Welsbach Electric Corp. v. MasTec North America, Inc.

23 A.D.3d 639, 804 N.Y.S.2d 805

This text of 23 A.D.3d 639 (Welsbach Electric Corp. v. MasTec North America, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Welsbach Electric Corp. v. MasTec North America, Inc., 23 A.D.3d 639, 804 N.Y.S.2d 805 (N.Y. Ct. App. 2005).

Opinion

In an action, inter alia, to recover damages for breach of contract, the defendant appeals from so much of an order of the [640]*640Supreme Court, Queens County (Glover, J.), dated January 6, 2004, as granted that branch of the plaintiffs motion which was to dismiss its fifth and eleventh affirmative defenses.

Ordered that the order is affirmed insofar as appealed from, with costs.

In September 1999 the defendant, an entity incorporated in the State of Florida, entered into a primary contract with Telergy Metro LLC (hereinafter Telergy), a nonparty, to serve as general contractor for a construction project in New York City. The primary contract included a termination clause which provided the defendant with a right to terminate the contract if Telergy became insolvent.

Thereafter, on or about November 28, 2000, the defendant entered into an agreement with the plaintiff to serve as a subcontractor for the project (hereinafter the subcontract). The subcontract, which was governed by Florida law, included a “pay-when-paid” provision which made the defendant’s obligation to pay the plaintiff contingent upon and subject to the defendant’s receipt of payment from Telergy for work performed. The subcontract also included a termination provision which provided that upon termination of the primary contract, the subcontract would also be terminated upon the same basis and upon the same effective date as the primary contract.

When Telergy became insolvent in August 2001, the primary contract and the subcontract were both terminated. Neither the plaintiff nor the defendant received payment for work performed on the project.

The plaintiff subsequently commenced this action to recover moneys allegedly due and outstanding under the subcontract. The defendant asserted, inter alia, as affirmative defenses that the pay-when-paid provision and the termination provision of the subcontract relieved it of any payment obligation. Thereafter, the plaintiff moved, among other things, for summary judgment dismissing those affirmative defenses, and the Supreme Court granted that relief. We affirm.

Generally, the courts of this State will uphold choice-of-law provisions unless the jurisdiction whose law is to be upheld has no reasonable relation to the subject agreement, or enforcement of the provision would violate a fundamental public policy of this State (see Cooney v Osgood Mach., 81 NY2d 66, 78-79 [1993]; Schultz v Boy Scouts of Am., 65 NY2d 189, 202 [1985]; Culbert v Rols Capital Co., 184 AD2d 612, 613 [1992]).

The New York Court of Appeals stated in Schultz v Boy Scouts of Am. (supra at 202) that: “Public policy is found in the State’s [641]*641Constitution, statutes and judicial decisions and the proponent of the exception must establish that to enforce the foreign law ‘would violate some fundamental principle of justice, some prevalent conception of good morals, some deep-rooted tradition of the common weal’ expressed in them (Loucks v Standard Oil Co., [224 NY 99, 111 (1918)]. In addition, the proponent must establish that there are enough important contacts between the parties, the occurrence and the New York forum to implicate our public policy and thus preclude enforcement of the foreign law.”

Although the pay-when-paid provision at issue is enforceable under Florida law (see Everett Painting Co., Inc. v Padula & Wadsworth Constr., Inc., 856 So 2d 1059 [2003] [Fla App]), the New York Court of Appeals held in West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co. (87 NY2d 148 [1995]) that a pay-when-paid provision which forces a subcontractor to assume the risk that the owner will fail to pay the general contractor is void and unenforceable as contrary to public policy as set forth in Lien Law § 34.

Lien Law § 34, as amended in 1975 (L 1975, ch 74, § 1), provides: “Notwithstanding the provisions of any other . . . law, any contract, agreement or understanding whereby the right to file or enforce any lien created under article two is waived, shall be void as against public policy and wholly unenforceable.” (Emphasis added.)

The Lien Law is remedial in nature and intended to protect those who have expended labor or materials to improve real property at the direction of the owner or general contractor (see West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co., supra at 157).

