Webcor-Obayashi Joint Venture v. Zurich American Insurance Company

CourtDistrict Court, N.D. California
DecidedAugust 3, 2020
Docket3:19-cv-07799
StatusUnknown

This text of Webcor-Obayashi Joint Venture v. Zurich American Insurance Company (Webcor-Obayashi Joint Venture v. Zurich American Insurance Company) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Webcor-Obayashi Joint Venture v. Zurich American Insurance Company, (N.D. Cal. 2020).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 WEBCORE-OBAYASHI JOINT Case No. 19-cv-07799-SI VENTURE, 8 Plaintiff, ORDER GRANTING IN PART 9 PLAINTIFF'S MOTION FOR PARTIAL v. SUMMARY JUDGMENT 10 ZURICH AMERICAN INSURANCE Re: Dkt. No. 24 11 COMPANY,

12 Defendant.

13 14 On July 24, 2020, this Court heard oral argument on plaintiff Webcore-Obayashi Joint 15 Venture’s motion for partial summary judgment. Having carefully considered the arguments of the 16 parties and the papers submitted, plaintiff’s motion for partial summary judgment is GRANTED IN 17 PART. 18 19 BACKGROUND 20 In March 2009, Webcore-Obayashi Joint Venture (“WOJV”) and the Transbay Joint Power 21 Authority (“TJPA”) entered into a contract for WOJV to be the general contractor responsible for 22 constructing the Salesforce Transit Center (the “Center”) in San Francisco, California. Gillespie 23 Decl. ¶ 6. Under the contract, WOJV was prohibited from doing any of the actual construction, so 24 it relied on several subcontractors; one of whom was responsible for the fabrication of the building’s 25 steel girders. Id. ¶¶ 6-7. 26 WOJV also entered into a contract with Zurich American Insurance Company (“Zurich”) for 27 1 Builder’s Risk Insurance.1 Stoelting Decl. ¶¶ 5-6. The policy was in effect from March 28, 2011 2 to July 16, 2018. Id. at Ex. A. WOJV paid Zurich more than $12 million in premiums for a total 3 protection amount of over $1.5 billion. Id. ¶ 7. The general policy provisions are as follows: “This 4 policy, subject to the terms, exclusions, limitations and conditions contained herein or endorsed 5 hereto, insures against all risks of direct physical loss of or damage to Covered Property while at the 6 location of the INSURED PROJECT*2 and occurring during the Policy Term.” Stoelting Decl., 7 Ex. A at form PBR 001-COV (9-07A), page 1 of 13. Some of the policy’s exclusions under the 8 “Cost of Making Good” section include “faulty or defective workmanship, supplies or material.” 9 Id. at page 2 of 13. 10 In September 2015, girders were installed on the Fremont Street side of the Center (“Fremont 11 Street Girders”). Gillespie Decl. ¶ 9. Construction of the Center was substantially completed on 12 July 12, 2018, and it was opened to the public in August 2018. Id. ¶ 11. 13 On September 25 and 26, 2018, workers discovered two fractures in two separate Fremont 14 Street Girders. Id. ¶¶ 13-16. The Transit Center was immediately closed. Id. ¶ 14. These fractures 15 were found by painters working in a part of the Center above a ceiling, which separated that part of 16 the Center from the pedestrian and public access area. Kent Decl. ¶ 3. On September 27, 2018, 17 WOJV filed a claim with Zurich to recover the costs of investigating the damage, installing the 18 shoring, and permanently repairing the property. Stoelting Decl., Ex. B, C. WOJV worked with 19 TJPA to investigate, shore, and make repairs, ultimately spending millions of dollars on this 20 process.3 Gillespie Decl. ¶¶ 15, 17. The Center was reopened to the public in 2019. Id. ¶ 19. 21 TJPA hired LPI, Inc. to determine the cause of the fractures. Id. ¶ 4. On November 12, 22 1 Builder’s Risk Insurance “is a unique form of property insurance that typically covers only 23 projects under construction, renovation, or repair and insures against accidental losses, damages or destruction of property for which the insured has an insurable interest . . . . The purpose of builder’s 24 risk insurance is to compensate for loss due to physical damage or destruction caused to the construction project itself.” Factory Mutual Ins. Co. v. Peri Formworks Systems, Inc., 223 F. 25 Supp. 3d 1133, 1143 (D. Or. 2016) (quoting One Place Condo., LLC v. Travelers Prop. Cas. Co. of Am., No. 11 C 2520, 2015 WL 2226202 at *3 (N.D. Ill. Apr. 22, 2015)) (internal quotation marks 26 omitted).

