Weissbaum v. United States

72 Ct. Cl. 423, 1931 U.S. Ct. Cl. LEXIS 314, 1931 WL 2410
CourtUnited States Court of Claims
DecidedJune 1, 1931
DocketNo. J-150
StatusPublished
Cited by1 cases

This text of 72 Ct. Cl. 423 (Weissbaum v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weissbaum v. United States, 72 Ct. Cl. 423, 1931 U.S. Ct. Cl. LEXIS 314, 1931 WL 2410 (cc 1931).

Opinion

LittletoN, Judge,

delivered the opinion:

In this suit plaintiff seeks to recover from the defendant his actual loss and damages sustained because of failure of the defendant to deliver title and to put him in possession of certain improvements constructed by the defendant upon leased premises for the wrecking and removal of which, and for the restoration of the premises, the plaintiff and the de[435]*435fendant entered into a contract, and because of misrepresentation of the defendant’s authorized officers as to the accessibility of the improvements.

The contract in question was a “ Contract for the Construction and- Repair of Public Works, Including Vessels.” The United States had constructed an Army cantonment known as Camp Kearney upon leased premises in the State of California, including buildings, waterworks, sewer system, telegraph and telephone lines, lighting system, roads, and railways. The use of the premises as an Army cantonment had been abandoned and the United States advertised for bids for the letting of a contract for the removal of all of these improvements and for the restoration of the premises to a condition satisfactory to the defendant. The United States was bound to restore the premises as far as possible, and the plaintiff was the successful bidder and was awarded the contract to do the work. The subject matter of the contract was the wrecking and removal of the improvements, the restoration of the premises, and the sale of the salvaged material. Inasmuch as the right to keep and dispose of the salvaged materials that might be removed from the premises was more valuable than the cost of the wrecking and removal thereof and the restoration of the premises, the plaintiff agreed to pay the defendant $25,515 for the privilege of doing the work and retaining the salvaged material. Plaintiff was experienced in work of this kind and estimated the probable expense of doing the work and the amount which he could probably realize from the salvaged material. The contract required that the work be completed within ninety days after the execution of the contract.

Under the contract the United States warranted that it was the owner and entitled to possession and the right to remove the improvements upon the premises in question. The defendant, through its authorized officers, represented to bidders that the successful bidder would be given free access to the premises and would be placed in the possession of the improvements. As a matter of fact, however, at the time the advertisement and call for bids was made, and contin[436]*436uously thereafter until the execution of the contract, the defendant had actual notice, verbally and in writing, from the Mack Copper Company and its officers and representatives, upon whose land a portion of the improvements were located, that the title of the United States to the improvements and its right to enter upon the land and remove the same was disputed and denied, and that the said Mack Copper Company and its officers would refuse to permit the United States or anyone with whom it might make a contract to enter upon the premises or to remove the improvements therefrom. This information was concealed by the defendant from bidders and from the plaintiff at the time it made its bid and at the time the contract was entered into. These facts establish that there was a direct misrepresentation by the defendant of the conditions under which the work was to be performed. Hollerbach v. United States, 233 U. S. 165; United States v. Atlantic Dredging Co., 253 U. S. 1. This suit is not an action sounding in tort. The representation that the improvements were accessible and that the contractor would have free ingress and egress was the very foundation of the whole undertaking. The plaintiff did not pay the defendant $25,575 for a lawsuit. He paid for the right to remove the improvements. The United States particularly contracted to deliver possession, which it did not do until February, 1925, over two years after the contract was entered into. It was then enabled to do so only as a result of a decree of the United States District Court for the Southern District of California terminating a suit instituted against the Mack Copper Company and others which extended over a period from August, 1923, to February, 1925. When the Mack Copper Company and its officers and its representatives by the use of arms prevented the plaintiff and also the defendant from entering upon its property for the purpose of wrecking and removing the improvements the Quartermaster General and the Judge Advocate General of the Army, the Secretary of War, and the Attorney General of the United States all decided that the defendant had not delivered title and possession of the improvements to the plaintiff and that it had not performed its obligation [437]*437under the contract in providing the plaintiff free access to the premises for the purpose of performing the work required by the contract.

By specific direction of the Attorney General, the United States attorney for the southern district of California instituted a suit in the name of the United States in the District Court, Southern District of California, for an injunction against the Mack Copper Company and for damages. The basis of that suit was that the United States was the owner of the improvements and was entitled to possession thereof and the right to remove the same. This was denied by the Mack Copper Company and others and the issue thus joined was tried out. The Mack Copper Company contended that the United States had sold whatever right it had to Weiss-baum and that he was the proper plaintiff. The court decided, after a full and complete hearing, that the United States was the owner and entitled to possession of all of the improvements and equipment erected and installed by it in and upon said land of the Mack Copper Company, and that it had the right to remove, or cause to be removed off the premises, all of the improvements on said lands and premises, and decreed that the United States recover from the Mack Copper Company all damages arising by reason of their wrongful interference with the removal of said improvements and for the full value of all those improvements that were sold by the United States to the plaintiff and thereafter sold, missing, or removed from the premises by persons other than the plaintiff.

The matter was referred to a special master to take proof as to the damages. Upon appeal by the Mack Copper Company to the United States Circuit Court of Appeals for the Ninth Circuit, the decree of the district court was affirmed. Final judgment was entered by the district court in favor of the United States for $33,781.88 representing the value of the improvements removed from the premises by the Mack Copper Company and for interest of $822.79 upon that amount.

Upon entry of the decree of the court the defendant notified the plaintiff that it was then ready to deliver the balance [438]*438•of the improvements and demanded of the plaintiff that it proceed with the performance of the contract. In these circumstances it may not be said that the defendant is in nowise responsible to the plaintiff for his actual losses sustained by reason of the failure of the defendant to place him in possession of the improvements and to give him the right and uninterrupted privilege of removing the same.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delta Equipment & Construction Co. v. United States
104 F. Supp. 549 (Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
72 Ct. Cl. 423, 1931 U.S. Ct. Cl. LEXIS 314, 1931 WL 2410, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weissbaum-v-united-states-cc-1931.