This text of Watkins Development LLC v. Jackson Redevelopment Authority (Watkins Development LLC v. Jackson Redevelopment Authority) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watkins Development LLC v. Jackson Redevelopment Authority, (Mich. 2019).

Opinion

IN THE SUPREME COURT OF MISSISSIPPI

NO. 2018-CA-00302-SCT

WATKINS DEVELOPMENT, LLC, AND FARISH STREET GROUP, LLC

v.

JACKSON REDEVELOPMENT AUTHORITY, CENTRAL MISSISSIPPI PLANNING AND DEVELOPMENT DISTRICT, INC.

DATE OF JUDGMENT: 05/30/2017 TRIAL JUDGE: HON. J. DEWAYNE THOMAS TRIAL COURT ATTORNEYS: MARK D. HERBERT PERNILA STIMLEY BROWN CHAD J. HAMMONS MICHAEL MADISON TAYLOR, JR. SAMUEL L. BEGLEY LANCE L. STEVENS W. DAVID WATKINS ROBERT L. GIBBS ROBERT GREGG MAYER JAMES W. SHELSON BENJAMIN LYLE ROBINSON COURT FROM WHICH APPEALED: HINDS COUNTY CHANCERY COURT ATTORNEYS FOR APPELLANTS: W. DAVID WATKINS ROBERT L. GIBBS ATTORNEYS FOR APPELLEES: MARK D. HERBERT GINNY Y. DELIMAN JAMES W. SHELSON PERNILA STIMLEY BROWN NATURE OF THE CASE: CIVIL - OTHER DISPOSITION: AFFIRMED - 10/03/2019 MOTION FOR REHEARING FILED: MANDATE ISSUED:

BEFORE RANDOLPH, C.J., ISHEE AND GRIFFIS, JJ. ISHEE, JUSTICE, FOR THE COURT:

¶1. The Jackson Redevelopment Authority (JRA) leased several parcels along Farish

Street in Jackson to the Farish Street Group (FSG). In exchange for a long-term lease and

other favorable terms, FSG was given a set period of time to renovate the properties and to

sublet them to retail establishments. Watkins Development, which owned half of FSG,

contracted with FSG to do the renovations. The plan was to build an entertainment district

on Farish Street, but after a few years only a fraction of the renovations were done, and none

of the properties were occupied by tenants. JRA terminated the lease, and this litigation

followed. The Hinds County Chancery Court ultimately found that the lease was properly

terminated, that no party had shown it was entitled to money damages, and that Watkins

Development could not take a mechanic’s lien on the property. We find no error and affirm.

FACTS

¶2. The Farish Street project began more than two decades ago. Between 1997 and 2001,

the Jackson Redevelopment Authority acquired properties along Farish Street. In March

2002, JRA entered into a lease with Performa Mississippi, LLC, to develop the area into the

“Farish Street Entertainment District.” But after six years, Performa had failed to move

forward with any significant development.

¶3. During the summer of 2008, David Watkins and his company Watkins Development

formed Farish Street Group, LLC, to take over the project. On June 17, 2009, Performa

assigned the lease to FSG. FSG and JRA then executed an amended lease agreement on

January 27, 2010. The same day, Watkins Development entered into an agreement with FSG

2 to perform nearly all of the construction and development required by the amended lease.

The construction was funded in part by a $5.4 million loan from the State.

¶4. The amended lease agreement laid out detailed and specific deadlines FSG was

required to meet to refurbish and sublet the properties. It was uncontested that none of the

deadlines were met, and after three years none of the properties had been sublet.

¶5. On July 13, 2013, JRA’s board voted to terminate the lease as to some of the parcels

for “failure to commence and/or complete construction or renovation of improvements.” On

July 26, 2013, JRA gave written notice of the termination as to those parcels. On September

25, 2013, JRA gave written notice of the termination of the rest of the parcels, effective

October 5, 2013. And on October 7, 2013, JRA sent another letter confirming that the lease

was “fully and finally terminated.” JRA’s letters cited FSG’s “failure to commence and/or

complete construction or renovation of improvements.”

¶6. On October 3, 2013, another contractor hired by FSG, Dale Partners Architects, filed

a mechanic’s lien on the properties in the amount of $322,180.26.1 Four days later, Watkins

Development filed a mechanic’s lien claiming that $4,757,484.33 was owed. JRA sued to

expunge the liens.

¶7. On July 24, 2014, JRA filed a motion for partial summary judgment asking the court

to declare both liens invalid. On July 23, 2015, the chancellor granted the partial summary-

judgment motion, holding that the liens were invalid as a matter of law. The chancellor

1 Dale Partners also filed a separate suit against FSG in circuit court.

3 declined to award punitive damages, however, finding that the liens had not been filed “with

a bad purpose, an evil purpose, without ground for believing the act to be lawful.”

