Welded Construction, L.P. - Adversary Proceeding

United States Bankruptcy Court, D. Delaware·Decided August 13, 2019·No. 19-50180·Unknown

Opinion

IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE In re: ) Chapter 11 ) WELDED CONSTRUCTION, LLP., ef al., ) Case No. 18-12378 (KG) ) (jointly Administered) ) Debtors. ) WELDED CONSTRUCTION, L.P. AND ) WELDED CONSTRUCTION MICHIGAN, ) LLC, ) ) ) Plaintiffs, ) ) Vv. ) Adv. Pro. No. 19-50180 (KG) ) PRIME NDT SERVICES, INC., ) ) ) Defendants. ) Re: D.L. 7

MEMORANDUM OPINION INTRODUCTION Welded Construction, L.P. and Welded Construction Michigan, LLC (collectively, “Welded”) brought this adversary proceeding against Prime NDT Services, Inc. (“Prime”). Prime moves to partially dismiss the First Claim and wholly dismiss the Second Claim against it in the two-claim complaint (the “Complaint”) pursuant to Federal Rule of Civil Procedure 12(b)(6) (“Rule 12(b)(6)”), made applicable here by Federal Rule of Bankruptcy Procedure 7012 (“Bankruptcy Rule 7012”) (the “Motion”). In the First Claim, Welded alleges that Prime breached the Subcontract (discussed below) in providing Welded with defective and non-conforming x-ray films for over

seventy discrete welds, In the Second Claim, Welded alleges that Prime breached warranties in the Subcontract by not performing its work in a good and workmanlike

manner consistent with industry standards. Prime seeks partial dismissal of the First Claim and complete dismissal of the Second Claim. For the reasons that follow, the Court will deny the Motion in its entirety. [URISDICTION The Court has jurisdiction to hear these matters under 28 U.S.C. 8§ 1334(b) and 157(c)(1).1 The First Claim for breach of contract and the Second Claim for breach of warranty are non-core matters. Notwithstanding, on a motion to dismiss the Court has the power to enter an order on non-core matters even if it has no authority to enter a final order on the merits. Scher v. Essar Global Fund Ltd. (in re Essar Steel Minnesota LLC), 2019 WL 2264051, at *3 (Bankr. D. Del. May 23, 2019); Giuliano v. Genesis Fin. Sols. (In re Axiant, LLC), 2012 WL. 5614588, at *1 (Bankr. D. Del. Nov. 15, 2012) (citing In re Trinsum Grp., Inc., A67 B.R. 734, 739 (Bankr. S.D.N.Y. 2012) (“ After Stern v, Marshall, the ability of bankruptcy judges to enter interlocutory orders in proceedings ... has been reaffirmed....”)); Boyd v. King Par, LLC, Case No. 11-CV-1106, 2011 WL 5509873, at *5 (W.D. Mich. Nov. 10, 2011) (“[U}ncertainty regarding the bankruptcy court's ability to enter a final judgment ... does

not deprive the bankruptcy court of the power to entertain all pretrial proceedings”). Venue is proper in the District of Delaware pursuant to 28 U.S.C. §§ 1408 and 1409.

1 Prime does not consent to the Court's entry of a final judgment. Motion, p. 12. In deciding a motion to dismiss, the Court is not required to state findings of fact or conclusions of law. See Fed, R, Bankr. P. 7052 & Fed. R. Civ. P. 52(a)(3).

