Welfle v. Motorist Ins. Group, 06 Ca 0063-M (4-23-2007)

2007 Ohio 1899
CourtOhio Court of Appeals
DecidedApril 23, 2007
DocketNo. 06 CA 0063-M.
StatusPublished
Cited by2 cases

This text of 2007 Ohio 1899 (Welfle v. Motorist Ins. Group, 06 Ca 0063-M (4-23-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Welfle v. Motorist Ins. Group, 06 Ca 0063-M (4-23-2007), 2007 Ohio 1899 (Ohio Ct. App. 2007).

Opinion

DECISION AND JUDGMENT ENTRY
This cause was heard upon the record in the trial court. Each error assigned has been reviewed and the following disposition is made: {¶ 1} Welfle Inc. entered into a contract to remove asphalt from a bridge owned by Medina County. Welfle set its milling machine to grind too deeply, *Page 2 damaged the underlying concrete deck, and was required to reimburse Medina County for the cost of repairs. It then sought coverage under a comprehensive general liability insurance policy that The Motorist Insurance Group had issued to it. Motorist denied coverage, and Welfle brought this declaratory judgment action against it. The trial court determined that Welfle was not entitled to coverage. The issue before this Court is whether the concrete deck was either "[t]hat particular part of real property" on which Welfle was "performing operations" or "[t]hat particular part of any property" that had to be repaired because Welfle incorrectly performed work "on it." This Court affirms the decision of the trial court granting summary judgment to Motorist because the bridge deck had to be repaired as a result of Welfle incorrectly performing work on it.

I.
{¶ 2} Welfle is in the business of removing asphalt and concrete from roads and bridges so new asphalt or concrete can be applied. During 2004, it was a subcontractor on a job in Medina County to repair a box beam bridge on Friendsville Road. Welfle's assignment was to remove the existing asphalt from the concrete bridge deck so new asphalt could be applied to it. The value of its subcontract was $3,958.50.

{¶ 3} In order to remove the asphalt from the bridge deck, Welfle used a machine called a rotomill. A rotomill can be used to remove either asphalt or concrete. It is operated by a three member crew. One crewmember, the operator, stands atop the machine and controls its forward progress. The other two *Page 3 crewmembers walk beside the machine, one on each side, and watch for obstructions, such as manhole covers, ahead of the machine.

{¶ 4} The rotomill that Welfle used on the Friendsville Road Bridge has a grinding drum that is six feet six inches wide with 165 carbide bits on it. As the asphalt or concrete is being ground from the surface under the rotomill, the resulting debris is loaded onto a truck following the rotomill by way of a conveyor mounted on the back of the rotomill. The crewmembers on either side of the machine set the depth to which the drum grinds the asphalt or concrete being removed.

{¶ 5} A representative of Medina County told the Welfle crew assigned to the Friendsville Road Bridge project that there were eight inches of asphalt that needed to be removed from the bridge deck to expose the concrete. As they started making their first 6-foot-6-inch wide pass over the bridge, they set the drum to grind seven inches deep. Although crewmembers can normally hear when the bits cut into concrete underlying asphalt, the construction of the bridge apparently muffled the sound so they did not hear anything unusual. When the first truck was filled with debris and the crew stopped so that truck could be replaced by an empty truck, however, they saw that they had been cutting into the concrete bridge deck. They raised the drum to a point at which it would no longer cut into the deck and continued their first pass. Even with the drum set at this new depth, however, they again cut into the concrete deck. After they completed their *Page 4 first pass, the crew had no further problems as they removed the rest of the asphalt from the bridge deck.

{¶ 6} There was at least one point during the first pass at which the rotomill cut two inches deep into the concrete deck. This weakened the bridge deck to such an extent that, as a truck was driven over it, it cracked. Because of the damage to the bridge deck, it was necessary to pour new concrete on the entire deck.

{¶ 7} Because Medina County had incorrectly instructed Welfle that there were at least eight inches of asphalt on the bridge deck, it assumed financial responsibility for the first time Welfle's crew cut into the deck. The county maintained, however, that Welfle was responsible for the rest of the damage to the deck. Welfle contributed $39,630.59 toward repair of the bridge deck, and sought reimbursement from Motorist.

{¶ 8} Motorist declined coverage for the damage to the bridge deck based upon two exclusions found in the comprehensive general liability policy it had issued to Welfle. Welfle brought this declaratory judgment action against Motorist, and both parties moved for summary judgment. The trial court denied Welfle's motion and granted Motorist's motion. Welfle appealed to this Court.

II.
{¶ 9} Welfle has assigned three errors on appeal, but they all amount to an argument that the trial court incorrectly granted Motorist's motion for summary *Page 5 judgment and incorrectly denied its motion for summary judgment. The trial court did not err in granting Motorist's motion and denying Welfle's motion.

III.
{¶ 10} In reviewing a trial court's order ruling on a motion for summary judgment, this Court applies the same standard a trial court is required to apply in the first instance: whether there were any genuine issues of material fact and whether the moving party was entitled to judgment as a matter of law. Parenti v. Goodyear Tire Rubber Co., 66 Ohio App. 3d 826, 829 (1990). None of the historical facts in this case are in dispute. Further, insurance policies are contracts, and their interpretation is a matter of law for the court. City of Sharonville v.Am. Employers Ins. Co., 109 Ohio St. 3d 186, 187 (2006) (citingAlexander v. Buckeye Pipe Line Co., 53 Ohio St. 2d 241, paragraph one of the syllabus (1978)). The only question, therefore, is which party was entitled to judgment as a matter of law based upon the provisions of the insurance policy at issue.

{¶ 11} Motorist has argued that it was entitled to judgment as a matter of law based upon two faulty-workmanship exclusions found in the policy it issued Welfle:

2. Exclusions

This insurance does not apply to:

. . .

j. Damage To Property "Property damage" to:

*Page 6

5.That particular part of real property on which you or any contractors or subcontractors working directly or indirectly on your behalf are performing operations, if the "property damage" arises out of those operations; or

6.That particular part of any property that must be restored, repaired or replaced because "your work" was incorrectly performed on it.

Motorist's position is that the bridge deck was "[t]hat particular part of real property" on which Welfle was performing operations and the damage to the bridge deck arose from those operations. In addition, according to Motorist, Medina County had to repair the bridge deck because Welfle incorrectly performed work on it.

{¶ 12}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cincinnati v. Metro. Design
2019 Ohio 364 (Ohio Court of Appeals, 2019)
Beaverdam Contracting v. Erie Ins. Co., 1-08-17 (9-29-2008)
2008 Ohio 4953 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 1899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/welfle-v-motorist-ins-group-06-ca-0063-m-4-23-2007-ohioctapp-2007.