Waycross Air-Line Railroad v. Offerman & Western Railroad

40 S.E. 738, 114 Ga. 727, 1902 Ga. LEXIS 778
CourtSupreme Court of Georgia
DecidedFebruary 6, 1902
StatusPublished
Cited by12 cases

This text of 40 S.E. 738 (Waycross Air-Line Railroad v. Offerman & Western Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waycross Air-Line Railroad v. Offerman & Western Railroad, 40 S.E. 738, 114 Ga. 727, 1902 Ga. LEXIS 778 (Ga. 1902).

Opinion

Cobb, J.

The Offerman and Western Railroad Company brought, in the superior court of Ware county, an action against the Way-cross Air-Line Railroad Company and others upon a bond in which the defendant .company was principal and the other defendants were securities, alleging in substance as follows: Both plaintiff and the defendant company are corporations created under the laws of Georgia, the latter having its chief office in Ware county. Plaintiff was authorized by its charter to construct a line of railroad from Offerman in the county of Pierce to Nicholls in the county of Coffee, and, in order to reach the place selected as its terminus-at Nicholls, was compelled to cross the tracks of the defendant company at that point. Near the terminus was a large sawmill operated by the Southern Pine Company, and the output from its mill was necessarily shipped over the line of the defendant company, and itwell knew that if the plaintiff wasallowed to cross its tracks and reach the plant of the Southern Pine Company, on account of the community of interest between the stockholders of the latter company and the plaintiff the business of the defendant company would be necessarily lessened, the plaintiff being under agreement with the Southern Pine- Company to move the output of its mill when in position to handle the traffic, which was also well known to the defendant company. The defendant company desiring, by reason of the facts above mentioned, to prevent the completion of the plaintiff’s road, applied for an injunction to restrain it from prosecuting a proceeding which it had instituted to condemn a right of way across the tracks of the defendant company, and on October- 9, 1899, procured a restraining order having that effect. On December 16,1899, the application forinjunction coming onfor a hearing, the temporary restraining order was rescinded and the application for injunction was denied. On December 23, the defendant company had certified a bill of exceptions assigning error upon the refusal of the judge to grant the in junction, and procured an order allowing a supersedeas of the judgment rescinding the restraining order and denying the injunction until the final determination of the case in the Supreme Court, upon condition that a bond should be given with good security in the sum of $10,000, conditioned to pay to the plaintiff all of the damages which it should sustain by reason of any delay resulting from the granting of the restraining order and the continuing of the same in force. [729]*729The honcl required by this order was given, a copy of the same being exhibited to the petition. The condition of the bond was to pay to the plaintiff all damages which it “ should suffer by reason of any delay entailed upon it by reason of its being restrained from condemning a right of way across the Way cross Air-Line Railroad at Nicholls from the time when said crossing could have been condemned up to the time when the said crossing should he actually put in and the road put in operation,” in the event the judgment refusing the injunction should be affirmed by the Supreme Court. On the 27th day of February, 1900, the Supreme Court affirmed the judgment refusing the injunction. See Waycross R. Co. v. Offerman R. Co., 109 Ga. 827. The prosecution of the writ of error in the Supreme Court delayed the operations of the plaintiff until March 10, 1900, when the damages for crossing the tracks of the defendant company were fixed by assessors, duly tendered aud accepted, and the crossing made. In the interval from the 23d of December, 1899, to the 10th of March, 1900, the amount that the plaintiff would have earned per day if it had been allowed to cross the tracks of the defendant company is distinctly alleged, as well as what would have been the expense attendant upon the making of such earnings; and attached to the petition are exhibits showing the quantity of freight which had been shipped by the Southern Pine Company over the line of the defendant company between the dates above mentioned, with the amounts which had been received by the defendant company as freight from such shipments; such exhibits showing that the actual loss sustained-by the plaintiff company on account of its inability to reach its terminus and to haul the freights of the Southern Pine Company amounted in the aggregate to more than $2,500. It is alleged that the earnings so lost are not speculative but certain in character, being amounts which would have been earned by the plaintiff company from hauling the shipments from the sawmill of the Southern Pine Company, which would have been shipped over the line of the plaintiff if its line had been completed, and that the failure of the plaintiff to receive such freight was entirely due to the action of the defendant company in preventing it from completing its line by constructing a crossing over the tracks of the defendant company, and that these damages were in contemplation of the parties at the time the bond sued on was executed. The defendants demurred to the petition; and their demurrers having been overruled, they excepted.

[730]*7301, 2. It is contended that the court erred in overruling the demurrer, for the reason that it appeared from the petition that the superior court of Ware county was without jurisdiction. While the principal office of the defendant company is located in the county of Ware, it is said that as the contract was made and was to be performed in the county of Pierce, and that as the wrong and injury complained of was done in the county of Coffee, the suit should have been brought either in the proper court in the county of Pierce or of Coffee. By the Civil Code, § 2334, it is provided: “All railroad companies shall be sued in the county in which the cause of action originated, . . and also on all contracts made or to be performed in the county where suit is brought; any judgment rendered in any other county than the one in which the cause so originated shall be utterly void.” So far as the contention that the suit should have been brought in the county of Coffee is concerned, it is sufficient to say that the suit is not brought for any tort or wrong done in that county, but it is an action upon a contract; and therefore the question to be determined is, where a suit of this character is to be brought. It is true that the damages resulted to the plaintiff from its inability to complete its line of road in Coffee county, on account of the injunction which had been obtained in Pierce county; but the cause of action in the present case is not anything done in Coffee county, but is the breach of a contract entered into by the defendants in another county. The bond sued on does not appear on its face to have been executed in Pierce county. The signatures to the bond are attested by a notary-public in Ware county, and from this it might be inferred that it was made in that county. But even treating the contract as one made in Pierce county, while the plaintiff had a right to bring the action in that county because the contract was made there, still it was not absolutely necessary that the action should be brought there, if the contract was to be performed in another county. The undertaking in the bond was to pay damages upon the happening of a certain condition, and the place at which the defendant company could be called on to pay these damages was at the place of its residence, that is, where its principal office was located, and this would be the place where the contract was to be performed. If the bond sued on had been an instrument where demand for performance had to, be made before suit, demand would have had to be made in the county of Ware; [731]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Seaford v. Eastern Shore Public Service Co.
24 A.2d 436 (Superior Court of Delaware, 1942)
State Ex Rel. Seattle National Bank v. Joiner
244 P. 551 (Washington Supreme Court, 1926)
Haas & Haas v. Marks
123 S.E. 109 (Supreme Court of Georgia, 1924)
Firestone Tire & Rubber Co. v. Shore
121 S.E. 709 (Court of Appeals of Georgia, 1924)
Martin v. Hight
118 S.E. 595 (Court of Appeals of Georgia, 1923)
Whitlock v. Mozley & Co.
82 S.E. 886 (Supreme Court of Georgia, 1914)
Jones v. Rountree
74 S.E. 1096 (Court of Appeals of Georgia, 1912)
Morel v. Sylvania & Girard Railroad
68 S.E. 588 (Supreme Court of Georgia, 1910)
Carolina Portland Cement Co. v. Columbia Improvement Co.
60 S.E. 279 (Court of Appeals of Georgia, 1908)
Anderson v. Hilton & Dodge Lumber Co.
49 S.E. 725 (Supreme Court of Georgia, 1905)
Waycross Air-Line Railroad v. Offerman & Western Railroad
47 S.E. 582 (Supreme Court of Georgia, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
40 S.E. 738, 114 Ga. 727, 1902 Ga. LEXIS 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waycross-air-line-railroad-v-offerman-western-railroad-ga-1902.