Welded Tube Company of America v. Phoenix Steel Corporation

512 F.2d 342, 1975 U.S. App. LEXIS 15672
CourtCourt of Appeals for the Third Circuit
DecidedMarch 13, 1975
Docket74-1612
StatusPublished
Cited by27 cases

This text of 512 F.2d 342 (Welded Tube Company of America v. Phoenix Steel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Welded Tube Company of America v. Phoenix Steel Corporation, 512 F.2d 342, 1975 U.S. App. LEXIS 15672 (3d Cir. 1975).

Opinion

OPINION OF THE COURT

WEIS, Circuit Judge.

The Pennsylvania law on artisans’ liens is the principal subject of this appeal. Our review of the law as applied by the district court does not disclose error but a remand is required for limited findings on subsidiary issues.

The parties to this diversity suit entered into a “requirements contract” in 1965, the terms of which were embodied in an exchange of letters. The agreement provided that the Welded Tube Company was to fabricate structural tubing from steel coils which had been delivered to its Philadelphia plant by the Phoenix Steel Corporation. That company agreed to pay a certain scheduled amount for the tubing which it ordered as needed, the price dependent upon the quantity required each month. Payment was to be made by Phoenix within twenty to thirty days from the date on which Welded submitted the invoices. Welded had a similar arrangement with another steel company and also purchased steel on its own account for fabrication into tubing.

*344 After some years of doing business according to the terms of this contract, Phoenix notified Welded in July, 1968 that it did not plan to continue in the tubing field and that it intended to conclude the arrangement between them. It offered Welded the opportunity to buy the steel on hand, but the parties were unable to agree upon a price. Phoenix continued to place orders for tubing until June 30, 1969, when it terminated the contract.

On June 30, 1969, there were no outstanding invoices for amounts owed to Welded, although some completed work had not yet been billed. Invoices for that material were duly prepared in the next few weeks and totaled $51,013.08. 1 Phoenix admits that it owes this amount and has offered to pay it.

Welded claimed that, in addition to the foregoing amount, it was entitled to substantial sums for the preliminary work which had been performed on the coils in its possession, and it refused to turn over the steel on hand to Phoenix. In August of 1969, Phoenix received an offer of $104 per ton for the quantity of steel remaining at the Welded plant but was unable to complete the sale because of Welded’s refusal to yield possession.

On October 23, 1969, Welded filed the present suit, claiming (1) $51,013.08 for finished tubing, (2) $75,271.94 for preliminary work on partly used coils, and (3) $20,163.00 for storage and handling of the coils upon which no work had been performed. After efforts to settle the controversy failed, Welded advised that it proposed to dispose of this steel at a “public sale” 2 on November 23, 1970. Welded was the only bidder and bought the steel at an average price of $52.86 per ton. It later manufactured structural tubing from that material.

After the nonjury trial, the district judge made findings that:

1. Welded was not entitled to an artisan’s lien;
2. Welded had wrongfully withheld possession of the steel from Phoenix;
3. the fair market value of the steel on June 30, 1969 was $103 per ton;
4. Welded had not proved a loss for the preliminary work performed on the coils;
5. Welded was not entitled under the contract to charge for storage; and
6. Phoenix was entitled to recover for the value of the steel at $103 per ton — the sum of $273,516 — less the admitted amount due Welded for work on the finished goods, $51,013.08, plus interest on the net amount.

Welded Tube Company of America v. Phoenix Steel Corporation, 377 F.Supp. 74 (E.D.Pa.1974).

The parties had intended their contractual arrangement to continue for five years unless, two years prior to expiration, either gave written notice to terminate. Welded does not contend that the termination, first discussed with it by Phoenix in July, 1968 and finally confirmed as of June 30, 1969, violated the contract, and so we assume that no breach • of the pertinent provision occurred.

