Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc.

2018 Ohio 4748
Ohio Court of Appeals·Decided November 20, 2018·No. 17CA885·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT PIKE COUNTY

WAVERLY CITY SCHOOL DISTRICT : BOARD OF EDUCATION, et al., :

:

Plaintiffs-Appellants, : Case No. 17CA885 :

v. : DECISION AND : JUDGMENT ENTRY TRIAD AR, INC., et al., :

:

Defendants-Appellees. : RELEASED 11/20/2018

APPEARANCES:

Michael DeWine, Ohio Attorney General, and William C. Becker, Jerry Kasai, Craig Barclay, and Howard H. Harcha IV, Assistant Ohio Attorneys General, Columbus, Ohio, for plaintiff- appellant Ohio School Facilities Commission.

Mark A. Foley, Columbus, Ohio, for plaintiff-appellant Waverly City School District Board of Education and Special Counsel for Ohio School Facilities Commission.

J. Stephen Teetor, Scyld D. Anderson, and Lee W. Westfall, Isaac Wiles Burkholder & Teetor, LLC, Columbus, Ohio, for defendant-appellee Crace Construction Company.

Donald W. Gregory and Eric B. Travers, Kegler Brown Hill + Ritter Co. LPA, Columbus, Ohio, for defendant-appellee Ohio Farmers Insurance Company as surety for Crace Construction Company.

Bradley J. Barmen, Lewis Brisbois Bisgaard and Smith, Cleveland, Ohio, for defendant-appellee Terracon Consultants, Inc.

Hoover, P.J.

{¶ 1} This appeal arises from the Pike County Court of Common Pleas’ decision and journal entry granting summary judgment to defendants-appellees Crace Construction Company (“Crace”), Terracon Consultants, Inc. (“Terracon”), and Ohio Farmers Insurance Company, Inc. (“OFIC”) (as surety for Crace) (collectively “appellees”), and to defendants J&H Reinforcing &

Pike App. No. 17CA885 2

Structural Erectors, Inc. (“J&H”) and OFIC (as surety for J&H), in a dispute over a school construction project in Waverly, Ohio. The trial court determined that plaintiffs-appellants Waverly City School District Board of Education (“Waverly”) and the Ohio School Facilities Commission (“OSFC”)1 (collectively “appellants”), had already been made whole via prior settlements with co-defendants Staggs Roofing Inc. (“Staggs”), Tremco, Inc. (“Tremco”), OFIC (as surety for Staggs), BBL Ohio, LLC/DAG Construction Co. (“BBL”), and Triad AR Inc. (“Triad”), and therefore were not entitled to recover further damages from any of the appellees under their remaining breach of contract claims. In addition, the trial court reasoned that because appellants could not set forth evidence apportioning fault/damages among the various co- defendants, appellants could not recover further damages from the remaining non-settling appellees. On appeal, Waverly and OSFC seek reversal of the trial court’s decision and journal entry.

{¶ 2} For the reasons discussed below, we disagree with the trial court that the appellants’ settlements with the settling co-defendants extinguish their remaining breach of contract claims against the non-settling appellees. Furthermore, we disagree with the trial court’s determination that because appellants’ experts could not apportion fault/damages among the various co-defendants their claims for breach of contract could no longer survive. Therefore, we conclude that the trial court did not properly grant summary judgment in favor of the appellees on appellants’ breach of contract claims. Accordingly, the judgment of the trial court is reversed; and this matter is remanded to the trial court for further proceedings consistent with this opinion.

I. Facts and Procedural Posture

1 Following commencement of this lawsuit, H.B. 49, Section 515.10, effectively changed the name of plaintiff- appellant Ohio School Facilities Commission to the Ohio Facilities Construction Commission. Nevertheless, to maintain consistency with the language employed by the trial court, we use the commission’s former name throughout this opinion.

Pike App. No. 17CA885 3

A. The Project

{¶ 3} The Waverly school construction project (hereinafter the “Project”), spanning a time period between 2002-2004, involved the building of a campus of four separate schools2 at an original cost of nearly $50 Million. Waverly and OSFC jointly funded the Project. Rather than having a general contractor performing all construction, the Project called for multiple prime contractors, each with specific scopes of work. There were separate contracts with four prime contractors: Crace, masonry/concrete walks; Staggs, roofing; J&H, general trades/floor slab; and George J. Igel and Company, Inc. (“Igel”), site preparation. There were separate contracts with an architect, Triad, for design and oversight/quality control, and a construction manager, BBL, for oversight/quality control. There was also a contract with geo-technical firm, Terracon (fka H.C. Nutting Company), to provide evaluation of the construction site and soil testing during construction.

B. Construction Defects and Remediation

{¶ 4} Waverly took occupancy of the Project at the beginning of the 2004-2005 school year, and immediately experienced major water intrusion problems at all four buildings. In addition, another problem developed with the concrete floor slab in ES-2 heaving in the gymnasium and adjacent classrooms. After several years of failed attempts to fix the problems, the appellants hired CTL Engineering (“CTL”) and Schooley Caldwell & Associates (“SCA”) to investigate the causes of the water intrusion problems, as well as the heaving floor slab in ES-2. CTL and SCA issued reports, and were able to classify the Project’s construction defects into three separate categories, namely: (1) roofing; (2) masonry; and (3) general trades/floor slab. CTL also identified design defects attributable to Triad. The appellants hired Robertson

2 The schools were: (1) Elementary School 1 (“ES-1”); (2) Elementary School 2 (“ES-2”); (3) Junior High School; and (4) High School.

Pike App. No. 17CA885 4

Construction Services (“RCS”) to remediate the defective work. Remediation was performed from 2013-2015 at a total cost of $6,592,887.84.3 This amount included the total of sums billed by RCS for the design and repairs of the roof, masonry, concrete, soils, and all other work at all four buildings of the Waverly campus. This sum also included an admitted betterment of $863,306.

C. The Original Complaint

{¶ 5} The appellants filed their original complaint in August 2013 and asserted claims against Crace, Staggs, J&H, Igel, and OFIC as surety for the contractors, for their defective work; against Triad, for its design and oversight failures; and against BBL for its oversight failures. The claims included breach of contract and breach of warranties claims against the prime contractors; indemnification under the surety bonds against OFIC; and negligence and breach of contract claims against BBL and Triad.

D. The Amended Complaints

{¶ 6} After initial discovery Igel was voluntarily dismissed from the lawsuit. Thereafter, the appellants filed an amended complaint on December 11, 2014, adding Terracon as a defendant and asserting claims of negligence and breach of contract for the floor slab heaving issue and its failure to properly test the soil and advise with respect to the heaving floor slabs in ES-2.

{¶ 7} Roofing installer Staggs filed a third-party complaint against roofing materials supplier and inspector, Tremco. Tremco counterclaimed against Staggs, asserting a right to indemnify for any liability based upon faulty installation. Thereafter, the appellants filed a second amended complaint on March 26, 2015, adding Tremco as a defendant, and asserting

3 The cost of remediation was paid by Waverly and the OSFC, with Waverly’s share of the costs being $1,354,629 and the OSFC paying the remaining balance.

Pike App. No. 17CA885 5

Free access — add to your briefcase to read the full text and ask questions with AI

Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc., 2018 Ohio 4748 (Ohio Ct. App. 2018).

2018 Ohio 4748 (Waverly City School Dist. Bd. of Edn. v. Triad AR, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Yousef v. Yousef
2019 Ohio 3656 (Ohio Court of Appeals, 2019)