Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc.

2018 Ohio 4748
CourtOhio Court of Appeals
DecidedNovember 20, 2018
Docket17CA885
StatusPublished
Cited by1 cases

This text of 2018 Ohio 4748 (Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc., 2018 Ohio 4748 (Ohio Ct. App. 2018).

Opinion

[Cite as Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc., 2018-Ohio-4748.]

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT PIKE COUNTY

WAVERLY CITY SCHOOL DISTRICT : BOARD OF EDUCATION, et al., : : Plaintiffs-Appellants, : Case No. 17CA885 : v. : DECISION AND : JUDGMENT ENTRY TRIAD AR, INC., et al., : : Defendants-Appellees. : RELEASED 11/20/2018

APPEARANCES:

Michael DeWine, Ohio Attorney General, and William C. Becker, Jerry Kasai, Craig Barclay, and Howard H. Harcha IV, Assistant Ohio Attorneys General, Columbus, Ohio, for plaintiff- appellant Ohio School Facilities Commission.

Mark A. Foley, Columbus, Ohio, for plaintiff-appellant Waverly City School District Board of Education and Special Counsel for Ohio School Facilities Commission.

J. Stephen Teetor, Scyld D. Anderson, and Lee W. Westfall, Isaac Wiles Burkholder & Teetor, LLC, Columbus, Ohio, for defendant-appellee Crace Construction Company.

Donald W. Gregory and Eric B. Travers, Kegler Brown Hill + Ritter Co. LPA, Columbus, Ohio, for defendant-appellee Ohio Farmers Insurance Company as surety for Crace Construction Company.

Bradley J. Barmen, Lewis Brisbois Bisgaard and Smith, Cleveland, Ohio, for defendant-appellee Terracon Consultants, Inc.

Hoover, P.J.

{¶ 1} This appeal arises from the Pike County Court of Common Pleas’ decision and

journal entry granting summary judgment to defendants-appellees Crace Construction Company

(“Crace”), Terracon Consultants, Inc. (“Terracon”), and Ohio Farmers Insurance Company, Inc.

(“OFIC”) (as surety for Crace) (collectively “appellees”), and to defendants J&H Reinforcing & Pike App. No. 17CA885 2

Structural Erectors, Inc. (“J&H”) and OFIC (as surety for J&H), in a dispute over a school

construction project in Waverly, Ohio. The trial court determined that plaintiffs-appellants

Waverly City School District Board of Education (“Waverly”) and the Ohio School Facilities

Commission (“OSFC”)1 (collectively “appellants”), had already been made whole via prior

settlements with co-defendants Staggs Roofing Inc. (“Staggs”), Tremco, Inc. (“Tremco”), OFIC

(as surety for Staggs), BBL Ohio, LLC/DAG Construction Co. (“BBL”), and Triad AR Inc.

(“Triad”), and therefore were not entitled to recover further damages from any of the appellees

under their remaining breach of contract claims. In addition, the trial court reasoned that because

appellants could not set forth evidence apportioning fault/damages among the various co-

defendants, appellants could not recover further damages from the remaining non-settling

appellees. On appeal, Waverly and OSFC seek reversal of the trial court’s decision and journal

entry.

{¶ 2} For the reasons discussed below, we disagree with the trial court that the

appellants’ settlements with the settling co-defendants extinguish their remaining breach of

contract claims against the non-settling appellees. Furthermore, we disagree with the trial court’s

determination that because appellants’ experts could not apportion fault/damages among the

various co-defendants their claims for breach of contract could no longer survive. Therefore, we

conclude that the trial court did not properly grant summary judgment in favor of the appellees

on appellants’ breach of contract claims. Accordingly, the judgment of the trial court is reversed;

and this matter is remanded to the trial court for further proceedings consistent with this opinion.

I. Facts and Procedural Posture

1 Following commencement of this lawsuit, H.B. 49, Section 515.10, effectively changed the name of plaintiff- appellant Ohio School Facilities Commission to the Ohio Facilities Construction Commission. Nevertheless, to maintain consistency with the language employed by the trial court, we use the commission’s former name throughout this opinion. Pike App. No. 17CA885 3

A. The Project

{¶ 3} The Waverly school construction project (hereinafter the “Project”), spanning a

time period between 2002-2004, involved the building of a campus of four separate schools2 at

an original cost of nearly $50 Million. Waverly and OSFC jointly funded the Project. Rather than

having a general contractor performing all construction, the Project called for multiple prime

contractors, each with specific scopes of work. There were separate contracts with four prime

contractors: Crace, masonry/concrete walks; Staggs, roofing; J&H, general trades/floor slab; and

George J. Igel and Company, Inc. (“Igel”), site preparation. There were separate contracts with

an architect, Triad, for design and oversight/quality control, and a construction manager, BBL,

for oversight/quality control. There was also a contract with geo-technical firm, Terracon (fka

H.C. Nutting Company), to provide evaluation of the construction site and soil testing during

construction.

B. Construction Defects and Remediation

{¶ 4} Waverly took occupancy of the Project at the beginning of the 2004-2005 school

year, and immediately experienced major water intrusion problems at all four buildings. In

addition, another problem developed with the concrete floor slab in ES-2 heaving in the

gymnasium and adjacent classrooms. After several years of failed attempts to fix the problems,

the appellants hired CTL Engineering (“CTL”) and Schooley Caldwell & Associates (“SCA”) to

investigate the causes of the water intrusion problems, as well as the heaving floor slab in ES-2.

CTL and SCA issued reports, and were able to classify the Project’s construction defects into

three separate categories, namely: (1) roofing; (2) masonry; and (3) general trades/floor slab.

CTL also identified design defects attributable to Triad. The appellants hired Robertson

2 The schools were: (1) Elementary School 1 (“ES-1”); (2) Elementary School 2 (“ES-2”); (3) Junior High School; and (4) High School. Pike App. No. 17CA885 4

Construction Services (“RCS”) to remediate the defective work. Remediation was performed

from 2013-2015 at a total cost of $6,592,887.84.3 This amount included the total of sums billed

by RCS for the design and repairs of the roof, masonry, concrete, soils, and all other work at all

four buildings of the Waverly campus. This sum also included an admitted betterment of

$863,306.

C. The Original Complaint

{¶ 5} The appellants filed their original complaint in August 2013 and asserted claims

against Crace, Staggs, J&H, Igel, and OFIC as surety for the contractors, for their defective

work; against Triad, for its design and oversight failures; and against BBL for its oversight

failures. The claims included breach of contract and breach of warranties claims against the

prime contractors; indemnification under the surety bonds against OFIC; and negligence and

breach of contract claims against BBL and Triad.

D. The Amended Complaints

{¶ 6} After initial discovery Igel was voluntarily dismissed from the lawsuit. Thereafter,

the appellants filed an amended complaint on December 11, 2014, adding Terracon as a

defendant and asserting claims of negligence and breach of contract for the floor slab heaving

issue and its failure to properly test the soil and advise with respect to the heaving floor slabs in

ES-2.

{¶ 7} Roofing installer Staggs filed a third-party complaint against roofing materials

supplier and inspector, Tremco. Tremco counterclaimed against Staggs, asserting a right to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yousef v. Yousef
2019 Ohio 3656 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 4748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waverly-city-school-dist-bd-of-edn-v-triad-ar-inc-ohioctapp-2018.