Welded claims that it held a common law artisan’s lien for work done on personal property at the owner’s request. Restatement of Security § 61 (1941). For the purpose of discussion, it may be assumed that such a lien might have been valid in these circumstances, if the contractual terms were consistent with its existence. However, it is not the policy of the law in Pennsylvania to extend the application of common law liens, and it has been held that there is a waiver of such a lien when a contract between parties provides for delivery of goods on credit. Carbon Silk Mills Co. v. Powell, 108 F.2d 474 (3d Cir. 1939), cert. denied 310 U.S. 625, 60 S.Ct. 896, 84 L.Ed. 1396 *345 (1940). In addressing a party’s contention that a liberal approach should be taken toward artisans’ liens, the Pennsylvania Supreme Court said in Mitchell v. Standard Repair Co., 275 Pa. 328, 332, 119 A. 410, 411 (1923):

“The commercial customs of to-day do not favor the tying up of personal property by liens; and, if the courts should now countenance any such general attitude toward the credit system as that announced in the case relied on by appellant, business, as that term is presently understood, would soon come to a standstill.”

Welded relies upon International Electronics Co. v. N.S.T. Metal Products Co., 370 Pa. 213, 88 A.2d 40 (1952), but we find that case distinguishable because of the terms of the contract between those parties. While there was a credit arrangement in the International case, the agreement also provided for possession by the artisan for a given period of time in the absence of compliance with a cancellation clause. Since admittedly that clause had been breached, the state court held that the credit arrangement did not negate the right to a lien as a matter of law. United States v. Toys of the World Club, Inc., 288 F.2d 89 (2d Cir. 1961), also cited by Welded, involved a situation where payment was to be made before final delivery and, therefore, is also distinguishable.

There are no contractual limitations on possession involved here, and, therefore, we cannot say that the district court erred in finding that the right to an artisan’s lien had been waived by the agreement to permit deliveries on a credit basis. '

In Pennsylvania the right to a lien for storage is not extended to an artisan in the absence of contractual entitlement but is limited to warehousemen and those in the business of storage. Mitchell v. Standard Repair Co., supra. See also Restatement of Security § 64, comment d (1941). Hence, Welded was not entitled to a lien for storage.

Having concluded that Welded did not have a lien and was not entitled to retain possession, it follows that it is liable to Phoenix for conversion of its property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrup v. Ben Thompson Enterprises (In Re Northrup)
220 B.R. 855 (E.D. Pennsylvania, 1998)
In Re Midway Airlines, Inc.
167 B.R. 880 (N.D. Illinois, 1994)
Lichtenstein v. Kidder, Peabody & Co. Inc.
840 F. Supp. 374 (W.D. Pennsylvania, 1993)
Mack Trucks, Inc. v. Performance Associates Corp.
553 A.2d 412 (Superior Court of Pennsylvania, 1989)
Royal Insurance v. Ideal Mutual Insurance
649 F. Supp. 130 (E.D. Pennsylvania, 1986)
Royal Ins. Co.(UK) Ltd. v. Ideal Mut. Ins. Co.
649 F. Supp. 130 (E.D. Pennsylvania, 1986)
Beaupierre v. Julien Industrious
19 V.I. 424 (Supreme Court of The Virgin Islands, 1983)
Cernica v. Wagner's Wheel Alinement, Inc.
27 Pa. D. & C.3d 678 (Mercer County Court of Common Pleas, 1983)
Associates Financial Services Co. v. O'Dell
417 A.2d 604 (Supreme Court of Pennsylvania, 1980)
In Re Alan Wood Steel Co.
2 B.R. 161 (E.D. Pennsylvania, 1980)
Universal Computer Systems, Inc. v. Allegheny Airlines, Inc.
479 F. Supp. 639 (M.D. Pennsylvania, 1979)
Stern v. Bricklin
455 F. Supp. 346 (E.D. Pennsylvania, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
512 F.2d 342, 1975 U.S. App. LEXIS 15672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/welded-tube-company-of-america-v-phoenix-steel-corporation-ca3-1975.