision.
Footnotes
149 A.D.2d 790 (Westage Development Group, Inc. v. White) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.