Weber v. Collins

41 S.W. 249, 139 Mo. 501, 1897 Mo. LEXIS 187
CourtSupreme Court of Missouri
DecidedJune 8, 1897
StatusPublished
Cited by9 cases

This text of 41 S.W. 249 (Weber v. Collins) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weber v. Collins, 41 S.W. 249, 139 Mo. 501, 1897 Mo. LEXIS 187 (Mo. 1897).

Opinions

Macfarlane, J.

The suit is by plaintiffs, as contractors, against Clara S. Collins, Monroe R. Collins, husband of the said Clara, and ^Robert E. Collins, upon a balance of an account for building a dwelling house,, and to establish and enforce a mechanic’s lien upon the land and building for the contract price.

The petition charges, in substance, that plaintiffs furnished the materials and constructed a dwelling ho'use, on Lindell avenue in the city of St. Louis, under a contract with defendant Clara S. Collins, in behalf of herself and her husband and codefendant, Monroe R. Collins. The contract price was $11,369.52 and extras to the amount of $69, making a total of $11,438.52. Credits for $8,000, are admitted, leaving an alleged balance due of $3,438.52.

The petition further charges that at the time of making the contract the title to the land, upon which the building was constructed, was vested in Esther Collins, the mother of the said defendant, Monroe R. Collins, who had agreed to give the lot to her daughter-in-law, the said Clara, for a home, and that she did put her and her husband in possession thereof for the purpose of constructing the building. That said Esther Collins thereafter died leaving the legal title in defendants, her sons, Monroe R. Collins and Robert E. Collins. General judgment is also asked against the said defendants Clara S. and Monroe R. Collins.

The answers of Monroe R. and Robert S. Collins were general denials. The answer of defendant Clara S. Collins, in addition to a general denial set up that the building was constructed under a special contract, which required its completion by the fifteenth of September, 1892, and provided for a forfeiture of $5 per day for delays, unless for causes specified. That the building was not completed until April 15, 1893, making two hundred and two days’ delay, amounting to [505]*505$1,010, which she asked to have deducted from the contract price. The reply admitted the delay but claimed they were unavoidable from and for causes excepted under the contract.

The ease went to a referee, who stated the account as follows:

Unpaid balance of contract price............................$3,369.52
Extra....................................................... 5.00
$3,374.52
Less balance on account of delay ......................... 372.00
$3,002.52

The referee found that plaintiffs were not entitled to a mechanic’s lien, but that the contract for the improvement was made in the name of Clara S. Collins for herself, and as agent for her husband, and recommended a general judgment against them both for the amount found to be due. Exceptions to the report were filed and overruled and judgment was rendered in accordance therewith. From the judgment the defendants alone appeal.

The finding of the referee being against the mechanic’s lien, and plaintiff not appealing, that issue, wThich was the most important one tried, is not for consideration on this appeal.

Defendants assigned but two errors. First, it having been shown that the house was delivered two hundred and two days after the date fixed by the contract for its completion, plaintiff did not show adequate cause for the delay allowed them by the referee. Second, Monroe R. Collins is not shown to be personally liable to plaintiff upon the contract made by his wife, Clara S. Collins.

Both these propositions challenge the correctness of the finding of facts by the referee. It is well settled, under the decisions of this court, that the finding [506]*506of the referee on questions of fact, in cases in which the parties are entitled to jury trial, stands as a special verdict of a jury, and where there is substantial evidence to sustain it, the appellate courts will presume that the “whole evidence was properly weighed and therequisiteefEectgiven.it. The Wiggins Ferry Co. v. Railroad, 73 Mo. 420; Hardware Co. v. Wolter, 91 Mo. 488; Howard Co. v. Baker, 119 Mo. 397.

The contract provided that the time for completion of the building should be extended if plaintiff was unavoidably delayed in its construction by any “general strike,” or by “inclement weather.” Plaintiff, by reply to defendant’s counterclaim, confessed the delay of two hundred and two days, but alleged that it was caused by general strikes and by inclement weather. Evidence was introduced by plaintiff tending to prove that the delay was unavoidable on account of the causes so specified in the contract. It was shown that the operatives of the planing mills in- the city of St. Louis were on a strike from June 15, to August 8, 1892. There were twenty-eight of such mills and only three of them were in operation and they were unable to secure skilled labor. By reason of this strike plaintiffs were unable to have the necessary material for the building prepared.

Defendant’s counsel insists that this was not a “general strike” within the meaning of the contract. The referee thought differently, and we quite agree with him. Mill work, such as was required to be done for the construction of this building, could only be prepared under special orders, and some considerable time was required to fill them. It could not have been contemplated by the parties that such material would be prepared by foreign mills when so many were in operation in the city. Indeed plaintiffs had already conr tracted with the Crescent Planing Mills for the- prepa[507]*507ration of most of the materials before the strike commenced. The strike of the operatives in the mills in St. Louis was general and I am of the opinion that the strike was general within the contemplation of the parties to the contract.

There was also substantial evidence tending to prove delays caused by inclemency of the weather. The finding of the referee as to the extent of the delays on this account is conclusive upon us if the evidence was competent. In order to prove the character of the weather, the temperature and rainfall, plaintiff called as a witness the official observer of the United States Signal Service office at St. Louis. Plaintiff objected to the competency of the testimony of this witness for the reasons that he acquired his information from the records of the office and did not testify from his personal knowledge. We are of opinion that the records themselves would have been admissible as evidence of the character of the weather. The record is required to be kept by the layvs of the United States. They are official, and a statute of the State provides that “all-records........kept in any public office of the United States,.......not appertaining to a court, shall be evidence'in this State.” R. S. 1889, sec. 4844. It was certainly competent for the officer who kept the record to refresh his memory by a reference to it.

Defendant complains chiefly of the finding of the referee that Monroe R. Collins is personally liable for the"balance found to be due upon the building contract, and to the general judgment of the court .against him. There is no dispute that the contract was signed by Clara S. Collins alone, but the referee finds, as a fact, that her .husband, Monroe R. Collins, was the real party interested, and his wife was merely acting as agent for him when she entered into the agreement with plaintiffs. If his finding of fact is correct, the [508]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kuhlman Plastics Co. v. Kansas City Power & Light Co.
400 S.W.2d 409 (Supreme Court of Missouri, 1966)
Perles & Stone, Inc. v. Childs Co.
84 S.W.2d 1052 (Supreme Court of Missouri, 1935)
Humphrey v. Bussey
128 So. 848 (Supreme Court of Florida, 1930)
Young v. Emmke
242 S.W. 161 (Missouri Court of Appeals, 1922)
Donner v. Whitecotton
212 S.W. 378 (Court of Appeals of Kansas, 1919)
Morton v. Manchester Investment Co.
168 S.W. 904 (Missouri Court of Appeals, 1914)
Wallis v. Inhabitants of Wenham
90 N.E. 396 (Massachusetts Supreme Judicial Court, 1910)
Priddy v. Boice
99 S.W. 1055 (Supreme Court of Missouri, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
41 S.W. 249, 139 Mo. 501, 1897 Mo. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weber-v-collins-mo-1897.