Watts Constructors, LLC v. CDM Constructors, Inc.

CourtDistrict Court, D. Guam
DecidedNovember 20, 2014
Docket1:14-cv-00012
StatusUnknown

This text of Watts Constructors, LLC v. CDM Constructors, Inc. (Watts Constructors, LLC v. CDM Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watts Constructors, LLC v. CDM Constructors, Inc., (gud 2014).

Opinion

1 2 3 4 DISTRICT COURT OF GUAM 5 TERRITORY OF GUAM 6 7 WATTS CONSTRUCTORS LLC, CIVIL CASE NO. 14-00012 8 Plaintiff, 9 vs. ORDER 10 CDM CONSTRUCTORS, INC., 11 Defendant. 12 13 This matter is before the court on a Motion to Dismiss for Improper Venue, or in the 14 alternative, to Transfer Venue, filed by Defendant CDM Constructors, Inc. (“CDM”). See ECF 15 No. 8. Therein, CDM moves to dismiss this action for improper venue. In the alternative, CDM 16 requests the court transfer this action to the United States District Court for the Northern District 17 of California. The court has reviewed all pertinent pleadings filed herein and has had the 18 opportunity to hear argument from counsel on November 14, 2014. Based on the analysis set forth 19 infra, the court hereby denies the motion in its entirety. 20 FACTUAL BACKGROUND 21 This action arises from a contract between the parties relating to the construction of AAFES 22 Andersen Shopping Center on Andersen AFB, Guam (the “Project”). According to Complaint, 23 Defendant CDM entered into a joint venture with CAPE to submit a proposal to the Air Force 24 Center for Engineering and the Environment (“AFCEE”). Compl. at ¶9, ECF No. 1.1 25 26 1 This is confirmed by the Declaration of John Czapor, which is appended as Exhibit A 27 to CDM’s Memorandum in Support of Motion to Dismiss for Improper Venue. See Czapor Decl. at ¶1, ECF No. 9. According to said declaration, CDM, a construction and engineering 28 (continued...) 1 According to the Declaration of Mr. Czapor, around April 12, 2006, the CDM/CAPE joint 2 venture was awarded contract number FA8903-06-D-8509. See Czapor Decl. at ¶1, ECF No. 9. 3 “This contract did not set a specific price for a specific project, instead it created a contract vehicle 4 for individual ‘task orders’ . . . to be awarded for HERC projects.” Id. at ¶2. 5 On October 3, 2006, AFCEE issued a request for proposal (“RFP”) for construction of the 6 Project. Compl. at ¶7, ECF No. 2. The RFP included alleged 95% complete construction 7 documents2 and specified that the 100% complete construction documents would be sent out as an 8 amendment on or about October 30, 2006. Id. at ¶¶7-8. 9 CDM, as lead for the joint venture, then requested the plaintiff Watts Constructors LLC 10 (“Watts”) prepare a bid for the Project. Id. at ¶10. 11 AFCEE did not issue the 100% complete construction documents until November 20, 2006, 12 which only provided the bidders 15 calendar days to review these documents before the bids were 13 due. Id. at ¶¶11-12. Nevertheless, Watts timely submitted its bid to CDM on December 5, 2006. 14 Id. at ¶14. 15 On December 5, 2006, Watts and CDM entered into a Master Services Agreement.3 Id. at 16 ¶15. According to the Complaint, under the Master Services Agreement, Watts agreed to furnish 17 services, labor, materials, and equipment for projects based on task orders issued by CDM, and 18 CDM agreed to pay Watts for such services, labor, materials, and equipment. Id. According to 19 the Declaration of Mr. Czapor, the Master Services Agreement 20 set up a framework for CDM and Watts to potentially enter into agreements for individual projects that would correspond with the “task orders” awarded under the 21 CDM/CAPE prime contract. These agreements between CDM and Watts pursuant 22 23 1(...continued) company, entered into a joint venture with CAPE, Inc., another construction and engineering 24 company, on or about October 10, 2005, “for the purpose of preparing a proposal to the U.S. Air Force to execute work under their Heavy Engineering Repair and Construction (“HERC”) 25 Indefinite Delivery Indefinite Quantity contract.” Id. 26 2 The Complaint asserts that AFCEE later “admitted that those documents were really 27 only 70% or less complete.” Id. at ¶25. 28 3 A copy of the Master Services Agreement is attached as Exhibit 1 to the Complaint. 1 to the Master Services Agreement would also be called Task Orders. 2 Czapor Decl. at ¶3, ECF No. 9. 