West v. Pinkston

138 P. 1152, 44 Utah 123, 1914 Utah LEXIS 10
CourtUtah Supreme Court
DecidedJanuary 30, 1914
DocketNo. 2505
StatusPublished
Cited by5 cases

This text of 138 P. 1152 (West v. Pinkston) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West v. Pinkston, 138 P. 1152, 44 Utah 123, 1914 Utah LEXIS 10 (Utah 1914).

Opinion

FRICK, J.

This was an action by a subcontractor to foreclose a mechanic’s lien. The complaint was directed against the original contractor and the owner of the premises, and is in the usual form in such actions. The contractor answered the complaint, but his answer is not material here and will not be further noticed. The owner of the premises, who is the respondent here, also answered the complaint, setting up two [125]*125■defenses, one negative and the other affirmative; the latter being in the nature of an estoppel. The case was tried to the court, who made findings of fact and conclusions of law ■against the appellant; and judgment was duly entered thereon, to reverse which this appeal is prosecuted.

The findings of fact fairly reflect both the pleadings and the evidence, and we shall state the material parts thereof in place of a statement of facts.

The court found that prior to the 1st day of August, 1910, Mary L. Albaugh, hereafter called “respondent,” entered into a contract with her corespondent, E. M. Pinkston, hereafter designated “contractor,” whereby the latter agreed to ■erect and complete a dwelling house for her upon certain premises owned by her for the agreed price of $3015; that on or about the 1st day of August aforesaid said contractor sublet to appellant the mason work required for said dwelling at the agreed price of $850; and that said work was performed between the 1st and the 26th days of August, 1910, as agreed upon by appellant, and he then became entitled to said sum of $850 for said work; that on or about the 2d day of September, 1910, the contractor, in payment for said work, made and delivered his personal check to appellant for said sum of $850, at which time appellant delivered to the contractor a receipt in full, which receipt was made and delivered to enable the latter to obtain the money due him on the contract price from respondent; that said contractor, within a few days thereafter, exhibited said receipt to the respondent, stating to her that he had paid the appellant for the work aforesaid; that, relying upon said receipt and the representations of said contractor, respondent paid him the sum of $900 to apply on the building contract; that, when said contractor delivered his check as aforesaid to appellant, it was agreed between them that the check should not he presented for payment for a few days so as to give the contractor time to obtain the necessary money from respondent and deposit the same in the bank on which the cheek was drawn; that, after said contractor received said sum of $900 as aforesaid, he did not deposit the same in the bank, and [126]*126refused to pay tbe same, or any part thereof, to appellant,, and at no time paid the latter said sum of money or any part thereof for said work; that, when respondent paid said sum of $900 as aforesaid to the contractor, she did not know, nor was she informed in any way that the said contractor had not paid appellant as shown by said receipt, but she then believed, and acted upon such belief, that appellant had received payment in full for said work, and that she would not have paid said money to said contractor had she known or been informed that appellant had not been paid in full as indicated by his receipt, and that by reason of the premises she was deceived; that, “since said payment of said $900 to the defendant Pinkston by the defendant Albaugh, the defendant Albaugh has not paid to the defendant Pinkston any sum of money or any other thing on account of said contract or contract price, except payments to other subcontractors of said Pinkston in payment for and discharge of their several valid claims, demands, and liens, and rights to liens upon said premises for the completion of the said contract with the said defendant Albaugh; that at the time this suit was begun all of said contract price had been so and properly paid out by the defendant Albaugh towards the finishing and completion of said dwelling house except the sum of $222.07; that before this suit was begun the defendant Albaugh advised the plaintiff (appellant) that the defendant Albaugh would, upon the completion of said house and contract of said Pink-ston, account to the said plaintiff and protect him to the extent of any moneys remaining due upon said contract with said Pinkston, and said Albaugh has at all times been able, ready, and willing to do the same; that this suit was prematurely brought; that the plaintiff is estopped to maintain this action; that in open court, during the trial of this cause, the defendant Albaugh offered to do equity and to submit to judgment in this cause notwithstanding said suit was prematurely brought for the said balance remaining in her hands, and which said balance is $282.72, except that the defendant Albaugh insisted and insists on an abatement of said sum in the amount of her costs and attorney’s fees in this [127]*127suit; that there is still due and unpaid on the original contract between defendant Albaugh and defendant Pinkston the sum of $222.07, and still due and unpaid on account of extras the sum of $60.65, and in equity the plaintiff (appellant) is entitled to the same as against the defendant Pinkston.” The court also found that appellant had complied with the provisions of our statute respecting the filing •of a mechanic’s lien and that he was entitled to the sum of twenty-five dollars as attorney’s fee as against the contractor.

Upon the foregoing facts the court entered conclusions of law that appellant is entitled to judgment against the respondent Albaugh in the sum of $282.72, without costs, and' that the costs of respondent, including an attorney’s fee of twenty-five dollars for defendant the mechanic’s lien proceedings amounting to twenty-five dollars be deducted' therefrom; that appellant is entitled to judgment against Pink-ston, the contractor, for the full amount of $850 with interest, and for twenty-five dollars as attorney’s fee, and for his costs and expenses of preparing and filing his lien. Judgment was entered accordingly.

While appellant’s counsel has assigned numerous errors, he, in his brief, has reduced all of them to two propositions: (1) That the trial court erred in holding that appellant by kis conduct,. had estopped himself from enforcing or had waived his right to enforce a mechanic’s lien against respondent and her property; and (2) that it erred in holding that the appellant was not entitled to enforce his lien to the extent of the balance remaining in respondent’s hands, and that he could not recover costs and attorney’s fee as against her.

1,2 The first proposition seems to be based very largely upon the fact that, after appellant had failed to obtain the money from the contractor, he went to see the architect of the building in question, and that he (the architect) and the lumber company, which had obtained the money from the contractor, and the contractor then entered into an arrangement whereby the lumber company agreed that it would waive its right to a lien against the dwelling [128]*128bouse in question to tbe extent of $1000 in consideration of baying received tbe money paid to tbe contractor as aforesaid. In view of tbis arrangement, counsel for appellant argues tbat respondent was practically placed just where sbe-was before sbe bad paid tbe money to tbe contractor, so far,, at least, as tbe right to file liens against her dwelling was concerned. It should, however, be remembered tbat respondent was not a party to tbe foregoing arrangement and bad no part or share in it, and therefore is not to be bound as a party thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JP Koch, Inc. v. JC Penney Company, Inc.
534 P.2d 903 (Utah Supreme Court, 1975)
Hutchison Bros. Excavating v. Dworman
307 A.2d 760 (District of Columbia Court of Appeals, 1973)
G. R. Sponaugle & Sons, Inc. v. McKnight Construction Co.
304 A.2d 339 (Superior Court of Delaware, 1973)
Detroit Graphite Co. v. Carney
1935 OK 1151 (Supreme Court of Oklahoma, 1935)
Stewart Lumber Co. v. Unique Home Builders, Inc.
294 P. 988 (Washington Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
138 P. 1152, 44 Utah 123, 1914 Utah LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-v-pinkston-utah-1914.