Webb Construction, Inc. v. City of Shreveport

766 So. 2d 607, 2000 La. App. LEXIS 2072, 2000 WL 1193104
CourtLouisiana Court of Appeal
DecidedAugust 23, 2000
DocketNo. 33,645-CA
StatusPublished
Cited by2 cases

This text of 766 So. 2d 607 (Webb Construction, Inc. v. City of Shreveport) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Webb Construction, Inc. v. City of Shreveport, 766 So. 2d 607, 2000 La. App. LEXIS 2072, 2000 WL 1193104 (La. Ct. App. 2000).

Opinions

| í KOSTELKA, J.

Plaintiff appeals the rejection of his suit to collect damages against a public body for the alleged wrongful award of a construction contract to a competitor. Finding that plaintiff failed to prove he sought a proper remedy as soon as the facts necessary therefor became readily ascertainable, we affirm the judgment of the district court.

Facts and ProcedüRal History

During October 1993, the City of Shreveport (“City”) solicited bids on behalf of the Shreveport Airport Authority to construct an above-ground storage tank fuel farm at the Shreveport Regional Airport. John Webb, on behalf of Webb Construction, Inc., (collectively “Webb”) prepared and submitted a bid in accordance with the specifications. However, when bids were opened and read on November 11, 1993, another enterprise, Netherton Company (“Netherton”), was the apparent low bidder. Webb was the second lowest bidder.

In addition to the specifications for the construction project and other various provisions, the bid documents supplied by the City contained requirements concerning the type of bid bond that would be acceptable. Language appearing at the bottom of the bid bond form designated that “[sjurety companies executing BONDS must appear on the Treasury Department’s most current list ... and be authorized to transact business in the state where the project is located.” A similar definition of an “acceptable surety company” appears in a section of the bid documents entitled “Insurance Requirements for Contractors.” Netherton supplied a bid bond from Patterson Insurance Company (“Patterson”), a surety who did not appear on the requisite Treasury Department List.

Although unaware of the particular facts of the bid which Netherton submitted for this project, Webb did know that Nether-[609]*609ton had encountered financial difficulties during another recent construction project. Thus, at the time | ;.of the bidding process, Webb suspected that Netherton would not be able to post a bond that comported with the bid specifications. Accordingly, five days after the bids were opened (November 16, 1993), Webb wrote a letter to John Eason (“Eason”), the City’s Purchasing Agent, questioning the validity of Nether-ton’s bid bond and requesting copies of those documents for his own review.

On the same date, Tammy Shogren (“Shogren”), the City’s Manager of Administrative Services, composed an inter-office memo directed to Jerry Jones (“Jones”), the City Attorney. Shogren revealed that Eason had informed her that the supplier of Netherton’s bid bond, Patterson, did not meet the qualifications specified in the bid documents, i.e., Patterson was not on the Treasury Department list. She further stated that Eason had already received inquiries about this matter which might lead to a protest of the bid. Shogren sought Jones’s advice as to whether the City could accept the bid and award the contract to Netherton. Although the record contains no evidence of a specific, written response to this inquiry, the contract was, in fact, awarded to Netherton.

Meanwhile, Webb followed his November 16 letter to Eason with periodic phone calls. Webb estimates that he called Ea-son every two or three days. Eason would tell him that the documents were still in the legal department. Eventually, Webb was told that Netherton’s bid ‘bond was satisfactory. But, Webb did not receive the copies of the bid documents he requested. Nevertheless, he made no efforts beyond the letter and phone calls to obtain the documentation.

Finally, in January 1994, Webb received a letter from the City informing him that the contract had been awarded to Nether-ton in December 1993. Shortly thereafter, Webb drove past the project site and noticed that construction had begun. Although satisfied that the City would not have awarded the contract to Netherton had the bid bond been inadequate, Webb remained curious about the situation. Accordingly, he made three separate trips to the courthouse trying to | ¡¡locate the contract . and its supporting documentation. However, the City had neglected to file the contract.

Then, in late February or early March 1994, while meeting with his attorney on an unrelated matter, Webb mentioned his recent experience with the public bid process. The attorney, Evan Rogers (“Rogers”), offered his assistance in procuring the documentation. Thus, on March 2, 1994, Rogers wrote a letter to Jones requesting the bid and contract documents on behalf of Webb.1 Rogers testified that it took four weeks, with one or two phone calls per week, to get a response. In April 1994, Jones finally provided the requested documentation. At that time, Webb first became aware that Patterson was Nether-ton’s surety for the bid bond. Webb also learned that the City had been aware of the problem as early as November 16, 1993. Yet, Jones assured Rogers (and Webb) that the problem had been rectified in that Netherton had substituted certified funds in lieu of the defective bid bond. Rogers then requested copies of the certified funds, as they had not been included with the previously-released documentation.

For nearly two months, Jones assured Rogers that he was collecting the information regarding the certified funds and would supply it as soon as it was available. Finally, on June 19, 1994, Jones called Rogers and admitted that the City had made a mistake and never procured certified funds from Netherton. Yet, the construction project was almost finished by [610]*610this time. Jones revealed that the City was attempting to put together a settlement package for Webb; thus, Rogers believed there was no need to file suit to nullify the contract during this time of open communication between the parties.

1 ¿Ultimately, in mid-August 1994, Jones informed Rogers and Webb that there would be no settlement. Construction on the tank fuel farm was then complete.

Two weeks later, on August 26, 1994, Webb Construction, Inc. filed suit against the City claiming that Netherton’s bid complied with neither the contract provisions nor La. R.S. 38:2218. Webb sought an award for lost profits and other items of damages. The City responded to the petition with an exception of no cause of action which the trial court granted. This court, relying on Airline Construction Co. v. Ascension Parish School Board, 568 So.2d 1029 (La.1990), agreed that Webb had failed to state a cause of action in that he did not seek nullity of the contract or state in specific detail the circumstances that pi'evented him from filing a timely suit for injunction. Webb Construction v. City of Shreveport, 27,761 (La.App.2d Cir.12/06/95), 665 So.2d 653 (“Webb I”). Per La. C.C.P. art. 934, the matter was remanded to afford Webb an opportunity to amend his petition with such allegations as would satisfy the requirements of La. R.S. 38:2220(B) (the Public Contracts Law) and remove the grounds of the exception.

Webb filed his amended petition on December 15, 1995, demanding a judicial declaration of the nullity of the contract between the City and Netherton. He additionally alleged facts regarding the verbal and written requests for information he had made to the City and averred that he did not have sufficient knowledge of any deficiencies until he received the bidding documents, some time after the contract was awarded to Netherton. Again, the City challenged the petition through an exception of no cause of action, claiming that Webb added no new substantive facts but merely reworded and embellished the prior allegations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chanler v. Jamestown Insurance Co.
223 So. 3d 614 (Louisiana Court of Appeal, 2017)
Will Drill Resources, Inc. v. Huggs, Inc.
836 So. 2d 1211 (Louisiana Court of Appeal, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
766 So. 2d 607, 2000 La. App. LEXIS 2072, 2000 WL 1193104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/webb-construction-inc-v-city-of-shreveport-lactapp-2000.