West Coast Construction Co. v. Oceano Sanitary District

17 Cal. App. 3d 693, 95 Cal. Rptr. 169, 1971 Cal. App. LEXIS 1517
CourtCalifornia Court of Appeal
DecidedMay 19, 1971
DocketCiv. 36894
StatusPublished
Cited by23 cases

This text of 17 Cal. App. 3d 693 (West Coast Construction Co. v. Oceano Sanitary District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Coast Construction Co. v. Oceano Sanitary District, 17 Cal. App. 3d 693, 95 Cal. Rptr. 169, 1971 Cal. App. LEXIS 1517 (Cal. Ct. App. 1971).

Opinion

Opinion

LILLIE, J.

In February of 1969 plaintiff instituted an action against defendant (hereinafter referred to as “District”) and others in which damages —for breach of contract involving the construction of a sewer, system and by reason of certain tortious acts—were demanded; in connection therewith, an injunction was also sought to prevent the District from expending or disbursing any monies for the construction of such sewer system except as should be necessary to maintain it in its then condition. After a hearing on February 21, at which proof was presented, a preliminary injunction was granted. Almost 11 months later, on plaintiff’s application, the injunction was broadened in scope; specifically, the District was enjoined during the pendency of the action from expending monies from a specified sewer construction fund either for payments to any contractor other than plaintiff, attorney’s fees and other costs of litigation, or the employment of experts and expert witnesses. The District appeals from the order granting the foregoing restraints.

On July 1, 1967, a written contract was entered into between plaintiff *697 and the District to construct the sewer system in question. As construction progressed, plaintiff received monthly progress payments of which 10 percent was retained by the District as security for plaintiff’s fulfillment of the contract. As of November 2, 1967, the District was delinquent to the extent of approximately $139,000 in progress payments; plaintiff then stopped construction and filed a claim (Gov. Code, § 910) for $244,-540.63, representing the above delinquency and other items (including damages for breach of contract). In an effort to find some way of completing the project and settling plaintiff’s claim, extensive negotiations were carried on between the parties and the Farmers Home Administration (United States Department of Agriculture), referred to as “FHA” which originally had purchased $400,000 of the District’s general obligations bonds and $150,000 of its revenue bonds to finance the project. At the District’s request, on February 5, 1968, plaintiff submitted a lump sum bid of $213,000 to complete the project conditioned on the raising by the District of sufficient funds to pay other items set forth in plaintiff’s claim with security therefor, including the retention monies held by the District. On March 19, 1968, the District represented to plaintiff that FHA would purchase an additional $50,000 of its revenue bonds, also, that the District would receive a grant from FHA in the sum of $150,000. It was further represented that these funds, along with the balance of construction funds on hand (assertedly $220,000), would enable the District to meet plaintiff’s demands and allow it to deposit in escrow the sum of $42,949.65 to secure payment of one item set forth in plaintiff’s claim. On March 25, 1968, according to the declaration of plaintiff’s counsel (Mr. Weaver), the District further represented through its administrative officer (Mr. Butch) that after receipt of the bond and grant proceeds, the total funds available for payment of construction costs, as well as the deposit in escrow of the sum above mentioned, amounted to $416,949.65; in addition, according to the declaration, Mr. Butch stated that the District would have $13,300 available for engineering fees, bond costs, attorney’s fees and other incidentals connected with the completion of the project.

On March 28, 1968, allegedly on the basis of the above representations plaintiff entered into an agreement with the District entitled “Agreement of Release, Compromise and Settlement,” the breach of which is pleaded in plaintiff’s first cause of action. In its second cause of action, injunctive relief is asked upon the ground of the District’s alleged insolvency and its actions in employing other contractors, both resulting in plaintiff’s inability to recover the monies due it under the agreement in question. The instant action was commenced on February 10, 1969, some four days after plaintiff again discontinued work on the project which it had previously resumed upon execution of the settlement agreement; a temporary *698 restraining order was obtained on the basis of the matters set forth in plaintiff’s second cause of action. After an order to show cause hearing on February 21, 1969, a preliminary injunction (the form of which was prepared by counsel for the District) was issued by the court (Judge O’Reilly) on February 24, 1969; thereunder it was ordered that the District not spend any construction or FHA funds for the engagement of contractors other than plaintiff, the latter also being ordered to return to the job of construction within 15 days. On April 8, 1969, the court refused to dissolve the injunction after a complaint by the District that plaintiff was in contempt. Thereafter, on August 21, 1969, the District filed its answer, accompanied by a coúnterclaim, its demurrer to the complaint having been previously overruled.

