Weitz Co. v. Travelers Casualty & Surety Co. of America

266 F. Supp. 2d 984, 2003 U.S. Dist. LEXIS 9332, 2003 WL 21349727
CourtDistrict Court, S.D. Iowa
DecidedJune 2, 2003
Docket4:02-cv-40188
StatusPublished
Cited by2 cases

This text of 266 F. Supp. 2d 984 (Weitz Co. v. Travelers Casualty & Surety Co. of America) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weitz Co. v. Travelers Casualty & Surety Co. of America, 266 F. Supp. 2d 984, 2003 U.S. Dist. LEXIS 9332, 2003 WL 21349727 (S.D. Iowa 2003).

Opinion

ORDER ON MOTION OF DEFENDANT EMPLOYERS INSURANCE OF WAUSAU FOR SUMMARY JUDGMENT

GRITZNER, District Judge.

This matter comes before the Court on Defendant Employers Insurance of Wau-sau’s (‘Wausau”) Motion for Summary *986 Judgment (Clerk’s No. 36). A hearing was held on April 4, 2003; Henry A. Harmon argued on behalf of Wausau, and John A. Templer argued on behalf of Plaintiff, The Weitz Company (“Weitz”). For the reasons discussed below, Wausau’s Motion for Summary Judgment is denied.

I. BACKGROUND FACTS 1

In 1989, Weitz entered into a general contractor construction contract with Shoreline Care, Limited Partnership (“Shoreline”) of North Branford, Connecticut. During this first phase of the construction project (“Phase I”), Weitz was to construct a continuing care retirement community for Shoreline called Evergreen Woods. To provide the heating, ventilation, and air conditioning (“HVAC”) work in Evergreen Woods during Phase I construction, Weitz subcontracted with Janaz-zo Heating and Air Conditioning, Inc. (“Janazzo”), of Milldale, Connecticut, on August 22, 1990 (Subcontract “D385-32”). Under the D385-32 subcontract, Janazzo was to begin its part of Phase I construction on July 30, 1990, and finish by June 17, 1991. Janazzo was to have Weitz included as an additional insured on Janaz-zo’s commercial general liability (“CGL”) insurance policies for Phase I construction.

On April 30, 1991, Weitz contracted with Shoreline again, agreeing to be general contractor for a second phase of construction at Evergreen Woods (“Phase II”). To provide the HVAC work during Phase II, Weitz entered into a second subcontract with Janazzo on January 9, 1992 (Subcontract “D385-D1”). Under the D385-D1 subcontract, Janazzo was to begin its part of the Phase II construction on December 30, 1991, and be finished by May 15, 1992. Again, it was understood that Janazzo would have Weitz included as an additional insured on Janazzo’s CGL insurance policies for Phase II construction. Although multiple insurance companies provided insurance coverage throughout the construction of Evergreen Woods, this motion only concerns two Wausau policies.

A. The Wausau Insurance Policies.

The first Wausau policy at issue, policy 1520 00 079387 (“1520”), was in effect from September 1, 1989, through September 1, 1990. Policy 1520 was effective for nine days during the existence of the Phase I/D385-32 subcontract between Weitz and Janazzo (Phase I/D385-32 signed on August 22, 1990; policy 1520 expired on September 1, 1990). Policy 1520 lists Janazzo as the named insured but does not list Weitz anywhere as an additional insured.

By the time Janazzo and Weitz agreed to the second subcontract in January of 1992, policy 1520 had expired and Janazzo had purchased a second Wausau policy, policy 1521 00 079387 (“1521”). Policy 1521 was in effect from September 1,1990, through September 1, 1991. Thus, policy 1521 had expired four months before Weitz and Janazzo agreed to the second subcontract (Policy 1521 expired on September 1, 1991, and subcontract D385-D1 was signed on January 9, 1992). Janazzo is listed as the named insured on policy 1521. Through an additional insured endorsement made effective on September 26, 1990, Weitz became an additional insured to the 1521 policy. This September endorsement clearly shows Weitz as a named additional insured under policy 1521 for the “Evergreen Woods Project D385-32 H.V.A.C. & Plumbing” portion of the construction project. On October 11, 1990, *987 Wausau issued a certificate of insurance to Weitz which referenced policy 1521 and indicated that “The Weitz Company is named as additional insured for job known as: Subcontract Agreement # D385-32— Evergreen Woods”. See Wausau Ex. E. Weitz, therefore, had additional insured status under policy 1521, but only as to Phase I construction (the D385-32 subcontract).

B. Phase I and Phase II Construction Problems are Discovered.

The first indication that problems existed with the Evergreen Woods HVAC system occurred when portions constructed during Phase II were claimed to be under-designed for the size of the Evergreen Woods facility. It was asserted the HVAC system created negative air pressure, meaning the exhaust system drew out more air than the supply system was designed to bring into the premises, therefore providing inadequate heating. Shoreline claimed Janazzo should have known of the faulty design of the HVAC system before installing it and had failed to alert Shoreline. Furthermore, Shoreline asserted Janazzo had failed to perform its air balancing report duties faithfully, which, if done correctly, would have uncovered the design problems ' of the HVAC system. Eventually, Shoreline focused its allegations onto Weitz as general contractor, leading Shoreline to pursue arbitration against Weitz in June of 1994 pursuant to an arbitration clause contained, in the Phase II contract. 2 At the conclusion of arbitration, the arbitrators assessed liability to Weitz but did not award Shoreline damages. 3 In connection with the Phase II arbitration, Weitz incurred defense costs totaling approximately $338,778.83.

Subsequently, similar issues arose with that portion of the HVAC system constructed during Phase I. On May 2, 1996, Shoreline brought suit against Weitz in Connecticut state court related to Phase I construction. 4 The Phase I lawsuit con- *988 eluded on February 28, 2002. On November 15, 2002, the. Connecticut state court announced its decision, finding in favor of Shoreline against Jansen & Rogan, the mechanical and electrical consulting engineers who designed the HVAC system, in the amount of $228,853.98. See Shoreline Care Ltd. P’ship v. Jansen & Rogan Consulting Eng’rs, 2002 WL 31758432 *7 (Conn.Super.Ct. Nov.15, 2002) (unpublished). The court dismissed Shoreline’s counts against Weitz and Janazzo without assessing liability upon either of them. See id. In connection with the Phase I litigation, another insurance company named as a defendant in this case, Travelers, obtained legal services on behalf of Weitz and, as of June of 2002, had spent over $750,000 associated with the Phase I litigation. Wanting to monitor these attorneys, Weitz obtained independent legal counsel and has incurred approximately $35,196.08 in associated costs as of October of 2002.

C. Correspondence Between Weitz and Wausau.

While the Phase II arbitration was ongoing, Weitz contacted Wausau about both Wausau policies in an effort to recoup the Phase II arbitration expenses. Eventually, this exchange of correspondence also concerned Weitz’ request for coverage under both Wausau policies for the Phase I litigation. Describing all of the letters contained in the record is unnecessary; however, elaboration on three items of correspondence is pertinent to the Court’s decision.

1. The July 27,1995, Letter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. Lexington Insurance
982 F. Supp. 2d 975 (S.D. Iowa, 2013)
State Farm Mutual Automobile Insurance v. Superior Court
8 Cal. Rptr. 3d 56 (California Court of Appeal, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
266 F. Supp. 2d 984, 2003 U.S. Dist. LEXIS 9332, 2003 WL 21349727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weitz-co-v-travelers-casualty-surety-co-of-america-iasd-2003.