Weaver v. Millard

819 P.2d 110, 120 Idaho 692, 1991 Ida. App. LEXIS 193
CourtIdaho Court of Appeals
DecidedSeptember 27, 1991
Docket18272
StatusPublished
Cited by26 cases

This text of 819 P.2d 110 (Weaver v. Millard) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weaver v. Millard, 819 P.2d 110, 120 Idaho 692, 1991 Ida. App. LEXIS 193 (Idaho Ct. App. 1991).

Opinion

SILAK, Judge.

This dispute arises from an oral contract between a contractor and a partnership for which the contractor constructed commercial fishponds for the partnership business. For the reasons stated below, we affirm the judgment of the district court in favor of the plaintiff contractor, including the order of the district court denying defendants’ motion to disqualify counsel for plaintiff or to disqualify counsel for the third-party defendants. We also affirm the judgment of the district court awarding attorney fees to the third-party defendants.

The district court made the following findings of fact which are pertinent to this appeal. Appellant David Millard (Millard) *695 is a professional civil engineer with considerable experience in the economic analysis and construction of land development projects, including experience with concrete construction. Third-party defendant Mark Lupher (Lupher) managed a fish farm for another company, had his own ponds (the Harral ponds), and had raised catfish in Mississippi before coming to Idaho. Ken Corpron (Corpron) is a fishery specialist who approached Millard about growing catfish using the warm water well on the Millard Ranch located near Buhl, Idaho. Dave Diehl (Diehl) is a professional civil engineer. Roger Krupp (Krupp) is a concrete construction contractor. These men formed a partnership known as the Crystal Springs Warm-Water Aqua-Culture General Partnership (the partnership) for the purpose of raising catfish to be sold for processing.

On February 28, 1986, Lupher, Millard, and Corpron signed an agreement of understanding which set out the responsibilities of the parties and the purposes of the partnership. The agreement projected total costs of $130,800, including $27,000 for construction of the ponds with a $7,400 contingency. The agreement provided that Lupher and Corpron would receive a management fee for designing and managing the facility as well as for purchasing and marketing the fish. Lupher also contracted with the partnership to supply the fingerlings and then purchase the adult catfish for processing. Millard was to be responsible for water right acquisition, land, conveyance system design, and facility construction.

In June, 1986, a partnership agreement was executed incorporating the agreement of understanding and other agreements. Millard, the managing partner, delegated the authority for construction of the facility to Lupher. Although Millard gave Lupher a draft set of plans for the ponds, the design, site selection, and construction decisions were fully vested in Lupher. Lupher decided to use a different design.

On August 27, 1986, Lupher entered into an oral time-and-materials contract with respondent Dan Weaver, doing business as Dan Weaver Construction (collectively, Weaver), to build the concrete fishponds for the partnership. Weaver began construction shortly thereafter, and Lupher supervised the construction on a daily basis. On October 1, 1986, when the construction was partially complete, Weaver billed the partnership $21,233.07 for pond construction and an additional amount for moving some water lines. The partnership paid Weaver $22,392.27 on October 10, 1986.

At a partnership meeting on October 13, 1986, concern was expressed at the cost of the ponds. The partners viewed the site and agreed that construction would continue under Lupher’s direction. Lupher, after a brief on-site consultation with Weaver, reported that the ponds were 75% complete and projected an additional expenditure of $8,000 to $10,000 to finish the project. No partner expressed any objection to the design, layout, or workmanship of the ponds at that time.

On November 1, 1986, Weaver billed the partnership $18,723.76, and Millard, approximately two days prior to completion of the construction, ordered Weaver to stop work on the project. The partnership did not pay Weaver’s November bill. Weaver filed a materialman’s lien on the property and, on December 17,1986, filed this suit to foreclose the lien. On April 23, 1987, the partnership answered the complaint and counterclaimed, alleging that the work was not performed in a workmanlike manner. The partnership also filed a third-party complaint against Lupher alleging that Lupher breached the partnership agreement. Lupher responded to the third-party complaint on July 31, 1987. On September 8, 1988, the appellants moved to disqualify either counsel for Weaver or counsel for Lupher on the ground that Weaver and Lupher were represented by members of the same law firm. The district court denied the motion on October 12, 1988.

