Per Curiam:

This case was referred to Trial Commissioner Saul Richard Gamer with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 134(h). The commissioner has done so in an opinion and report filed on April 20,1972. Plaintiff has filed no exceptions to or brief on this report and the time for so filing pursuant to the rules of the court has expired. On June 15, 1972, defendant filed a motion that the court adopt the commissioner’s opinion, findings of fact and recommended conclusion of law as the basis for its judgment in this case. Since the court agrees with the opinion, findings of fact and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case, without oral argument. Therefore, plaintiff is not entitled to recover and the petition is dismissed.

OPINION OF COMMISSIONER

Gamer, Commissioner:

In 1959, plaintiff, an investor in real estate, owned certain land located on Lee Street in Knoxville, Tennessee. Pursuant to an Agreement to Lease entered [327]*327into on October 7, 1959 with, defendant, represented by an official of the Post Office Department, plaintiff constructed on such property, in accordance with plans and specifications approved by the Department, a building for its use as a bulk mail facility. Upon completion of construction, and in accordance with the Agreement to Lease, the Department, by a Lease for Post Office Quarters dated April 29, 1960, rented the building, which became known as the Lee Street Parcel Post Annex, for a term of five years at a rental of $18,000 per annum.1

At this time, plaintiff was dealing with the Department through a real estate agent (who was also an attorney). The agent, under a trusteeship arrangement with plaintiff, was the record title holder of the property. Since there is now no dispute about plaintiff’s having been the actual owner of the property (which in fact was, pursuant to the trust arrangement, subsequently reconveyed to plaintiff and his wife), the term “plaintiff” will, for convenience, sometimes be used herein, when referring to events in the period during which the trusteeship arrangement existed (1959-1964), as applicable either to plaintiff himself or his agent.

A portion of plaintiff’s claim arises from certain work performed by the construction contractor (or his subcontractors) that plaintiff employed to construct the building. Plaintiff contends that such work constituted changes or extras not called for by the approved plans and specifications, and that certain officials attached to the Knoxville Post Office and to the Post Office Department’s regional office at Memphis, Tennessee (which region was handling the details of the construction and lease of the facility), took it upon themselves, without plaintiff’s knowledge or consent, to order such changes or extras to be made by direct instructions to the construction contractor (or his subcontractors). Plaintiff maintains that he was required to pay his construction contractor $14,671.39 for such extra work; that defendant has refused to reimburse him therefor; and that the rental for the building, agreed to prior to its erection and calculated upon [328]*328plaintiff’s investment therein based upon the approved plans and specifications, did not afford such reimbursement. Plaintiff seeks payment here for such extras.

This portion of the claim is not allowable for several reasons.

One of the principal stumbling blocks is that the record is wholly unclear as to who were the officials who gave the alleged orders and instructions with respect to the particular changes or extras about which plaintiff complains. Further, where some identification is attempted, there is no showing that the individuals involved were officials vested with the requisite authority to order construction changes or extras in a situation of this kind. Without such a showing, recovery is not permissible. L. B. Samford, Inc. v. United States, 187 Ct. Cl. 714, 410 F. 2d 782 (1969).

There was no Government construction contract of the usual kind here involved. The only construction contract that was entered into was between the plaintiff and a contractor of his own selection. Since the Government was not a party to that contract, no Government official, of course, would have any authority to give work orders with respect thereto. Indeed, the record is again unclear as to what was the nature of the “orders,” “instructions,” or “directions” that were allegedly given by defendant’s officials to the construction contractor with respect to the work in question.

Further, the record is not sufficient to support plaintiff’s contention that neither he nor his agent knew about or authorized the extras. Plaintiff’s own witness, the president of the construction contracting firm, testified flatly that since his contract was with plaintiff’s agent, he would not take any instructions from any Government official about the work he was to perform; that he insisted upon an authorization from plaintiff or his agent before he performed the work in question; and that all of such work was in fact authorized and paid for by the agent.2

The only contract to which defendant was a party during the period the building was being constructed was the Agree-[329]*329meiit to Lease. If defendant desired, after construction commenced, that certain changes be made in the building which it Avas to occupy as a tenant, there was a regular procedure by which such changes could be effected and appropriate compensation made by defendant therefor in the form of additional rent. Plaintiff and his agent were familiar with this procedure because it was actually utilized. During February 1960 the Post Office Department decided that the facility should have six concrete block docks and metal canopies. It so advised plaintiff’s agent and requested a cost figure. The construction contractor’s quotation was acceptable to defendant and the extra work was authorized in the specified amount under an agreement specifically providing therefor and further providing that “the lease * * * will be considered as amended to provide payment for the work upon satisfactory completion of the same, such payment to be in a lump sum as additional rental under the lease.” The agreement was executed on defendant’s behalf by the Regional Real Estate Manager, the only Post Office Department official in the region here involved who was authorized to enter into amendatory rent agreements of this kind.3 The record contains no similar amendments to the 1959 Agreement to Lease or the 1960 lease itself with respect to any of the extras comprising the claim herein.4

Finally, since the building, including the alleged extras, was completed and occupied by defendant in 1960, and this suit was not filed until 1970, the claim, insofar as it seeks compensation for the extras as construction items, is clearly barred by the six-year statute of limitations applicable to this court.5

[330]*330As to the statute of limitations point, plaintiff argues that, even if the extras are not recoverable as construction items completed in 1960, they nevertheless are properly includable in the damages growing out of asserted breach of contract claims which accrued in 1965 and thereafter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Grant v. United States
134 Fed. Cl. 348 (Federal Claims, 2017)
Lucas v. United States
37 Cont. Cas. Fed. 76,269 (Court of Claims, 1992)
Essen Mall Properties v. United States
36 Cont. Cas. Fed. 75,942 (Court of Claims, 1990)
New America Shipbuilders, Inc. v. United States
34 Cont. Cas. Fed. 75,519 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
463 F.2d 343, 199 Ct. Cl. 324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wells-v-united-states-cc-1972.