27 2 The “Insured Project*” is the Salesforce Transit Center. Stoelting Decl., Ex. A. 1 2019, LPI issued its final report. Saraf Decl., Ex. B. at 135 (“LPI Report”). It stated that after the 2 girders were thermally cut to create weld access holes in September 2015, microcracks gradually 3 started to develop. Id. at 184-95; Kent Decl. ¶ 11. Subsequently, when the girders were installed, 4 larger “pop-in cracks” developed at the access holes from residual stress. Id. Due to these “pop-in 5 cracks,” fractures formed in the girders because of the stress from the thermally cut weld access 6 holes and the normal service induced stress. Id. LPI concluded these fractures necessarily occurred 7 between February and April 2018. LPI Report at 134. LPI also concluded the fractures were not 8 formed due to structural design issues, asserting the service induced stress alone would not have 9 caused the fractures had no weld access holes been created. Id. at 185. WOJV hired Exponent, Inc., 10 to determine the nature of the fractures and when they occurred. Saraf Decl. ¶¶ 2-3. Exponent 11 concluded these fractures were “brittle”—meaning they occurred quickly and without warning. Id. 12 ¶ 3. Exponent also concluded the fractures occurred no later than June 2018. Id. 13 Zurich hired Kent Engineering (“Kent”) to conduct its own girder failure analysis. Kent 14 Decl., ¶ 2. On March 28, 2019, Kent issued its report. Stoelting Decl., Ex. D (“Kent Report”). It 15 agreed with LPI’s conclusions and found “3 distinct stages in crack propagation” that occurred from 16 September 2015 to mid-2018. Id. at 2; Kent Decl. ¶¶ 8, 11. These stages were: (1) “microcrack 17 formation at the inner surface of [the weld access holes],” (2) “semi-elliptical pop-in crack extension 18 from the tip of existing microcracks,” and (3) “final girder fracture.” Kent Report at 3. Kent 19 determined mechanical grinding should have been performed to remove the layer of microcracks 20 and prevent the final fractures from occurring. Id. Ultimately, Kent concluded “that the Fremont 21 Street fractures were the result of brittle micro-cracks that eventually grew through the entire girder 22 flange over approximately 30 months.” Kent. Decl. ¶ 8. 23 On April 24, 2019, Zurich denied coverage on the basis that the damage did not manifest 24 until after the policy term’s expiration. Stoelting Decl., Ex. C. at 60 (Coverage Denial Letter). It 25 also stated that since the fractures were due to faulty or defective materials workmanship, coverage 26 was precluded under the policy’s exclusions. Id. 27 On June 6, 2020, WOJV filed the instant motion for partial summary judgment. WOJV 1 Court, 51 Cal. 3d 674 (1990), is limited to insurance claims for progressive loss; (2) as a matter of 2 fact, the fractures in the steel girders occurred suddenly and were not progressive; (3) as a matter of 3 fact, the fractures occurred no later than June 2018, while WOJV was still covered by Zurich’s 4 insurance policy; and (4) as a matter of fact, the fractured girders fall within Zurich’s builder’s risk 5 policy. 6 7 LEGAL STANDARD 8 Summary judgment is proper “if the movant shows that there is no genuine dispute as to any 9 material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). The 10 moving party bears the initial burden of demonstrating the absence of a genuine issue of material 11 fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). The moving party, however, has no burden 12 to disprove matters on which the non-moving party will have the burden of proof at trial. The 13 moving party need only demonstrate to the Court that there is an absence of evidence to support the 14 non-moving party's case. Id. at 325.