¶8. After a trial, the chancellor found that the lease was properly terminated, but he denied

monetary damages to JRA because of the delay in terminating the lease and the valuable

improvements that had been made to the properties. The chancellor also denied any

monetary award to FSG because it had not proved “any specific monetary amount which has

been gained by JRA due to FSG’s actions.” Dale Partners Architects did not appeal the

expungement of its lien.

DISCUSSION

1. Materiality of Breach of Lease

¶9. Farish Street Group admits it breached its development obligations under the lease,

“early and often,” as the chancellor found. But the developers assert FSG substantially

complied with the lease, and consequently the chancellor was required to reinstate it. The

developers contend that the timetables were “arbitrary” and “political cover” and that they

were “assured time and time again that the timetable would be modified, as needed, to fit the

realities of the market conditions and the progress of the development.” The developers

maintain that market conditions were difficult and that there were unexpected construction

delays, but they say they worked hard to secure investment and to proceed with the

development to the extent it was possible. They give varying figures for the total investment,

but they assert it was more than $10 million.

4 ¶10. The developers argue that FSG’s failure to complete the construction on time was not

a material breach of the lease and that substantial compliance with the construction

requirements of the lease would have rendered FSG’s breaches immaterial and not a basis

to terminate the lease. “Rescission of a contract is allowed in cases of fraud, mistake, or

material breach.” Daniels v. Crocker, 235 So. 3d 1, 17 (Miss. 2017) (internal quotation

marks omitted) (quoting Jackson Motor Speedway, Inc. v. Ford, 914 So. 2d 779, 783 (Miss.

Ct. App. 2005)). The remedy for a breach of contract that is not material is money damages,

not rescission. Id. This Court has said,

The termination of a contract is an “extreme” remedy that should be “sparsely granted.” [citations omitted]. Termination is permitted only for a material breach. A breach is material when there “is a failure to perform a substantial part of the contract or one or more of its essential terms or conditions, or if there is such a breach as substantially defeats its purpose,” Gulf South Capital Corp. v. Brown, 183 So. 2d 802, 805 (Miss. 1966), or when “the breach of the contract is such that upon a reasonable construction of the contract, it is shown that the parties considered the breach as vital to the existence of the contract,” Matheney v. McClain, 248 Miss. 842, 849, 161 So. 2d 516, 520 (1964).

J.O. Hooker & Sons, Inc. v. Roberts Cabinet Co., 683 So. 2d 396, 402–03 (Miss. 1996)

(alteration in original) (quoting UHS-Qualicare v. Gulf Coast Cmty. Hosp., Inc., 525 So.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Simmons v. Bank of Mississippi
593 So. 2d 40 (Mississippi Supreme Court, 1992)
JO Hooker & Sons v. Roberts Cabinet
683 So. 2d 396 (Mississippi Supreme Court, 1996)
Matheney v. McClain
161 So. 2d 516 (Mississippi Supreme Court, 1964)
Key Constructors, Inc. v. H & M GAS CO.
537 So. 2d 1318 (Mississippi Supreme Court, 1989)
BEVIS CONSTR. CO., INC. v. Kittrell
139 So. 2d 375 (Mississippi Supreme Court, 1962)
Perry v. Sears, Roebuck & Co.
508 So. 2d 1086 (Mississippi Supreme Court, 1987)
Garner v. Hickman
733 So. 2d 191 (Mississippi Supreme Court, 1999)
Sanford v. Federated Guar. Ins. Co.
522 So. 2d 214 (Mississippi Supreme Court, 1988)
Paulk v. Housing Authority of City of Tupelo
195 So. 2d 488 (Mississippi Supreme Court, 1967)
Kirkland v. Chinita Land Development, Inc.
798 So. 2d 620 (Court of Appeals of Mississippi, 2001)
Redd and Hill v. L & a Contracting Co.
151 So. 2d 205 (Mississippi Supreme Court, 1963)
PMZ Oil Co. v. Lucroy
449 So. 2d 201 (Mississippi Supreme Court, 1984)
Limbert v. Miss. Univ. for Women
998 So. 2d 993 (Mississippi Supreme Court, 2008)
UHS-Qualicare, Inc. v. GULF COAST COM. HOSP., INC.
525 So. 2d 746 (Mississippi Supreme Court, 1987)
Sanderson Farms, Inc. v. Gatlin
848 So. 2d 828 (Mississippi Supreme Court, 2003)
Wright v. Roberts
797 So. 2d 992 (Mississippi Supreme Court, 2001)
Hendrick v. Green
618 So. 2d 76 (Mississippi Supreme Court, 1993)
Morris v. MacIone
546 So. 2d 969 (Mississippi Supreme Court, 1989)
Cenac v. Murry
609 So. 2d 1257 (Mississippi Supreme Court, 1992)
Wright v. Rub-A-Dub Car Wash, Inc.
740 So. 2d 891 (Mississippi Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Watkins Development LLC v. Jackson Redevelopment Authority, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watkins-development-llc-v-jackson-redevelopment-authority-miss-2019.