WC James, Inc. v. Phillips Petroleum Company

347 F. Supp. 381, 1972 U.S. Dist. LEXIS 12165
CourtDistrict Court, D. Colorado
DecidedAugust 29, 1972
DocketCiv. A. C-3069
StatusPublished
Cited by4 cases

This text of 347 F. Supp. 381 (WC James, Inc. v. Phillips Petroleum Company) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WC James, Inc. v. Phillips Petroleum Company, 347 F. Supp. 381, 1972 U.S. Dist. LEXIS 12165 (D. Colo. 1972).

Opinion

MEMORANDUM OPINION, FINDINGS OF FACT AND CONCLUSIONS OF LAW

WINNER, District Judge.

Plaintiff, a pipeline contractor, is a Nevada corporation with principal offices in Utah. Defendant, a petroleum producer and marketer, is a Delaware corporation with principal offices in Oklahoma. Diversity jurisdiction exists.

On June 23, 1970, the parties entered into a written contract by which plaintiff agreed to construct a 205,452 foot gas gathering pipeline system for defendant in the Highlight Field in Campbell County, Wyoming. The contract was awarded on bids which were submitted under a somewhat complicated pricing formula, and plaintiff’s bid was $215,007, with the next three low bids being $219,396, $219,472' and $224,435. 1 The contract required a 60-day completion, and, following oral agreement entered into in late June or early July, 1970, another 92,400 feet of line were added by supplemental agreement dated July 31, 1970. Time for completion was not extended by the written supplement, but at trial the parties were in substantial agreement that the completion date was extended another 30 days.

We do not here have a case in which Phillips is complaining about the con *383 tractor’s failure to complete the work on time, but, rather, we have alternative claims by the contractor against Phillips, and these alternative claims are phrased in the stipulated pretrial order as follows:

“First Claim: That defendant breached its contract by (1) requiring plaintiff to perform more work in installing more complex meter runs than the contract .drawings required, (2) requiring plaintiff to move each of plaintiff’s crews a disproportionately greater number of times than the contract specifically required or reasonably implied, (3) failing to provide rights of way as required by the contract and in advance of the time that plaintiff was ready to work thereon, (4) failing to permit plaintiff to exercise complete and authoritative control over the work and the details and means of doing the work, and (5) failing to deliver pipe and other materials to the job site or to Douglas, Wyoming, in the correct sizes, in sufficient quantities, or at such times as were impliedly promised by Defendant as a necessary incident to the contract, or were reasonable, or were repeatedly promised by defendant’s employees.
“Said breaches were either willful or constituted active interference with Plaintiff’s work under the contract. As a proximate result of the breaches, (1) plaintiff was required to perform a great amount of additional work at greatly increased costs to install meter runs, (2) each of plaintiff’s crews was required to travel from one meter setting to another, to move the equipment with which the work was being performed, and to spend many hours of non-productive time in connection with each move, (3) plaintiff was unable to perform any right of way work for approximately 75 days, was unable to perform the pipe welding phase of the work for approximately 32 days, was required to work in inclement weather at greatly increased costs which otherwise would have been avoided, was required to incur additional expenses in connection with the employment and use of the stringing, bending, pipe laying, tape and tie-in, backfill and clean-up and air test crews, was required to incur additional expense for the rental of equipment, for job supervision, and for additional overhead for nine additional weeks, and (4) plaintiff was unable to plan and perform the work in an efficient and economical manner with the result that plaintiff’s costs and expenses were substantially increased throughout the period of construction. As a proximate result of the aforesaid breaches, plaintiff has suffered three types and amounts of damages: (1) direct on the job losses were $295,-875.43, (2) loss of anticipated profits on the job were $65,000.00, and (3) damage to its credit and reputation and loss of its business were $400,000.-00.
“Second Claim: Plaintiff claims that Contract PP-8402 is against public policy because Plaintiff had no reasonable choice, because of the gross superiority of defendant’s bargaining power, but to adhere to unreasonable one-sided standard form terms which were unilaterally prepared by defendant. Said contract was a contract of adhesion in that it contained, in many pages of fine print, in paragraphs 2, 3, 3(d), 4, 4(a), 4(b), 4(c), 5, 6(e), 6(d), 7, 10, 10(a), 18, 19, 22, and 31 among others, provisions which were deceptive or unfair to plaintiff or one-sided in defendant’s favor. Said contract had for its object, directly or indirectly, to exempt defendant from liability for its own willful injury to plaintiff’s property and its own defaults and actions which interfered with the performance of the work by plaintiff or contributed substantially to plaintiff’s costs and expenses in performing the work. Said contract was therefore unlawful, void, against public policy, and unenforceable, entitling plaintiff to recover, on a quantum meruit basis, for material, machín *384 ery, equipment and labor used, done and performed by plaintiff.
“Plaintiff alleges the reasonable value of all material, machinery, equipment and labor was $760,000.00; that defendant has paid plaintiff $404,124.57, leaving a balance due of $360,875.43. In addition, plaintiff asserts damage to its credit and reputation and loss of its business were $400,000.00.”

Defendant, of course, denies liability, and it says that plaintiff was paid in full under an enforceable contract. Additionally, defendant says that all claims for extras and all disputes were settled by mutual agreement prior to the filing of this case and that there was an accord and satisfaction.

The preliminaries to the basic contract were these :

Under date of May 11, 1970, Phillips invited plaintiff to bid on the job. The invitation letter advised bidders of the names, addresses and telephone numbers of Phillips representatives to contact if the bidders had any questions concerning the proposed work or concerning the bid documents. The bid instructions said, “Bidders shall inspect the site of the work and obtain a sufficient knowledge of existing conditions as affect this work;” and the contract said, “ . . . Contractor shall assume entire responsibility for examination of the site of the work and for acquaintance with conditions that may exist or develop during the term of the contract.” A form of the contract was included in the bid pack as were a set of the engineering standards to be followed. Although some other bidders visited the site, plaintiff, who had done work in the area before, believed that it was not necessary to inspect the site, and he did not do so, although he did fly over it. Nor did he contact any of the named Phillips’ representatives to ask about the work which would be required under the proposed contract, although he did discuss the job with Phillips' representatives before the contract was signed. During that discussion he indicated that he planned to lay 8,000 ft. of pipe per day, but he did not say that his bid was conditioned on his ability to do so.

In preparing his bid, James relied on his past experience and on a “typical drawing” of a meter installation which was only partially dimensioned and which showed on its face that it was not drawn to scale.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Dressel
623 P.2d 370 (Supreme Court of Colorado, 1981)
Green v. Clinic Masters, Inc.
272 N.W.2d 813 (South Dakota Supreme Court, 1978)
Clinic Masters v. District Court for Cty. of El Paso
556 P.2d 473 (Supreme Court of Colorado, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
347 F. Supp. 381, 1972 U.S. Dist. LEXIS 12165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wc-james-inc-v-phillips-petroleum-company-cod-1972.