Werneberg v. Pittsburg

59 A. 1000, 210 Pa. 267, 1904 Pa. LEXIS 883
CourtSupreme Court of Pennsylvania
DecidedDecember 31, 1904
DocketAppeal, No. 80
StatusPublished
Cited by7 cases

This text of 59 A. 1000 (Werneberg v. Pittsburg) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Werneberg v. Pittsburg, 59 A. 1000, 210 Pa. 267, 1904 Pa. LEXIS 883 (Pa. 1904).

Opinions

Opinion by

Mb. Justice Mestrezat,

W. E. Howley & Company by a contract in writing dated September 16, 1896, agreed with the city of Pittsburg to construct a street in the city, known as Grant Boulevard, beginning at Seventh avenue and extending to Center avenue, a distance of about three miles. Howley & Company failed to begin the work, and on November 19, 1896, the contract, with the consent of the city and the surety of Howley & Company, was assigned to Werneberg, Sheehan & Company, the legal plaintiffs and appellants, who began the work on November 23, 1896, and completed it on March 26, 1901. The contract provided that the work should be commenced October 1, 1896, and be completed on or before May 1, 1898 which was subsequently extended until October 1, 1898. During the progress of the work, the plaintiffs were paid by the city from time to time according to the contract price on estimates of the amount due made by the director of the department of public works. On the completion of the street, March 26, 1901, the director made a final estimate of the entire work done and materials furnished under the contract and found a balance of $6,715.29 due the plaintiffs.

The contract contains two clauses relating respectively to arbitration and to measurements which bear upon the questions raised on this appeal. The arbitration clause provides that “ in case any question or dispute shall arise between the parties of the second part hereto and the said city of Pittsburg, party of the first part hereto, under the said plans, drawings, descriptions, general specifications, general conditions or terms of this contract, respecting the quality, quantity, or value of the work or labor done, or materials furnished or to be done or furnished, or any of the terms, stipulations, covenants or agreements herein contained, or respecting any claim for extra work, or respecting any matter pertaining to this contract, or [272]*272any part of the same, said question shall be referred to the director of the department of public works of the city of Pitts-burg, whose decision thereon shall be final, binding and conclusive upon all parties, without exception or appeal, and all right or rights of any action at law or in equity under and by virtue of this contract, and all matters connected with and relative to the same are hereby expressly waived by the parties of the second part.” The measuremeijt or estimate clause is, inter alia, as follows: “ It being expressly understood and agreed by the parties hereto that the measurements shall be taken after the completion of the work, and the estimate and certificate of the director of the department of public works shall be final and conclusive evidence of the amount of work performed by the said contractor under and by virtue of this agreement and shall be taken as the full measure of compensation to be received by the contractor, without the right of exception or appeal.”

At the time of the execution of tl e contract Edward M. Bigelow was the director of public works of the city of Pitts-burg and continued in office until June 11, 1900, when he was succeeded by George W. Wilson, who held the office until June 11, 1901, when he was removed by the recorder of the city and was succeeded by his predecessor, Mr. Bigelow, who continued in office until November 25, 1901, and was then succeeded by J. Guy McCandless, who held the office until April 1, 1903, when he was succeeded by Mr. Bigelow who was again appointed and has since continued to ¿old the office.

On the completion of the work in March 1901, the plaintiffs submitted to George W. Wilson, then director of the department of public works, a claim against the city for damages growing out of the contract and over and above the contract price of the work, aggregating $384,944.07. On April 6,1901, director Wilson, after notice to the parties, satas arbitrator under the terms of the contract and heard the claims of the plaintiffs and defendant. Before the director made his award, however, he was removed from office by the recorder of the city on June 11, 1901, and thereafter Reclined to complete the arbitration by rendering a decision up<jm the matters submitted to and heard by him. On May 12, 1902, more than a year after the work had been completed and i;he final estimates of the [273]*273amounts due according to the contract price had been made, J. Guy McCandless, then director of the department of public works, notified the parties that he would sit as arbitrator to determine the dispute between them under the arbitration clause of the contract. The plaintiffs denied his authority to sit as arbitrator and refused to appear before him. The director, however, proceeded with the arbitration and after hearing the testimony offered by the city and considering the proofs filed by the plaintiffs with director Wilson at the former arbitration, made a decision in writing on February 10, 1903, awarding to the plaintiffs the sum of $34,120.

The plaintiffs brought this action July 31, 1901, to recover the claim for damages which they had submitted to director Wilson for adjustment under the arbitration clause of the contract. A verdict was rendered for the plaintiffs for $134,427.64, increased by agreement to $140,040.41, subject to the question whether there was any evidence which entitled the plaintiffs to recover. Subsequently, the trial court entered judgment non obstante veredicto in favor of the defendant, holding that the arbitration clause vested jurisdiction in the director of the department of public works and that the proceedings before director Wilson were incomplete at the time he was removed from office and that thereafter he had no authority to make a decision; and further that the adjudication of director McCandless was final and conclusive on both parties and estops the plaintiffs from maintaining this action. The learned judge further held that if he were in error as to the effect of the arbitration clause of the contract, the final estimate clause would prevent the plaintiffs from recovering in the action. These are the two reasons assigned by the court for entering judgment for the defendant.

The errors complained of on this appeal are the entering of judgment non obstante veredicto for the defendant and in admitting in evidence on the trial of the cause, against the objection of the appellants, the award of director McCandless. The appellants contend that as the dispute between the parties arose while George W. Wilson was director of the department of public works, and it having been submitted to, and heard by,- him and he having been removed from office by the city before making an adjudication and thereafter declin' [274]*274ing to make a decision, the common-law jurisdiction of the courts attached. It is denied by the appellants that the measurement clause of the agreement prevents them from demanding and recovering the damages claimed in this action as held by the trial court.

that as Wilson was re-his authority to act as Vhat he did. in the mat-1. The first and controlling question for determination is the effect to be given to the reference' of the matters in dispute to director Wilson and his failure to make a decision thereon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seaboard Surety Co. v. Commonw'lth.
27 A.2d 27 (Supreme Court of Pennsylvania, 1942)
Canuso v. Philadelphia
192 A. 133 (Supreme Court of Pennsylvania, 1937)
Pittsburgh Union Stock Yards Co. v. Pittsburgh Joint Stock Co.
163 A. 668 (Supreme Court of Pennsylvania, 1932)
Commonwealth v. Eastern Paving Co.
136 A. 853 (Supreme Court of Pennsylvania, 1927)
Commonwealth v. Eastern Paving Co.
8 Pa. D. & C. 357 (Dauphin County Court of Common Pleas, 1926)
Holscher v. Ingalls Stone Co.
66 Pa. Super. 76 (Superior Court of Pennsylvania, 1917)
Wilbert v. Weicht
62 Pa. Super. 361 (Superior Court of Pennsylvania, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
59 A. 1000, 210 Pa. 267, 1904 Pa. LEXIS 883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/werneberg-v-pittsburg-pa-1904.