Watts-Healy Tibbitts A JV v. United States

84 Fed. Cl. 253, 2008 WL 4636173
United States Court of Federal Claims·Decided October 14, 2008·No. No. 08-261C·Published·Cited by 3 cases

Opinion

OPINION AND ORDER

SMITH, Senior Judge.

Previously, this Court entered a preliminary injunction against the Navy with respect to the contract at issue in this ease. In issuing the preliminary injunction, the Court found that it had no choice but to find the Contracting Officer’s decision arbitrary and capricious. This determination was based on the fact, which was crystal clear to the Court, that no adequate responsibility determination had been made by the Contracting Officer. It appeared that only the most cursory consideration had been made of very serious charges. For example, the Contracting Officer testified that because bid rigging is common in Japan it does not rise to a level serious enough to render the corporation not responsible. Further, even though the Contracting Officer testified that he did re-evaluate the responsibility determination, the [254] Contracting Officer alluded to the fact that because the award had already been made he could not disrupt that award. And finally, the Contracting Officer failed to obtain definitive guidance on the Navy’s required level of business integrity for international transactions in cases like this. The Court offered the Navy two choices with regard to the solicitation: 1) either designate a new contracting officer to make a new responsibility determination, or 2) re-solicit the contract. Instead, the Defendant filed a Motion to Stay the Injunction pending Possible Appeal. After denying the Motion to Stay the Injunction, the Court modified the preliminary injunction.

In the modified preliminary injunction, the Court ordered the Navy to make a new responsibility determination by a new contracting officer. The Court ordered that the new contracting officer obtain written advice from NAVFAC, by someone at the flag officer or presidential appointee level, as to the pertinent policy considerations and standards of business integrity in order to find the awardee responsible in international contracts. Further, the Court ordered that this reconsideration involve a reasoned analysis of the conduct of the awardee and the statutory and regulatory factors relevant to the purposes of a responsibility determination. It must also articulate the reasons for finding the awardee either a responsible contractor or not, consistent with the applicable law and Navy policy.

The new responsibility determination was due to be filed within thirty days from the date of the Court’s order. The Navy complied and a new responsibility determination in the form of an affidavit of Robert M. Griffin, Jr. was filed by the Defendant. Plaintiff responded to Mr. Griffin’s declaration and the Government filed its reply. Argument was held, and at oral argument the Court lifted the injunction for the reasons set forth on the record. This opinion elaborates that decision.

Procedural History

On October 5, 2007, the Naval Facilities Engineering Command, Pacific, issued a solicitation requesting proposals to construct the Kilo Wharf extension in Guam. On November 19, 2007, the bidders provided technical proposals to the Navy. Watts-Healy Tib-bitts and IBC/TOA Corporation were two of the bidders. On March 26, 2008, Plaintiff was informed that an award had been made to IBC/TOA. Thereafter, on April 10, 2008, Watts-Healy Tibbitts filed its first post-award bid protest requesting a temporary restraining order, a preliminary and a permanent injunction and declaratory judgment arguing that the “American Preference Policy” should have been applied to the IBC/ TOA proposal. This was denied in a sealed opinion by this Court filed on April 25, 2008 and unsealed on May 2, 2008.

On May 5, 2008, Plaintiff filed a Motion for Reconsideration of this Court’s April 25, 2008 opinion together with a second Motion for Preliminary Injunctive Relief based on additional grounds and an Amended Complaint. After full briefing, on June 9, 2008 the Court heard oral argument on Plaintiffs Motion. The matter was taken under advisement and, on June 17, 2008, the Court held a status conference whereupon the Court denied-in-part Plaintiffs Motion to Reconsider the Defendant’s decision not to apply the twenty percent preference but held in abeyance Plaintiffs other contentions. The Court ordered the contracting officer to appear to testify regarding the new facts related to the responsibility issue. On June 26, 2008, Defendant filed a Motion to Reconsider this Order which was subsequently denied. On July 15, 2008, the contracting officer testified before this Court.

On July 18, 2008, the Court entered its sealed Opinion and Order granting Plaintiffs Motion for Reconsideration and granting Plaintiffs Motion for Preliminary Injunction. On July 21, 2008, the Court unsealed the Order of Injunction and on July 23, 2008 unsealed the July 18, 2008 Opinion and Order. A Motion to Stay the Injunction pending Possible Appeal was filed by the Defendant on July 25, 2008, and after full briefing the Court held argument on August 5, 2008. The Motion to Stay was denied and a Modified Order Granting Preliminary Injunction was filed on that date. On August 28, 2008, the Defendant filed its new responsibility determination and the Plaintiff responded. [255] On September 9, 2008, the Court held oral argument on the new responsibility determination. At the conclusion of the argument, the Court lifted the preliminary injunction for the reasons set forth on the record and set forth in more detail below.

Facts 1

The Naval Facilities Engineering Command, Pacific, issued a solicitation requesting proposals to construct the Kilo Wharf extension in Guam. The Solicitation provided for a Pre-Award Survey/Responsibility Determination, citing FAR 9.104. Among other things, this Solicitation provision provided that the prospective contractor must demonstrate a “... satisfactory performance record, and be otherwise eligible to receive an award under applicable laws and regulations.” See Solicitation, Document 00100, Paragraph 1.24.

To facilitate a contracting officer’s determination of responsibility and business integrity, all federal contractors are required to furnish representations and certifications. One of those certifications, pursuant to FAR 52.209-5, entitled “Certification Regarding Debarment, Suspension, Proposed Debarment, and Other Responsibility Matters (Dec 2001)” requires a certification that the corporation has not, within a three-year period preceding this offer, been convicted of or had a civil judgment rendered against them for any commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, state, or local) contract or subcontract; violation of Federal or state antitrust statutes relating to the submission of offers; or commission of embezzlement, theft, forgery, bribery. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Watts-Healy Tibbitts A JV v. United States, 84 Fed. Cl. 253, 2008 WL 4636173 (uscfc 2008).

84 Fed. Cl. 253 (Watts-Healy Tibbitts A JV v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Algese 2 S.C.A.R.L. v. United States
127 Fed. Cl. 497 (Federal Claims, 2016)
Akal Security, Inc. v. United States
103 Fed. Cl. 310 (Federal Claims, 2011)
Acrow Corp. of America v. United States
97 Fed. Cl. 161 (Federal Claims, 2011)