Wescott v. Bunker

22 A. 388, 83 Me. 499, 1891 Me. LEXIS 78
CourtSupreme Judicial Court of Maine
DecidedMay 29, 1891
StatusPublished
Cited by3 cases

This text of 22 A. 388 (Wescott v. Bunker) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wescott v. Bunker, 22 A. 388, 83 Me. 499, 1891 Me. LEXIS 78 (Me. 1891).

Opinion

Whitehouse, J.

The defendant Bunker made a contract to build the "Whiting cottage” and stable appurtenant at Hull’s Cove, in Eden, for $15,000 and orally sublet to the plaintiff the stone work and masonry for the sum of $4550. The plaintiff furnished labor and materials to complete his original undertaking, and also performed extra work at the request of the owner of the premises of the value of $121.50. The payments ■credited amounted to $4238.68, leaving a balance duo of $432.82, and interest. The case shows that, under the instructions of the court, there was a finding by the jury that the plaintiff had a lien to secure payment of this balance of $466.57, ■on the buildings described for the labor and materials thus ■furnished in their erection. But it was contended in behalf of the owner, who appeared in defense, that this lien was dissolved by reason of the plaintiff’s failure to observe the requirements [503]*503of the statute in his proceedings to preserve and enforce his lien, and hence that no valid judgment can be rendered against the real estate. The court ruled otherwise, and the defendant took exceptions.

It is provided by section 30, ch. 91, E. S., that "whoever performs labor or furnishes labor or materials in erecting, altering or repairing a house, building or appurtenances by virtue of a contract with or by consent of the owner, has a lien thereon, and on the land on which it stands,” &c. By section 32 of the same chapter: "The lien mentioned in the preceding sections shall be dissolved unless the claimant within thirty days after he ceases to labor or furnish materials as aforesaid, files in the office of the clerk of the town in which such building is situated, a true statement of the amount due him with all just credits given,” etc. It is further provided by section 33, that "no inaccuracy in such statement relating to said property, if the same can be reasonably recognized, or in stating the amount due for labor or materials, invalidates the proceedings unless it appears that the person making it wilfully claims more than his due.”

Seeking to comply with these provisions the plaintiff duly filed the following statement of his account, alleging in the language of the statute that it was a "true statement of the amount due with all just credits given:”

"To labor and materials furnished upon "Whiting Cottage from July 1, 1887, to and including October 10, 1888,
$4550 00
To extra plastering, 6 50
To putting rollway to cellar, 50 00
To stone work under tower windows 65 00
$4671 50
Credit by order, $1150 00
Credit by cash, 3088 68
$4238 68
Balance due, $432 82”

[504]*504The contract was an entirety. The plaintiff was to perform certain work for a round sum. Iiis statement of the amount due him does not comprise a detailed and itemized account of the labor performed and materials furnished, but gives only the aggregate price of the undertaking as stipulated in the contract.

The plaintiff was a sub-contractor. His contract was not made with the owners of the real estate; and It is contended in limine, that in case of a sub-contractor, such a general statement of the amount of Ms claim is not sufficient to preserve the lien, but that a particular account of the transactions which are the foundation of it should be required.

It might be sufficient to observe upon this, point that the legislature has not seen fit to require such a specification of items. The section of the statute quoted (Sec. 32,) is applicable to all claimants. It makes no distinction between a contractor and a sub-contractor. It is proper to be reminded that the office of the court is jus dicere, not jus dare; and it might well be deemed an assumption of legislative powers to impose on the sub-contractor a burden not required by the express terms of the statute.

But numerous adjudications may be found in other jurisdictions based upon statutes having a scope and purpose closely resembling our own, making a distinction between the case of an original contractor and a sub-contractor with respect to the degree of particularity required in filing the lien account, and holding that a sub-contractor is bound to set out the items of his claim for the information and protection of the owner and of purchasers and others who may become interested in the property subjected to the lien. In Maryland, for instance, where the first attempt appears to have been made in this country to create a mechanic’s lien on buildings it was held, in case of a sub-contractor, that the notice or claim of lien should be specific as to the labor performed and materials furnished, to prevent fraud and collusion between contractor and sub-contractor and to enable the owner to ascertain the correctness and reasonableness of the demand. Carson v. White, 6 Grill, 17. So also in Pennsylvania, the second state to enact [505]*505a lien law in favor of mechanics, when the claim filed under the act of 1845, was based on a special contract with the owner, the contractor was not required to set out the nature or kind of work done or the kind or amount of materials furnished, as provided in other cases under the act of 1836. But in Lee v. Burke, 66 Penn. 336, Sharswood, J., says : "The act of 1845, was intended to prov ide for the case of a special contract made by a mechanic, with the owner for the erection of a building. The reason for requiring these particulars to be filed does not exist in the case of a special contract for a round sum of money. Censante ratione cessat et ipsa lex. But it is entirely different when the contract of the mechanic, though it may be for a round sum is not with the owner, but with a contractor under him. The contractor cannot bind the building by any special contract for more than the materials furnished and the work done at their fair market price.” And in Cray v. Dick, 97 Penn. 142, it was held that the statute of 1849, which allows the filing of a statement of the aggregate price of the work and materials where there is a contract for a stipulated sum, applies only to the original contractor notwithstanding- its general terms. The Court says : "The sub-contractor is entitled to no more than the fair market value of the work done and the materials furnished on the credit of the building, and hence the owner should be informed by the claim filed as to the particulars of the claim that he may make the necessary inquiries to satisfy himself as to its justice as a lien on his property. The agreement between the contractor and sub-contractor is not the measure of the owner’s responsibility; his building is bound for no more than the value of the work done and the materials furnished by the sub-contractor.” See also Rude v. Mitchell, 97 Mo. 365, and notes in American Law Review, Vol. 24, No. 5, page 857; Phillips on Mechanic’s Liens, sections 349-352; 2 Jones on Liens, sections 416-467.

The several kinds of privilegium recognized and allowed by the provisions of the civil law evidently formed the ground-work of the more complete and beneficent systems which have gradually been adopted in the American States. See Domat’s Civil Law, Strahan, sections 1742, 1744, and 1745. The [506]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pineland Lumber Co. v. Robinson
382 A.2d 33 (Supreme Judicial Court of Maine, 1978)
Moore v. Parish
45 N.E. 573 (Illinois Supreme Court, 1896)
Maynard v. Ivey
29 P. 1090 (Nevada Supreme Court, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
22 A. 388, 83 Me. 499, 1891 Me. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wescott-v-bunker-me-1891.