Watson v. Gray's Harbor Brick Co.

28 P. 527, 3 Wash. 283, 1891 Wash. LEXIS 156
CourtWashington Supreme Court
DecidedDecember 8, 1891
DocketNo. 194
StatusPublished
Cited by12 cases

This text of 28 P. 527 (Watson v. Gray's Harbor Brick Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watson v. Gray's Harbor Brick Co., 28 P. 527, 3 Wash. 283, 1891 Wash. LEXIS 156 (Wash. 1891).

Opinion

The opinion of the court was delivered by

Dunbab, J.

This action was brought on an alleged violation of a written contract made by the plaintiff and one Hamshaw, whom plaintiff claims to be a general agent of defendant, and as such manager had the authority to bind the defendant by his contract. The contract was signed, “ The Gray’s Harbor Brick Company, by F. T. Hamshaw, manager.”

The respondent moves the court to dismiss the said appeal, and affirm the judgment rendered in the court below, for the reason that there is no assignment of errors. The appellant, however, specified the errors in its motion for a new trial, and cites them in its brief, though not in a very formal way. This appeal was taken before the law of 1891 went into, effect, and under the provisions of the law then in force, we think, is sufficient, and the motion to dismiss will be denied.

Under the contract, the plaintiff agreed to sink a well for defendant, for which service defendant agreed to pay a stipulated price per foot. Plaintiff alleges that in view of [285]*285the fulfilling of his contract, he shipped his plant from "Walla Walla to Hoquiam at great expense, to wit, $225, and was ready and willing to perform his part of the contract; but was prevented by defendant from entering upon the work under the contract; and by reason of refusal of the defendant to carry out the work heis damagedin the said sum of $225, expense of moving his machinery; in the sum of $300, in the loss of profits that would accrue to him from the performance of the contract, and $75 loss of time in making preparation to do said work. The defendant denied that it entered into the contract with plaintiff at all, and contended on the trail that Hamshaw was not its agent, and had no authority to contract for it. During the progress of the trial there was some testimony showing that plaintiff was engaged in digging wells for other parties during the time that "he would have been engaged in working for defendant under the contract, if the terms of the contract had been carried out. After the admission of this testimony the court made the following statement:

“Upon an examination of the contract during the adjournment,we have cometo the conclusion that this contract is not revokable at the will of the defendant; that under its provisions there is an express agreement that he shall sink at least one well to a depth not to exceed 500 feet. The allegations of the complaint being that the contract was abrogated by the defendant before he had commenced any operations on the sinking of the well, it would constitute a breach of the contract, if proven. The measure of damages, in that instance, is the amount of expense necessarily incurred by the plaintiff in preparing for the work, and a reasonable allowance for his time in so doing, not exceeding the amount claimed in his complaint.”

Whereupon the plaintiff moved to strike out all that part of the testimony of Mr. Watson which did not relate to the expense incurred by him in bringing his machinery and expert workmen from Walla Walla to Gray’s Harbor, [286]*286and other expense incurred by him at Gray’s Harbor, including his own time and personal expenses in preparing to perform the contract. This was an exclusion of the testimony tending to show that the plaintiff received continuously a lucrative employment, out of which he realized profit, on his arrival at the place where this contract was to be performed; which motion was sustained by the court and objected to by the defendant. Afterward the court instructed the jury as follows:

Instruction 8: “If you believe, then, that the company was bound by the contract in the manner as stated in the foregoing instructions, and that the plaintiff made preparation to do the work, and was then prohibited from doing it by the company, they would be liable to him for his expenses and reasonable compensation for Ins time lost, not exceeding the amount claimed in his complaint.”

To which instruction the defendant excepted.

While the measure of damages seems largely to have been the bone of contention at the trial, no authorities are cited by either appellant or respondent on that question. We think there was no error committed by the court in excluding the testimony referred to above. We do not question the general rule that plaintiff cannot recover for avoidable consequences. This is a natural sequence of the principle which confines the damages to direct and immediate consequences, and can be pleaded when the nature of the case will permit; for it is not the policy of the law to permit a man to aggravate his damages by his own neglectful acts. As, for instance, it has been held that where a man’s fence has been knocked down and his crops exposed to the ravages of cattle, that it was his duty to repair the fence as soon as it came to his notice, and that he could not recover damages that were incurred after that time. This rule is made especially applicable to actions by employes to recover for personal services where they have been dismissed by their employers without sufficient cause, [287]*287and prevented from completing the services according to the contract. They must seek other employment, and the amount which they earn in this way, or which they might have earned had they made reasonable exertions, will be allowed in reduction of the damages given by their discharge. Sedgwick on Damages, § 206- There is a well defined distinction drawn by all the authorities between contracts for hire, or for personal services, and the contract to do a specific act. In the former case, if the plaintiff gets employment at the same wages, it is plain that he is not damaged, and when he does not his damages are easily ascertained. In the latter species of contract, where the employer refuses to accept of the services, or to have the work contracted for performed, or prevents the employé from performing the same in any manner, the usual measure of damages, where the contract relates to the manufacture of an article, or the construction of a building, or the performance of some other specified act, is the difference between the price agreed to be paid and what it would have cost the employe to complete it, provided such cost would be less than the contract price. Field on Law of Damages, § 339. The duty to seek employment is dependent upon the original contract being one of employment or hire. It is not applicable to every contract. Sedwick on Damages, § 208. It was held by the supreme court of Pennsylvania, in Wolf v. Studebaker, 65 Pa. St. 459, a leading case decided in 1870, that ordinary contracts of hire, and contracts for the performance of some specified undertaking, cannot be governed by the same rule. That in one case the party can earn no more than the wages, and if he gets that his loss will be but nominal, whereas, in the other case, the loss of the property is the loss of the benefit of the contract. The damage may be said to be fixed by the law of the contract the moment it is broken, and cannot be altered by collateral circumstances independent of and totally discon[288]*288nected from it, and from the party occasioning it. To plead the doctrine of avoidable consequences to such case, said the court, “ would necessarily involve proof of everything, great and small, no matter how various the items done by the plaintiff during the period of the contract might be, and how much he made in the meantime.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Longenecker v. Brommer
368 P.2d 900 (Washington Supreme Court, 1962)
Dill v. Zielke
173 P.2d 977 (Washington Supreme Court, 1946)
Suryan v. Lake Washington Shipyards
300 P. 941 (Washington Supreme Court, 1931)
Beeson Brothers v. Chambers
285 P. 433 (Washington Supreme Court, 1930)
Robbins v. Seattle Peerless Motor Co.
268 P. 594 (Washington Supreme Court, 1928)
Yarno v. Hedlund Box & Lumber Co.
225 P. 659 (Washington Supreme Court, 1924)
Spencer v. Gross, Kelly & Co.
163 P. 1087 (New Mexico Supreme Court, 1917)
Owensboro Shovel & Tool Co. v. Moore
157 S.W. 1121 (Court of Appeals of Kentucky, 1913)
Bogart v. Pitchless Lumber Co.
130 P. 490 (Washington Supreme Court, 1913)
Harness v. Kentucky Fluor Spar Co.
147 S.W. 934 (Court of Appeals of Kentucky, 1912)
Hickok v. W. E. Adams Co.
99 N.W. 77 (South Dakota Supreme Court, 1904)
Sullivan v. McMillan
37 Fla. 134 (Supreme Court of Florida, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
28 P. 527, 3 Wash. 283, 1891 Wash. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watson-v-grays-harbor-brick-co-wash-1891.