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Vito Campanelli Peggy Campanelli John Caudillo Barbara Caudillo Neil Damrow Gayle Damrow Nancy Durrant Garfield Ecung Debra Ecung George Giakoumakis Mary Lou Giakoumakis Donald Huner Tommie Jenkins Carrie Jenkins Brenda Kalosh Donald Menck Florence Menck Cheryl Mondheim William Noah Terry Noah Roy Rosenblatt Lorraine Rosenblatt Darla Severn Loyal Smith Mildred Stafford Marilyn Taber, and James House Pat House v. Allstate Life Insurance Company, an Illinois Corporation, and Shadowbrook Design Group, Inc., a California Corporation W.S.C., a California Corporation, Dba Western States Construction, Dba Western States Geotechnical, AKA Western States Companies, Vito Campanelli Peggy Campanelli John Caudillo Barbara Caudillo Neil Damrow Gayle Damrow Nancy Durrant Garfield Ecung Debra Ecung George Giakoumakis Mary Lou Giakoumakis James House Pat House Donald Huner Tommie Jenkins Carrie Jenkins Brenda Kalosh Donald Menck Florence Menck William Noah Terry Noah Roy Rosenblatt Lorraine Rosenblatt Darla Severn Loyal Smith Mildred Stafford Marilyn Taber, and Cheryl Mondheim v. Allstate Life Insurance Company, an Illinois Corporation, and Shadowbrook Design Group, Inc., a California Corporation W.S.C., a California Corporation, Dba Western States Construction, Dba Western States Geotechnical, AKA Western States Companies, Vito Campanelli Peggy Campanelli John Caudillo Barbara Caudillo Neil Damrow Gayle Damrow Nancy Durrant Garfield Ecung Debra Ecung James House Pat House Tommie Jenkins Carrie Jenkins Brenda Kalosh Donald Menck Florence Menck Cheryl Mondheim William Noah Terry Noah Roy Rosenblatt Lorraine Rosenblatt Darla Severn Loyal Smith Mildred Stafford Marilyn Taber Donald Huber, and George Giakoumakis Mary Lou Giakoumakis v. Allstate Life Insurance Company, an Illinois Corporation, Vito Campanelli Peggy Campanelli John Caudillo Barbara Caudillo Neil Damrow Gayle Damrow Nancy Durrant Garfield Ecung Debra Ecung George Giakoumakis Mary Lou Giakoumakis James House Pat House Donald Huner Tommie Jenkins Carrie Jenkins Brenda Kalosh Donald Menck Florence Menck Cheryl Mondheim Roy Rosenblatt Lorraine Rosenblatt Darla Severn Loyal Smith Mildred Stafford Marilyn Taber, and William Noah, Terry Noah v. Allstate Life Insurance Company, an Illinois Corporation, and Shadowbrook Design Group, Inc., a California Corporation W.S.C., a California Corporation, Dba Western States Construction, Dba Western States Geotechnical, AKA Western States Companies
322 F.3d 1086 (Ninth Circuit, 2003)
Montrose Chemical Corp. v. Admiral Insurance
897 P.2d 1 (California Supreme Court, 1995)
Prudential-LMI Commercial Insurance v. Superior Court
798 P.2d 1230 (California Supreme Court, 1990)
Stanton Road Associates v. Pacific Employers Insurance
36 Cal. App. 4th 333 (California Court of Appeal, 1995)
Central National Insurance v. Superior Court
2 Cal. App. 4th 926 (California Court of Appeal, 1992)
Hill v. Allstate Insurance
962 F. Supp. 1244 (C.D. California, 1997)
Fireman's Fund v. Structural Systems Technology, Inc.
426 F. Supp. 2d 1009 (D. Nebraska, 2006)
Kapsimallis v. Allstate Insurance
104 Cal. App. 4th 667 (California Court of Appeal, 2002)
Itow v. United States
223 F. 25 (Ninth Circuit, 1915)
Sapiro v. Encompass Insurance
221 F.R.D. 513 (N.D. California, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Webcor-Obayashi Joint Venture v. Zurich American Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/webcor-obayashi-joint-venture-v-zurich-american-insurance-company-cand-2020.