Watson Cogeneration Co. v. Southern Cal. Edison Co. CA2/1

CourtCalifornia Court of Appeal
DecidedSeptember 30, 2014
DocketB251746A
StatusUnpublished

This text of Watson Cogeneration Co. v. Southern Cal. Edison Co. CA2/1 (Watson Cogeneration Co. v. Southern Cal. Edison Co. CA2/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watson Cogeneration Co. v. Southern Cal. Edison Co. CA2/1, (Cal. Ct. App. 2014).

Opinion

Filed 9/30/14 Watson Cogeneration Co. v. Southern Cal. Edison Co. CA2/1 Opinion follwing rehearing NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION ONE

WATSON COGENERATION B251746 COMPANY, (Los Angeles County Plaintiff and Appellant, Super. Ct. No. BC473092)

v.

SOUTHERN CALIFORNIA EDISON COMPANY,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Los Angeles County. Gregory W. Alarcon, Judge. Affirmed. Rovens Lamb and Steven A. Lamb for Plaintiff and Appellant Carlsmith Ball, James Polish; Southern California Edison Company, Leon Bass, Jr., and Michael J. Barrett for Defendant and Respondent.

__________________________________ This is an action for breach of contract and unjust enrichment by an energy producer, Watson Cogeneration Company (Watson), against an energy buyer, Southern California Edison Company (SCE). The parties do not dispute that SCE agreed to purchase energy from Watson at a specified price for a 20-year period. They disagree whether that 20-year period terminated on December 31, 2007, as SCE contends, or on April 5, 2008, as Watson contends. The trial court agreed with SCE’s interpretation of the agreement and entered judgment in its favor on both causes of action. We affirm. FACTS AND PROCEEDINGS BELOW The following facts are undisputed. Watson owns a cogeneration facility that produces energy for refining petroleum and running electricity-generating turbines. In 1984, Watson entered into a contract to sell the excess energy it produced to SCE at the agreed-on price for a period of 20 years. (The parties refer to this agreement as the Power Purchase Contract or PPC.) The PPC provided in section 1.8 that it “shall continue in effect for a period of 20 years beginning on the Firm Operation Date.” The “Firm Operation Date” was defined in section 2.15 of the contract as: “The date agreed on by the Parties on which each generating unit(s) of the Generating Facility is determined to be a reliable source of generation and on which such unit can be reasonably expected to operate continuously at its effective rating (expressed in kW).” The PPC further provided in section 1.7 that the “Firm Operation Date for the Generating Facility will be on or before December 31, 1988.” In 1986, SCE sent Watson some proposed modifications of the PPC including a modification of the definition of “Firm Operation Date” in section 2.15. (We show the proposed language in italics and the existing language in bracketed strikeout-type.) “Firm Operation Date: The date agreed on by the Parties on which [each generating unit(s)] all the generating units of the Generating Facility [is] are determined to be [a] reliable [source] sources of generation and on which such [unit] units can be reasonably

2 expected to operate continuously at [its] their effective [rating] ratings (expressed in kW).” (Italics and strikeouts added.) The proposed language was never adopted. In 1988 the parties amended the PPC sections pertaining to its commencement date. They amended section 2.15 to state in relevant part: “The Firm Operation Date for the Generating Facility shall be the Firm Operation Date for the last individual Generator to achieve firm operation. The Firm Operation Date for individual Generators shall be the date agreed on by the Parties on which each Generator of the Generating Facility is determined to be a reliable source of generation and on which such Generator can be reasonably expected to operate continuously at its effective rating (expressed in kW).” The parties also amended section 1.8 to read: “This Contract . . . shall continue in effect for a period of twenty years (20) beginning on the earliest Firm Operation Date.” (Italics added.) We will refer to these changes in the PPC as the 1988 Amendments. Watson’s facility consists of six power generating units. The parties agree that the first generator achieved firm operation on January 1, 1988 and that the last generator achieved firm operation on April 6, 1988. The parties dispute whether the 20-year term of the contract began on the date the first generator attained firm operation or on the date that all the generators had obtained that status. Watson sued SCE for breach of contract, unjust enrichment and declaratory relief claiming that the PPC did not expire until April 5, 2008, 20 years after the last generator attained firm operation, and therefore SCE owed it over $10 million under the contract. SCE countered that the PPC expired on December 31, 2007, 20 years after the first generator achieved firm operation, i.e. the “earliest” Firm Operation Date.1 After considering extrinsic evidence as to the PPC’s commencement date, the trial court sustained SCE’s demurrer to the breach of contract cause of action without leave to amend, overruled SCE’s demurrer to the unjust enrichment cause of action and

1 After December 31, 2007, SCE continued to purchase energy from Watson but at a lower rate. 3 subsequently granted SCE’s motion for summary judgment on the claim of unjust enrichment.2 Watson filed a timely appeal.

DISCUSSION We review de novo the trial court’s ruling sustaining the demurrer. (Blank v. Kirwan (1985) 39 Cal.3d 311, 318.) Watson contends that the trial court erred in sustaining the demurrer to its breach of contract cause of action because the PPC is ambiguous as to the commencement date and the extrinsic evidence alleged in the complaint and submitted with Watson’s request for judicial notice shows that the PPC could reasonably be interpreted to mean that the commencement date was April 6, 1988, the date by which all of Watson’s generators had attained firm operation. We hold as a matter of law that the contract is not reasonably susceptible to Watson’s interpretation. The party “moving for a demurrer based on [contract] language must establish conclusively that this language unambiguously negates beyond reasonable controversy the construction alleged in the body of the complaint. [Citation.] To meet this burden, [the defendant] is required to demonstrate that the [contract] language supporting its position is so clear that parol evidence would be inadmissible to refute it. [Citation.] Absent this showing, the court must overrule the demurrer and permit the parties to litigate the issue in a context that permits the development and presentation of a factual record, e.g., summary judgment or trial.” (Palacin v. Allstate Ins. Co. (2004) 119 Cal.App.4th 855, 862.) When ruling on a demurrer the court must conditionally consider any parol evidence alleged in the complaint or subject to judicial notice to determine if it would be relevant to prove a meaning to which the contract is reasonably susceptible. (George v. Automobile Club of Southern California (2011) 201 Cal.App.4th 1112, 1122 [evidence alleged in complaint]; Ascherman v. General Reinsurance Corp. (1986) 183 Cal.App.3d 307, 310-311 [evidence judicially noticed].)

2 Watson does not challenge the court’s summary judgment order or its order sustaining SCE’s demurrer to the declaratory relief cause of action. 4 In ruling on the demurrer in this case, the court took judicial notice of the 1988 Amendments and documents filed by SCE with the Public Utilities Commission, along with the parol evidence that Watson alleged in its complaint. The 1988 amendments established a Firm Operation Date for the generating facility itself and separate Firm Operation Dates for the individual generators.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blank v. Kirwan
703 P.2d 58 (California Supreme Court, 1985)
Ascherman v. General Reinsurance Corp.
183 Cal. App. 3d 307 (California Court of Appeal, 1986)
Palacin v. All State Insurance
14 Cal. Rptr. 3d 731 (California Court of Appeal, 2004)
George v. Automobile Club of Southern California
201 Cal. App. 4th 1112 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Watson Cogeneration Co. v. Southern Cal. Edison Co. CA2/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watson-cogeneration-co-v-southern-cal-edison-co-ca21-calctapp-2014.