We-Mac Manufacturing Co. v. Mid-State Petroleum Equipment, Inc.

827 S.W.2d 257, 18 U.C.C. Rep. Serv. 2d (West) 1078, 1992 Mo. App. LEXIS 548
CourtMissouri Court of Appeals
DecidedMarch 24, 1992
DocketWD 44985
StatusPublished
Cited by1 cases

This text of 827 S.W.2d 257 (We-Mac Manufacturing Co. v. Mid-State Petroleum Equipment, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
We-Mac Manufacturing Co. v. Mid-State Petroleum Equipment, Inc., 827 S.W.2d 257, 18 U.C.C. Rep. Serv. 2d (West) 1078, 1992 Mo. App. LEXIS 548 (Mo. Ct. App. 1992).

Opinion

BERREY, Judge.

Appellant appeals from the judgment entered against it in the sum of $14,167.83, in this court-tried case. The trial court also entered judgment for the respondent on appellant’s counterclaim and appellant appeals.

Appellant alleges the trial court erred first in finding appellant had contracted for a 9' x 25' tank. Appellant next alleges the trial court erred in finding appellant did not have the right to reject the 9' X 25' tank. For its third point, appellant contends the finding of the trial court is against the weight of evidence. And finally, appellant contends the trial court erred in failing to award appellant damages on its counterclaim.

On September 11, 1990, John Dotson, a principal of appellant, phoned We-Mac Manufacturing Co. He talked with Richard Ramey, a member of respondent’s sales staff. Dotson priced gasoline storage tanks and tie-down straps together with freight charges. According to Ramey they talked about two tanks, a 15,000 gallon tank, 11' in diameter by 21' long and a 12,000 gallon tank, 9' in diameter by 25' long. Ramey testified We-Mac manufactures two sizes of the 12,000 gallon tank, the 9' by 25' tank and a 8' X 32' tank. At trial, a written memo memorializing this conversation was introduced.

According to Ramey the two sizes of 12,000 gallon tanks were discussed with appellant. Ramey explained that the 9' X 25', 12,000 gallon tank could be delivered with the 15,000 gallon tank and save appellant the cost of a separate haul. Ramey explained that in Missouri the maximum length for a load is 53 feet. The 15,000 gallon tank and the 12,000 gallon tank that was 9' X 25' would fit the truck, as the total length would be about 46 feet. If the other 12,000 gallon tank was ordered the total length would be 53 feet, requiring a special permit to transport them.

Ramey testified that Dotson did not place an order on this date, but that an order was placed on September 12, 1990, over the phone by someone named Don with Dotson’s company. Don proceeded to give Ramey a purchase order, number 2880, which Ramey entered on his shipping order sheet. According to the shipping *259 order, Don ordered a 15,000 gallon tank 11' X 21' and a 12,000 gallon tank 9' X 25'. Following this oral phone agreement, appellant sent We-Mac a written order for an 11' X 21' tank and an 8' X 32' tank. On October 5, 1990, the tanks were delivered to appellant at his site in Mexico, Missouri. We are mindful that under Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976), the judgment of the trial court will be sustained on appellate review, “unless there is no substantial evidence to support it, unless it is against the weight of the evidence, unless it erroneously declares the law, or unless it erroneously applies the law.” Id.

In its first point, appellant alleges the court erred in finding it contracted for a 9' by 25' tank. An appellate court defers to the trial court’s determination even if the evidence might support a different conclusion in a court-tried case. Price v. American Bank of St. Louis, 793 S.W.2d 593, 598 (Mo.App.1990).

On October 6, Dotson called Ramey and told him he had shipped the wrong dimension 12,000 gallon tank. Due to labor and additional welds, the 8 foot diameter tank was more expensive than the 9'. This was discussed and the parties agreed to “split the difference in the cost.” Appellant was to pay a second delivery charge. We-Mac picked up the 9' diameter tank and placed it in its inventory. We-Mac wrote up the order as it had the previous order.

Ramey testified that an order form is always completed following receipt of the order. The 8' tank was subsequently delivered to appellant on October 10, 1990. An invoice was prepared shortly after delivery of the tanks, however, the total invoice amount of $14,398.83, was not paid. Appellant’s testimony was to the contrary. Appellant contended it had originally ordered an 8' 12,000 gallon tank. Further, appellant alleged in its counterclaim that We-Mac did not deliver the proper size tank timely and as a direct and proximate result of the failure, appellant sustained additional construction site costs.

Respondent presented substantial evidence to support the trial court’s determination. Mr. Ramey testified a 9' X 25' tank was ordered during a phone conversation. He supported this contention by producing a memorandum memorializing the substance of the conversation. Mr. Ramey also produced an order form which showed an order for a 9' X 25' tank as well as an 11' X 21' tank. The trial court has the ability to judge the credibility of the witnesses and is free to believe or disbelieve all, part, or none of the testimony of any witness. T.B.G. v. C.A.G., 772 S.W.2d 653, 654 (Mo.1989). The trial court found appellant had contracted for a 9' tank. We find no reason to disturb this finding on appeal. Appellant’s point I is denied.

Points II and III of appellant’s argument will be addressed together. Appellant alleges in Point II it could reject the order under § 400.2-607, RSMo 1986, and under Point III that in the alternative the trial court erred in holding appellant did not have the right to reject the order pursuant to § 400.2-207(2), RSMo 1986.

Section 400.2-207 of the Uniform Commercial Code (UCC) is applicable to this transaction and provides:

(1) A definite and seasonable expression of acceptance or a written confirmation which is sent within a reasonable time operates as an acceptance even though it states terms additional to or different from those offered or agreed upon, unless acceptance is expressly made conditional on assent to the additional or different terms.
(2) The additional terms are to be construed as proposals for addition to the contract. Between merchants such terms become part of the contract unless:
(a) the offer expressly limits acceptance to the terms of the offer;
(b) they materially alter it; or
(c) notification of objection to them has already been given or is given within a reasonable time after notice of this is received.

Appellant and respondent had reached an oral agreement and it was not changed because appellant sent a written confirmation containing different terms. *260 Central Bag Co. v. W. Scott & Co., 647 S.W.2d 828 (Mo.App.1983). Since appellant and respondent are merchants a different term becomes part of the contract unless it materially alters the contract. The substitution of an 8' tank for a 9' tank is a material alteration, and therefore, did not become part of the original contract under § 400.2-207(2)(b).

Section 400.2-601, RSMo 1986, states in part:
If the goods or the tender of delivery fail in any respect to conform to the contract, the buyer may,
(a) reject the whole; or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farning v. Brendal
150 S.W.3d 384 (Missouri Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
827 S.W.2d 257, 18 U.C.C. Rep. Serv. 2d (West) 1078, 1992 Mo. App. LEXIS 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/we-mac-manufacturing-co-v-mid-state-petroleum-equipment-inc-moctapp-1992.