BACKGROUND Sunoco Marketing Partners & Terminals L.P. and Sunoco Pipeline L.P. (collectively, “Sunoco”) own a pipeline project dubbed “Mariner East 2” (the “Project”). Compl. p. 1. The Project’s objective is to create new pipeline capacity from Ohio through West Virginia and Pennsylvania to transport natural gas liquids to Sunoco’s Marcus Hook Industrial Complex. Compl. pp. 1-2. Sunoco contracted with Welded for the latter

to construct three separate pipeline “spreads” for approximately 152.6 miles of high pressure liquified natural gas pipeline. Compl. p. 2. On January 6, 2016, Welded subcontracted with Prime to perform non-destructive examination (“NDE”) x-ray weld inspections on the P1 and. P5 spreads of the Project (the “Subcontract”). Compl. {J 1-2; p. 2; see also Compl. Ex. 1 (copy of Subcontract). Prime

was to perform NDE x-rays to determine whether the completed welds connecting each length of pipe conformed with the Subcontract’s quality standards. Compl. { 15. Prime warranted that its workmanship and materials would be of proper quality, be performed in line with industry standards, meet Sunoco’s specifications and be compliant with the Subcontract. Compl. § 12 (citing Subcontract, Ex. G, Art. 16.0). Prime also represented that it would perform its work in a safe, workmanlike and competent manner in accordance with sound construction and Sunoco approved standards. Compl. § 13 (citing Subcontract, Ex. G, Art. 20.0(1)). Prime would perform an x-ray by exposing three films for each weld that Welded completed. Compl. { 16. Prime would then inspect the x-ray films and report to Welded whether the weld was conforming. Compl. If the weld was, Welded would backfill

the trench and continue construction. Compl. § 18. Prime, not Welded, was required to perform QA/QC work on its x-ray films analysis to ensure compliance with the Subcontract. Compl. §f 19-20. Upon Prime’s reporting, Welded provided Sunoco with the films for a third party to perform further QA/QC work. Compl. 21. In or around June 2018, Sunoco discovered over seventy non-conforming discrete welds. Compl. { 22. Prime never disputed the findings establishing its defective work. Compl. { 24. Due to Prime’s defective work, Welded had to excavate the seventy non- conforming welds and bring each into compliance. Compl. ¢ 25-26. During Welded’s thirty days of remedial work, Welded had to halt its progress on the P1 spread, and thus fell far behind its production schedule. Compl. { 28. Welded hired additional workers from the week of August 19 through the week of October 21, 2018 to accelerate its work and meet the Project production schedule (the “Acceleration Costs”). Compl. § 28. Although Welded remedied the welds, Welded incurred hefty labor, equipment and Acceleration Costs to recover lost time in the production schedule. Compl. { 29. Sunoco then terminated Welded from the Project for

cause citing Prime’s defective work as a substantial factor. Compl. 31. On October 22, 2018, Welded filed for relief under Chapter 11 citing its Project termination as a substantial factor. Compl. { 32. On March 27, 2019, Welded filed a two-count Complaint seeking at least five million dollars in damages. Compl. p. 8.

LEGAL STANDARD Rule 12(b)(6) provides for dismissal for “failure to state a claim upon which relief

can be granted.” Rule 12(b)(6) is inextricably linked to Rule 8(a)(2), which provides that “Tal pleading that states a claim for relief must contain . ..a short and plain statement of the claim showing that the pleader is entitled to relief.” In Twombly, the Supreme Court ushered in the modern era of notice pleading under Rule 8(a)(2). The Court observed that “Tw]hile a complaint attacked by a Rule 12(b)(6) motion to dismiss does not need detailed factual allegations, a plaintiff's obligations to provide the ‘grounds’ of his ‘entitle[ment] to relief’ requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Bell Allantic Corp. v. Twombly, 550 U.S, 544, 555 (2007) (citations omitted). The Twombly standard is one of “plausibility” and not “probability” - “it simply calls for enough fact to raise a reasonable expectation that discovery will reveal evidence of” the necessary element. Id. at 556. The Supreme Court again addressed the Rule 8(a)(2) notice pleading standard in

its Igbal decision. See Ashcroft v. Iqbal, 556 U.S, 662, 677-79 (2009).

Free access — add to your briefcase to read the full text and ask questions with AI

Welded Construction, L.P. - Adversary Proceeding, (Del. 2019).

Welded Construction, L.P. - Adversary Proceeding (Welded Construction, L.P. - Adversary Proceeding) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related