Weldon Farm Products, Inc. v. Commodity Credit Corp.

214 F. Supp. 678, 1963 U.S. Dist. LEXIS 7741
CourtDistrict Court, D. Minnesota
DecidedFebruary 8, 1963
DocketNo. 4-61-Civ.-254
StatusPublished
Cited by1 cases

This text of 214 F. Supp. 678 (Weldon Farm Products, Inc. v. Commodity Credit Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weldon Farm Products, Inc. v. Commodity Credit Corp., 214 F. Supp. 678, 1963 U.S. Dist. LEXIS 7741 (mnd 1963).

Opinion

DEVITT, Chief Judge.

This action challenges the validity of a decision of the Contracts Disputes Board, Commodity Credit Corporation, upholding the decision of the Contracting Officer of the defendant in assessing liquidated damages against Weldon Farm Products, Inc. for delays in deliveries of certain carlots of nonfat dry milk purchased from Weldon under Contract LD-DF 2249.

Jurisdiction is based on 15 U.S.C.A. § 714b (c).

Section 201(c) of the Agricultural Act of 1949, 7 U.S.C.A. § 1446(c), authorizes purchases of milk products as a method of price support to producers of milk and butterfat. Pursuant to this statutory authority, defendant purchased large quantities of nonfat dry milk. This was accomplished under contracts of sale entered into under the terms of announcements, public notice of which was published for the marketing year April 1, 1957 through March 31, 1958, 22 F.R. 2308.

During the period March 28, 1957 through April 3, 1957, defendant entered into contracts of purchase covering 113,-830.094 pounds of milk with 14 separate contractors, including plaintiff, for delivery of milk meeting the same quality requirements as the contract involved in this action. Between May 31, 1957 and June 18, 1957, defendant entered into contracts with 17 separate contractors, including the plaintiff, for an aggregate of 89,168,972 pounds of additional milk meeting the same requirements as those in the contract involved in this action.

On September 27, 1957, plaintiff requested a three-week extension of time for delivery of dry milk under the exculpatory provisions of the liquidated damage clause of the contract between the parties. Later, on October 14,1957, plaintiff requested a four-week extension. These requests for extensions were based upon claims that unusually hot weather and generally adverse weather conditions led to an abnormal increase in bacteria count which in turn resulted in rejection by defendant of large quantities of nonfat dry milk in September and October, 1957. The basis for these requested extensions was amplified by defendant in a letter dated October 29, 1957. Later, on November 15, 1957, plaintiff requested additional time, totalling 9 weeks in all, for the same reasons.

Some ten months later, on September 8, 1958, the contracting officer of defendant replied to plaintiff’s requests for extensions of time. He denied them for the reason that evidence had not been furnished that the weather was inordinately severe. He was unable to conclude that the delays in delivery were due solely to causes beyond the control and without the fault or negligence of the contractor. Liquidated damages, in accordance with the contract, were assessed.

The Disputes Article of the contract provided that disputes concerning the contract should be decided in writing by the contracting officer subject to appeal within thirty days to the President of defendant corporation or to his duly authorized representatives whose decision would [680]*680be final, subject to the exceptions which are generally the same as those provided in the Wunderlich Act, 41 U.S.C. §§ 321, 322. The Contracts Disputes Board had been designated to hear appeals from decisions of contracting officers under the disputes article, 14 F.R. 1865, as amended, 20 F.R. 8535.

Plaintiff made timely appeal to the Contracts Disputes Board. Extensive hearings were held in St. Paul, Minnesota, form January 13 through January 16, 1959. These hearings included the appeals of plaintiff and several other petitioners who also had made late deliveries •under their respective contracts. The Contracts Disputes Board sustained the decision of the Contracting Officer in part, and reversed his decision in part. This appeal followed.

The contract involved in the instant case is made up of the following eight documents:

(a) Announcement LD-11 dated September 14, 1954, setting forth under Plan A the terms and conditions for the sale to defendant of Spray process nonfat dry milk packed in small containers;

(b) Request No. 39 dated June 5, 1957 by defendant for offers of milk subject to the terms and conditions of (i) Plan A of LD-11 as modified by said request, and (ii) the Uniform Contractual Provisions;

(c) Uniform Contractual Provisions (Form CSS-10 dated February 2, 1955) containing information for offerors and standard contractual provisions for use by defendant in procurement of commodities;

(d) Plaintiff’s telegram dated June 14, 1957, offering under said request 4,950.-000 pounds of milk at 18.24 cents per pound to be shipped from the plant of Dairyland Cooperative Association at Juneau, Wisconsin, in 10 weekly installments commencing the week of July 8, 1957 and terminating with the week of September 15, 1957;

(e) Defendant’s letter of June 18, 1957, accepting the above offer;

(f) Defendant’s telegram of July 18, 1957 to plaintiff stating defendant’s “desire to extend” delivery dates beginning with the week of July 22, 1957 (Weldon’s Ex. 7, Part II of Record);

(g) Plaintiff's telegram of July 19, 1957 in which “we accept two week’s extension” referred to in the above telegram of July 18,1957; and

(h) Defendant’s telegram of July 19, 1957 to plaintiff stating that the contract is amended to extend delivery dates as stated above.

Announcement LD-11 and Request No. 39 are each signed by Don S. Anderson— the Announcement by him in his capacity on September 14, 1954, of “Acting Director, Livestock and Dairy Division, CSS”, and the Request by him in his capacity on June 5,1957, of “Director, Livestock and Dairy Division.”

The following terms of the contract documents are pertinent:

(a) The provisions under Plan A of LD-11 reading:

“7. DELIVERY: * * * Within three business days after the offered delivery date(s), the Commodity Stabilization Service Office serving the territory in which the shipments originate will furnish shipping instructions for the milk. Delivery shall be effected in accordance with such delivery instructions within five business days after their receipt by the contractor, or within five business days after the offered delivery date(s), whichever is later.
* * * * * *
“9. DAMAGES, INCLUDING LIQUIDATED DAMAGES:- (a) Failure of the contractor to make delivery of the milk in accordance with the contracted delivery date(s) will cause serious and substantial damage to CCC because of its urgent need for prompt delivery. Since it will be difficult to prove the amount of such damage, the contractor shall pay to CCC by way of compensation, and not as penalty, liquidated damages at the rate of 0.10 cents per pound for each ten calendar days’ delay in delivery or fraction thereof. [681]*681The contractor in submitting an offer, and CCC in accepting such offer, agree that such damages are a reasonable estimate of the probable actual damages. Deductions representing such damages may be made by CCC from any amounts due the contractor. # * * Contractor’s right to proceed hereunder shall not be terminated and liquidated damages shall not be assessed if the contractor gives CCC prompt written notice of such delay and the cause thereof, and CCC determines in writ-ting that the delay is due solely to causes beyond the control and without the fault or negligence of the contractor * * *.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jennie-O Foods, Inc. v. United States
580 F.2d 400 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
214 F. Supp. 678, 1963 U.S. Dist. LEXIS 7741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weldon-farm-products-inc-v-commodity-credit-corp-mnd-1963.