In West-Fair, the New York Court of Appeals reviewed the Legislature’s intent in enacting Lien Law § 34 in reaching its determination that the pay-when-paid provision at issue was contrary to public policy. The Court of Appeals acknowledged that the sponsor of the bill which the Legislature ultimately enacted as Lien Law § 34 stated: “ ‘Since the year 1897 the Legislature has recognized the need to afford protection to those who furnish work, labor and services or provide materials for the improvement of real property. Throughout the succeeding years changes in the law have been enacted to clarify, enlarge and perfect the right of those who improve real property to be paid. The Lien Law has been the sole vehicle through which such interests may gain a measure of protection ... It has become prevalent in the construction industry to require contractors, subcontractors, materialmen and laborers to sign contracts or subcontracts containing clauses which waive the [642]*642right of the signator to file or enforce his mechanic’s [sic] lien. This legal barrier is thus imposed long before any work is performed or materials furnished. The surrender of such protective rights as a prerequisite to obtaining a contract or subcontract is repugnant, against public policy and should be void’ (Mem of Senator Donovan, L 1975, ch 74, 1975 NY Legis Ann, at 341)” (West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co., supra at 156-157 [emphasis added]).

While we agree with our dissenting colleague that the foreign jurisdiction (i.e., the State of Florida) has a reasonable relationship to the subject agreement (see generally Finucane v Interior Constr. Corp., 264 AD2d 618, 620 [1999]) predicated on the defendant’s incorporation in Florida and the underlying Florida choice-of-law provision, we nonetheless find that enforcement of the pay-when-paid provision would violate the public policy of this State (see West-Fair Elec. Constr. v Aetna Cas. & Sur. Co., supra).

Our dissenting colleague relies on the decision of the Appellate Division, First Department, in Hugh O’Kane Elec. Co., LLC v MasTec N. Am., Inc. (19 AD3d 126 [2005]), in which that court determined that the pay-when-paid provision at issue was valid pursuant to the parties’ Florida choice-of-law provision, and that the prohibition against this type of provision is not a deeply rooted tradition of this State. However, we do not find the reasoning and conclusion of the Appellate Division, First Department, in O’Kane to be persuasive.

In reaching its conclusion, the Appellate Division, First Department, indicated in O’Kane that between 1929 (when Lien Law § 34 was originally enacted) and 1975 (when Lien Law § 34 was amended), subcontractors could waive their lien rights by express agreement in writing, and before that, at common law, presumably could do so orally (see Hugh O'Kane Elec. Co., LLC v Mas Tech N. Am., Inc., supra at 127). The First Department also acknowledged that “[e]ven after the enactment of current section 34 in 1975, it was not clear that pay-when-paid provisions were covered . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)
Loucks v. . Standard Oil Co.
120 N.E. 198 (New York Court of Appeals, 1918)
Cooney v. Osgood Machinery, Inc.
612 N.E.2d 277 (New York Court of Appeals, 1993)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Hugh O'Kane Electric Co. v. MasTec North America, Inc.
19 A.D.3d 126 (Appellate Division of the Supreme Court of New York, 2005)
Crown Plastering Corp. v. Elite Associates, Inc.
166 A.D.2d 495 (Appellate Division of the Supreme Court of New York, 1990)
Culbert v. Rols Capital Co.
184 A.D.2d 612 (Appellate Division of the Supreme Court of New York, 1992)
David Fanarof, Inc. v. Dember Construction Corp.
195 A.D.2d 346 (Appellate Division of the Supreme Court of New York, 1993)
Marine Midland Bank, N. A. v. United Missouri Bank
223 A.D.2d 119 (Appellate Division of the Supreme Court of New York, 1996)
Blandford Land Clearing Corp. v. National Union Fire Insurance
260 A.D.2d 86 (Appellate Division of the Supreme Court of New York, 1999)
Finucane v. Interior Construction Corp.
264 A.D.2d 618 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
23 A.D.3d 639, 804 N.Y.S.2d 805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/welsbach-electric-corp-v-mastec-north-america-inc-nyappdiv-2005.