On December 2, 1969, the plaintiff’s counsel was mailed a copy of a letter written by counsel for the District (Mr. Shipsey) to Judge O’Reilly wherein he stated that “the restraining order in effect does not restrict a payment of funds for litigation expense” although “it does prevent use of those funds for employment of any contractor other than West Coast Construction Co., Inc. . . .” Thereafter plaintiff sought to broaden the provisions of the existing injunction. To that end a temporary restraining order was obtained on December 8, returnable December 24 based on the declaration of its counsel (Mr. Weaver) that the District intended to divert approximately $20,000 from the FHA sewer grant fund to furnish the District with an engineering report in connection with the instant litigation, that the District was already indebted to plantiff in the sum of $103,146, exclusve of its claim for damages, and that the balance of such FHA fund was only $55,512.

After four appearances and four continuances of the hearing-on the return of the temporary restraining order, the matter was heard on January 15, 1970, resulting in a preliminary injunction the scope of which was broadened to enjoin the diversion of funds for any litigation expenses whatsoever. It is this order which is here challenged.

Although the District’s counsel (Mr. Shipsey) was present in court on all four occasions when the matter was continued, even though on the fourth occasion (January 5) plaintiff’s counsel was not present, on the following day (January 6), Mr. Shipsey filed a counterdeclaration in opposition to the injunction sought, and the District participated in the hearing held on January 15, it is now for the first time contended that the issuance of the injunction was in excess of the court’s jurisdiction because the order to show cause, dated December 8, was made returnable on December 24, 16 days later and, therefore, more than the 15 days prescribed in section 527, Code of Civil Procedure. Plaintiff,recognizes that *699 decisions, including Agricultural Prorate Com. v. Superior Court, 30 Cal.App.2d 154, 155 [85 P.2d 898], support the above claim; significantly, however, in Agricultural Prorate Com. the continuance was over defendants’ objection and without their consent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dunlevie v. Valletta CA4/2
California Court of Appeal, 2021
Sweegen v. Chen CA4/3
California Court of Appeal, 2021
Rosilho v. Young CA2/4
California Court of Appeal, 2014
People v. Financial Casualty & Surety CA4/1
California Court of Appeal, 2014
People v. Accredited Surety and Casualty etc.
220 Cal. App. 4th 1137 (California Court of Appeal, 2013)
MALATKA v. Helm
188 Cal. App. 4th 1074 (California Court of Appeal, 2010)
Adler v. Vaicius
21 Cal. App. 4th 1770 (California Court of Appeal, 1993)
Friedman v. Friedman
20 Cal. App. 4th 876 (California Court of Appeal, 1993)
Paradise Hills Associates v. Procel
235 Cal. App. 3d 1528 (California Court of Appeal, 1991)
Doyka v. Superior Court
233 Cal. App. 3d 1134 (California Court of Appeal, 1991)
Chico Feminist Women's Health Center v. Scully
208 Cal. App. 3d 230 (California Court of Appeal, 1989)
Cabrera v. Plager
195 Cal. App. 3d 606 (California Court of Appeal, 1987)
Heckmann v. Ahmanson
168 Cal. App. 3d 119 (California Court of Appeal, 1985)
Alliance Bank v. Murray
161 Cal. App. 3d 1 (California Court of Appeal, 1984)
Gurrola v. County of Los Angeles
153 Cal. App. 3d 145 (California Court of Appeal, 1984)
J&K Cement Construction, Inc. v. Montalbano Builders, Inc.
456 N.E.2d 889 (Appellate Court of Illinois, 1983)
Volpicelli v. Jared Sydney Torrance Memorial Hospital
109 Cal. App. 3d 242 (California Court of Appeal, 1980)
International Molders & Allied Workers Union v. Superior Court
70 Cal. App. 3d 395 (California Court of Appeal, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
17 Cal. App. 3d 693, 95 Cal. Rptr. 169, 1971 Cal. App. LEXIS 1517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-coast-construction-co-v-oceano-sanitary-district-calctapp-1971.