Weeks v. Palmer Motorsports Park, LLC

CourtMassachusetts Land Court
DecidedAugust 13, 2021
DocketMISC 17-000493
StatusPublished

This text of Weeks v. Palmer Motorsports Park, LLC (Weeks v. Palmer Motorsports Park, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Land Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weeks v. Palmer Motorsports Park, LLC, (Mass. Super. Ct. 2021).

Opinion

WEEKS vs. PALMER MOTORSPORTS PARK, LLC, MISC 17-000493

BONITA J. WEEKS, in her capacity as Building Inspector and Zoning Enforcement Officer of the Town of Palmer, Plaintiff/contempt-complaint plaintiff, v. PALMER MOTORSPORTS PARK, LLC, Defendant/contempt complaint defendant

MISC 17-000493

AUGUST 13, 2021

HAMPDEN, ss.

VHAY, J.

FINDINGS OF FACT, CONCLUSIONS OF LAW, AND ORDER (Rule 65.3(h), Mass. R. Civ. P.)

This case involves an automobile racetrack in Palmer, Massachusetts, called the Palmer Motorsports Park (the "Park"). It's owned by a limited liability company with a similar name ("PMP"), the defendant in this case. While the Park hasn't achieved the fame of Indianapolis's Brickyard or the Daytona International Speedway, one thing is true about all three tracks: when there's racing, there's noise, and a lot of it.

The Park underwent development in the mid-2000s. Before it could be built, it needed a special permit from the Town of Palmer's Planning Board (the "Board"). The original owner of the Park knew when it applied for the permit that noise would be an issue. That owner submitted to the Board as part of the Park's permit application an analysis prepared by an acoustical engineering firm, Resource Systems Group, Inc. ("RSG"), of the Park's anticipated sound (the "2007 RSG Memorandum"). The Board held public hearings on the application between August and December 2007. Noise was the central issue at those hearings.

At the conclusion of its hearings, the Board found that the Park's "extensive sound analysis, combined with the remote location of the [site] and its unique 'bowl-shape' topography confirms that the adjoining premises are protected against serious detriment by the provision of sound and sight buffers. . . ." The Board thus concluded that "the surrounding neighborhood will not be negatively impacted in any way by . . . sound . . . ." The Board thus granted the special permit in December 2007 (the "Special Permit"). The Board nevertheless imposed twenty conditions on its grant of the permit, a permit no one appealed. The conditions included this one, Condition #10:

Within 90 days of the commencement of operation, the applicant shall record actual noise readings (receptors shall have the same location as in the original study), to validate the project model and confirm compliance with state regulations. New information shall be submitted to the Board for professional review, at the applicant's expense, and proper mitigation measures shall be implemented, if needed.

The Park changed owners after issuance of the Special Permit. Its current owner, PMP, supervised construction of the Park's current 2.14-mile racetrack. That track differs in shape and location from that proposed in the Park's 2007 application. It also differs from the track that RSG modeled in 2007.

The Park opened for racing in May 2015. Residents thereafter began complaining about the Park's noise. Eventually the Town's building inspector and zoning-enforcement officer, plaintiff Bonita J. Weeks, brought this action in 2017 against PMP, pursuant to G.L. c. 40A, § 7. Weeks accused PMP of violating Condition #10.

The Court held a trial on Inspector's claims in March 2018 trial. At the conclusion of that trial, the Court told that parties that PMP hadn't complied with Condition #10. The parties asked for time to negotiate a solution. The Court gave them that time, but by late 2019 the Court concluded that the case wouldn't settle. The Court thus issued a judgment, dated January 14, 2020 (the "Judgment"). Among other things, the judgment ordered PMP,

by no later than 45 days from the entry of this Judgment, to (a) implement proper mitigation measures so as to remedy all of the noise conditions that the evidence at trial of this matter and/or the study of the [Park] prepared by Resource Systems Group, Inc. ["RSG"], dated November 1, 2018 [the "2018 RSG Study"] shows are not in compliance with Condition #10 and (b) following PMP's implementation of such measures, provide to the . . . Board . . . , for professional review at PMP's expense, actual noise readings from the same locations as the "original study" described in Condition #10. In order to fulfill the requirements of subparagraph (b) of this [Order], such actual noise readings and corresponding data must be in such form as to allow a professional acoustical engineer engaged by the Board to determine whether noise from the Park, after PMP's implementation of mitigation measures, meets the requirements of Condition #10.

Recognizing that nearly two years had passed between the March 2018 trial and the Judgment, and that conditions at the Park may have changed, the Court noted in a decision accompanying the Judgment that "[i]t's possible that PMP already has done what [the Judgment] require[s]. It's also possible that more mitigation is needed. If the [Town's zoning] enforcement officer believes that PMP hasn't complied with the Court's orders, she may seek additional orders or a finding of contempt."

No one appealed the Judgment. But the Court's 2020 comments were prescient. On September 22, 2020, Inspector Weeks filed a complaint for contempt (amended in October 2020), charging that PMP hadn't complied with the Judgment. PMP answered the amended complaint for contempt in March 2021. PMP claimed it had done its best to obey the Judgment, and that any non-compliance was a result of the COVID-19 pandemic.

The parties appeared for trial by videoconference on June 22 and 23, 2021. The Court also took a view of the Park on the morning of June 22, 2021. [Note 1] After hearing the parties' witnesses, having reviewed their stipulations of fact, having considered the admitted documentary evidence, and having heard the arguments of the parties' counsel, the Court FINDS the facts set forth above, as well as these, by clear and convincing evidence:

1. The Special Permit authorized the use of a property located off West Ware Road in Palmer, MA (the "Property") as the site of a 2.14-mile long, 40-foot-wide motor sports course/ track, with an access road and paddock area, all within a 496-acre lot.

2. Since the 2015 opening of the Park, PMP has regularly conducted track-side noise monitoring, to determine if racers are exceeding the Park's published maximum noise rules. In 2017, PMP expanded the number of noise-monitoring locations, made them harder for racers to avoid, and increased the monitoring of cars in the Park's race paddock. Since the opening of the Park, PMP has "black flagged" cars found to have exceeded the maximum applicable noise level, prohibiting them from racing until their owners take measures to reduce the vehicle's sound.

3. In 2016, PMP started maintaining a supply of "baffle inserts" for race vehicles. One may insert the baffles directly into a racecar's tailpipe, reducing the engine's noise. Starting in 2017, PMP increased the variety of baffles the Park stocked.

4. In 2016, PMP installed fabric acoustic barriers near the Park's Turns 5, 9, and 10.

5. Following the March 2018 trial on Inspector Weeks's complaint in this action, PMP heightened its enforcement of its noise rules. A single noise violation resulted in an order to the driver to mitigate. A second violation in a day resulted in a second order to mitigate. A third violation in a day resulted in an order barring the vehicle from the track the rest of that race day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New England Overall Co. Inc. v. Woltmann
176 N.E.2d 193 (Massachusetts Supreme Judicial Court, 1961)
Martinez v. Lynn Housing Authority
119 N.E.3d 312 (Massachusetts Appeals Court, 2019)
Birchall
913 N.E.2d 799 (Massachusetts Supreme Judicial Court, 2009)
Fidelity Management & Research Co. v. Ostrander
662 N.E.2d 699 (Massachusetts Appeals Court, 1996)
Cooper v. Keto
990 N.E.2d 76 (Massachusetts Appeals Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Weeks v. Palmer Motorsports Park, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weeks-v-palmer-motorsports-park-llc-masslandct-2021.