Watts Constructors, LLC

CourtArmed Services Board of Contract Appeals
DecidedJanuary 26, 2015
DocketASBCA No. 59602
StatusPublished

This text of Watts Constructors, LLC (Watts Constructors, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watts Constructors, LLC, (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Watts Constructors, LLC ) ASBCA No. 59602 ) Under Contract No. N62473-10-D-5418 )

APPEARANCES FOR THE APPELLANT: Peter N. Ralston, Esq. Alix K. Schroeder, Esq. Oles Morrison Rinker & Baker, LLP Seattle, WA

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Tracey R. Rockenbach, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE THRASHER PURSUANT TO BOARD RULE 12.2

This appeal involves a contract awarded to Watts Constructors, LLC (Watts) by the Naval Facilities Engineering Command Southwest (government) to perform a utility upgrade for Camp Pendleton Marine Corps Base, California. Watts seeks an equitable adjustment for additional direct costs of $41, 148 it incurred while removing a differing site condition, as well as, interest it contends was the result of the government's delay in issuing a modification allowing Watts to proceed with the work. The facts are largely undisputed but the parties differ as to how Watts incurred costs should be allocated; whether the costs are direct costs or indirect overhead costs under Federal Acquisition Regulation (FAR) Part 31 cost principles (cost principles). Watts elected to proceed under the Board's Expedited Procedure (Rule 12.2) 1 and the parties elected to decide the appeal on the record pursuant to Board Rule 11. 2 Only

1 The Contract Disputes Act, implemented by Board Rule 12.2, provides that this decision shall have no value as precedent, and in the absence of fraud, shall be final and conclusive and may not be appealed or set aside. 2 The record consist of: the government's Rule 4 file (tabs 1-30); appellant's Supplemental Rule 4 file (tabs 1-8); the Declaration of Mr. Jeffrey M. Pruett (attachment to appellant's post-hearing brief); the government's Exhibit A, an email exchange between 22 August 2012 and 25 September 2012, Exhibit B, an unsigned modification and Exhibit C, the Declaration of Joseph U. Hill (attachments to the government's post-hearing brief); and Second Declaration of Mr. Jeffrey M. Pruett (attachment to appellant's reply brief). entitlement is at issue. The Board has jurisdiction over the dispute pursuant to the Contract Disputes Act (CDA) of 1978, 41 U.S.C. §§ 7101-7109. We deny the appeal.

FINDINGS OF FACT

1. On 16 August 2012, the government awarded Watts a firm-fixed price task order 0003 (contract) under Contract No. N62473-10-D-5418 (basic contract). This appeal primarily involves one requirement under the contract, to Relocate Sewer Lift Station 310406 (Sewer Lift Relocation). (R4, tab 3 at 1, 18)3

2. Pertinent to this appeal, the contract incorporated all clauses in the basic contract (R4, tab 3 at 101) which in tum incorporated the FAR cost principles through inclusion of DFARS 252.243-7001, PRICING OF CONTRACT MODIFICATIONS (DEC 1991) (R4, tab 30 at gov't supp. ex. 032). 4 Shortly after award the government informed Watts that it must consistently use a single distribution base for computing field office overhead, 5 using either a per diem rate or percentage mark-up to compute field office overhead on all changes (R4, tab 9). In response, Watts elected to recover overhead rates on a percentage basis, rather than a per diem basis for this contract (R4, tab 28 at 1031 ). The final cost objective for these costs was the contract as a whole (R4, tab 26 at 1021 ).

3. Watts encountered a differing site condition that interfered with the installation of the Sewer Lift Relocation (app. supp. R4, tab 7). Watts promptly notified the government and, on 10 July 2013, the government acknowledged a differing site condition existed and notified Watts any work it completed before a processed modification was issued would be at its own risk (app. supp. R4, tab 5 at 2). The work stoppage directly interfered with the installation of a manhole, excavation and completion of the Sewer Lift Relocation work (R4, tab 20 at 978).

4. On 22 July 2013 Watts submitted its initial cost proposal and a revised proposal on 31 July 2013 for the differing site condition. Both cost proposals contained a percentage markup for field office overhead, as was the case on a previous

3 All Rule 4 page numbers are to the Bates-stamped numbers. 4 DF ARS 252.243-7001, PRICING OF CONTRACT MODIFICATIONS (DEC 1991) states, "When costs are a factor in any price adjustment under this contract, the contract cost principles and procedures in FAR Part 31 and DF ARS Part 231, in effect on the date of this contract, apply." 5 The term "field office overhead" is often used interchangeably with the term "job site overhead." For consistency, we refer to the claimed costs at issue as field office overhead. 2 modification. 6 (R4, tabs 16-18) Mr. Jeffrey M. Pruett testified by affidavit that the percentage method was used under the assumption that the final modification, Modification No. 4 (Mod 4) would be completed before the original contract completion date and, therefore, the costs would be shared with other contract work (Declaration of Mr. Jeffrey M. Pruett (Pruett decl.) ~ 6). The parties conducted negotiations on 13 August 2013 culminating in an agreement on the costs to be reflected in Mod 4 (R4, tab 19 at 975). While waiting for the Mod 4 to be issued, Watts completed as much of the work as it could on the Sewer Lift Relocation and other contract items; once Watts had completed all possible work on the Sewer Lift Relocation, Watts moved its equipment and personnel to work on other contract items (Pruett decl. ~ 11 ).

5. Watts completed all other contract work before Mod 4 was issued and on 18 September 2013 requested that Mod 4 include language providing for payment of "associated costs" related to time delay in executing the modification (R4, tab 22 987-89). That same day, the government responded stating, "Because you charge [field office overhead] as a percentage rate, we don't agree that you are entitled to additional costs for the delay associated with this mod. However, you are more than welcome to submit a proposal for delay costs." (R4, tab 22 at 987)

6. On 20 September 2013, Watts submitted a revised proposal for Mod 4 that eliminated any percentage charge for field office overhead costs but requested a total cost of$57,782 that included $42,004 for the direct site costs (R4, tab 21at984).

7. On 23 September 2013, in an attempt to avoid further delay, the government responded to Watts suggesting that the parties execute Mod 4 as negotiated, i.e., including the percentage field office overhead, proposing to resolve the "time and associated costs related to this change" at a later date by the inclusion of language in the mod preserving Watts' claim (R4, tab 22 at 986). Watts executed bilateral Mod 4 on 23 September 2013 reimbursing Watts in the amount of $20,991.00. Mod 4 did not provide any time extension but stated, "If there is time and associated costs related to this change, it will be negotiated later upon Government review of the Contractor's Time Impact analysis dated September 19, 2013." (R4, tab 23) Mod 4 also included 10% mark-up for field overhead costs on the change (R4, tab 22 at 986, tab 25 at 1018).

8. On 15 October 2013, Watts submitted its proposal for additional delay requesting $41,148 and 39 working days (56 calendar days) (R4, tab 24 at 998). The costs claimed for field office overhead were for a quality control manager, a supervisor, an office trailer, and site fencing among other costs that Watts was

6 Modification No. 3 deleted work and included an amount for field office overhead that employed a percentage mark-up (R4, tab 28 at 1031 ). 3 required to provide on site (Second Declaration of Mr. Jeffrey M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 7101-7109
41 U.S.C. § 7101-7109
§ 7101
41 U.S.C. § 7101

Cite This Page — Counsel Stack

Bluebook (online)
Watts Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watts-constructors-llc-asbca-2015.