On October 31, 1988, the district court granted Lupher’s motion for summary judgment and dismissed the partnership’s third-party claim against him on the ground that, as a matter of law, the part *696 nership could not maintain an action against Lupher other than an action to dissolve the partnership and for final accounting. The partnership has not appealed from the order granting the motion for summary judgment.

Millard and the partnership then filed another third-party complaint requesting dissolution of the partnership, I.C. § 53-332, and a final accounting, I.C. § 53-340, on the ground that Lupher’s negligent supervision of the construction of the fishponds prejudicially affected the carrying on of the partnership business and/or made it not reasonably practicable to carry on the business in partnership with Lupher. The district court consolidated this third-party claim with the Weaver’s action against the partnership.

The court conducted a six-day bench trial after which it entered its findings of fact and conclusions of law. The district court entered a $5,813.63 judgment for Weaver on the contract, but refused to foreclose the materialman’s lien because Weaver’s statement of demand failed to reflect deductions for just credits and offsets. See I.C. § 45-507. The court determined the amount of the judgment by deducting the following amounts from Weaver’s November 1, 1986, bill to the partnership: $7,497 paid by the partnership directly to the concrete company which supplied the concrete for the ponds; $1,313.37 offset for labor overcharges; and $719.76 offset for concrete overcharges. The court further reduced the amount due Weaver by $3,380, the cost of repairs necessary to put the fishponds in operating order and required as a result of Weaver’s poor workmanship. 1 The court also denied the third-party claim against Lupher.

After additional proceedings to resolve the parties’ disputes as to the proper amount and proper bases on which to award costs and attorney fees, the court ultimately entered judgment for Lupher against the partnership for costs and attorney fees pursuant to I.C. § 12-120(3) and I.R.C.P. 54(e). The court denied costs and attorney fees to Weaver, but allowed costs against Weaver to the partnership pursuant to I.R.C.P. 68.

I. Attorney Disqualification

In district court, as in this appeal, the law firm of Decker and Hollifield represented both Weaver and Lupher; William R. Hollifield represented Weaver, and Fred Decker represented Lupher. The partnership moved, pursuant to Rules 1.7(b) and 1.10(a) of the Idaho Rules of Professional Conduct, 2 to disqualify either Decker or Hollifield.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lowman v. Morgan-Smart
564 P.3d 1203 (Idaho Supreme Court, 2025)
Litster Frost v. Idaho Injury Law Group
518 P.3d 1 (Idaho Supreme Court, 2022)
Nielson v. Talbot
Idaho Supreme Court, 2018
Bettwieser v. New York Irrigation District
297 P.3d 1134 (Idaho Supreme Court, 2013)
State v. Bennett J. Bartlett
298 P.3d 1074 (Idaho Court of Appeals, 2013)
Foster v. Traul
175 P.3d 186 (Idaho Supreme Court, 2007)
Arkansas Valley State Bank v. Phillips
2007 OK 78 (Supreme Court of Oklahoma, 2007)
Reding v. Reding
109 P.3d 1111 (Idaho Supreme Court, 2005)
Champion Produce, Inc. v. Ruby Robinson Co.
342 F.3d 1016 (Ninth Circuit, 2003)
Doe v. Doe
71 P.3d 1040 (Idaho Supreme Court, 2003)
Jenkins v. Jenkins
64 P.3d 953 (Idaho Supreme Court, 2003)
Chapple v. Madison County Officials
967 P.2d 278 (Idaho Supreme Court, 1998)
Parkland Corp. v. Maxximum Co.
920 F. Supp. 1088 (D. Idaho, 1996)
Crown v. Hawkins Co., Ltd.
910 P.2d 786 (Idaho Court of Appeals, 1996)
Paul S. Damron v. Vern Herzog, Jr.
67 F.3d 211 (Ninth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
819 P.2d 110, 120 Idaho 692, 1991 Ida. App. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weaver-v-millard-idahoctapp-1991.