3 On January 26, 2007, AFCEE awarded the construction contract to CDM/CAPE for over 4 $35 million.4 Compl. at ¶16. In late February 2007, AFCEE issued a notice to proceed with the 5 work, and Watts started working on the Project in February 2007. Id. at ¶¶17-18. 6 It was not until around May 7, 2007 that Watts entered into an agreement to serve as CDM’s 7 subcontractor for the Project for a fixed price of $30,703,900.5 CDM’s Mem. in Supp. at 5-6, ECF 8 No. 9. See also Compl. at ¶19, ECF No. 2. A copy of Task Order 001 is attached as Exhibit 2 to 9 the Complaint. 10 The parties eventually agreed to various change orders during the Project, and the last 11 change order (Change Order No. 4) modified the contract sum to $29,817,754.12. Compl. at ¶20, 12 ECF No. 2. 13 Construction was scheduled to be completed by August 14, 2008, but Watts contends that 14 the Task Order provided for a completion date of August 25, 2008. Id. at ¶21. The Project was 15 substantially complete and occupied on or about September 2008.6 Id. 16 The Complaint asserts that [t]hrough no fault of its own, Watts was delayed, disrupted, 17 impacted, and accelerated during the performance of its work” under the Master Services 18 Agreement. Compl. at ¶22, ECF No. 2. Watts claims that CDM provided it with “defective, 19 incomplete, conflicting, uncoordinated construction documents, and the defects, errors, and 20 omissions came to light as the Project progressed.” Id. at ¶26. Because of these alleged defects, 21 errors, and omissions and CDM’s purported failure to perform its contractual duties, Watts 22 contends that its work and the work of its sub-subcontractors was “delayed, disrupted, impacted, 23 24 4 The government’s award of the contract to CDM/CAPE for construction of the Project was Task Order 0003. Czapor Decl. at ¶6, ECF No. 9. 25 5 This agreement was identified as “Task Order 001" to the Master Services 26 Agreement. Czapor Decl. at ¶6, ECF No. 9. 27 6 According to Mr. Czapor, the Project was completed on or around September 8, 2008. 28 Czapor Decl. at ¶13, ECF No. 9. 1 and accelerated throughout the Project.” Id. at ¶27. The Complaint also claims that “Watts also 2 performed increased, extra, and/or changed work that was not included in its [Master Services] 3 Agreement and bid. Id. at ¶28. Furthermore, the Complaint alleges that “CDM’s acts, its failure 4 to act, errors, and/or omissions caused Watts to incur significant costs for investigation of design 5 errors and omissions, coordination of the design, and increased project management services, 6 among other costs.” Id. at ¶30. Although Watts states that it submitted numerous requests for 7 equitable adjustment to CDM seeking compensation for its increased costs, CDM has not paid these 8 adjustments, which are the subject of this action. Id. at ¶31. 9 According to CDM, 10 Towards the end and after construction, CDM and Watts held several meetings between management in Northern California addressing various unresolved 11 contractual matters. No such meeting occurred in Guam. Generally speaking, the parties discussed several topics that relate to the allegations that Watts raised in its 12 Complaint. 13 [A]t least two of these meeting between management occurred at Watts’ office in Novato, California. . . . [A]t least one of these meetings between management 14 occurred at CDM’s office in Walnut Creek, California. 15 Czapor Decl. at ¶¶15-16, ECF No. 9. 16 PROCEDURAL BACKGROUND 17 On August 13, 2014, Watts filed the instant action. The Complaint alleged five causes of 18 action: Breach of Express Contract, Breach of Duty of Good Faith and Fair Dealing, Action on 19 Account, Negligent Misrepresentation, and Prompt Pay Violation. See ECF No. 2. 20 In lieu of filing an answer, on October 9, 2014, CDM filed the instant Motion to Dismiss 21 for Improper Venue, or in the alternative, to Transfer Venue, along with a Memorandum in 22 Support. See ECF Nos. 8-9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piper Aircraft Co. v. Reyno
454 U.S. 235 (Supreme Court, 1982)
Employers Mutual Casualty Co. v. Bartile Roofs, Inc.
618 F.3d 1153 (Tenth Circuit, 2010)
Doe 1 v. AOL LLC
552 F.3d 1077 (Ninth Circuit, 2009)
Jones v. GNC Franchising, Inc.
211 F.3d 495 (Ninth Circuit, 2000)
Omnicell, Inc. v. Medacist Solutions Group, LLC
272 F.R.D. 469 (N.D. California, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Watts Constructors, LLC v. CDM Constructors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/watts-constructors-llc-v-cdm-constructors-inc-gud-2014.