Water Supply & Storage Co. v. Larimer & Weld Irrigaton Co.

24 Colo. 322
CourtSupreme Court of Colorado
DecidedSeptember 15, 1897
DocketNo. 3519
StatusPublished
Cited by15 cases

This text of 24 Colo. 322 (Water Supply & Storage Co. v. Larimer & Weld Irrigaton Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Water Supply & Storage Co. v. Larimer & Weld Irrigaton Co., 24 Colo. 322 (Colo. 1897).

Opinions

Mr. Justice Campbell

delivered the opinion of the court.

This controversy between the appellant corporation (plaintiff below) and appellees (defendants below) The Larimer and Weld Irrigation Company and The Windsor Reservoir and Canal Company, consists of two branches. The first relates to the extent of the priority of the canal owned by the appellee irrigation company over the ditch owned by the appellant; the second concerns the seniority of rival reservoir appropriations owned by the appellant and the appellee reservoir company.

The appellant is the owner of the Larimer county ditch and of reservoirs known as Nos. 1, 2, 3, 4 and 5 ; the appellee irrigation company of the Larimer and Weld canal and the appellee reservoir company of the Windsor reservoir. In proceedings duly instituted under our statutes, framed for the purpose of establishing the priority of rights to the [324]*324use of water for irrigation belonging to the various irrigating ditches and canals throughout the different water districts of the state, to which the then owners of these ditches arid canals were parties, a decree was duly entered in the district court of Larimer county on the 11, of April, 1882, adjudicating such priorities in water district No. 3, in which all the ditches and reservoirs in controversy are situate.

It is conceded as a matter of fact, and it so appears from the decree, that the priority of the canal of the appellee irrigation company is superior to that of the ditch of the appellant company; and in so far as the controversy with respect to them is concerned, the contention of appellant is that such priority is only to the extent of 560 cubic feet per second of time, while the position assumed by appellee is that such priority is to the extent of 720 cubic feet per second of time.

All of the reservoirs were constructed subsequent to the decrees mentioned; hence the controversy as to them is not affected by any prior judicial decree, but must be determined entirely from the evidence introduced before the trial court. The avowed object of the action is to obtain a judicial determination of the respective rights of the corporation litigants to divert water from the Cache la Poudre river, both for irrigation and for storage in reservoirs.

The second branch of the case we proceed first to dispose of. The evidence was submitted to the trial court without a jury; and findings of fact made that reservoirs Nos. 2, 3 and 4 of the plaintiff, to a specified capacity, were prior in right to the reservoir of the defendant; and that, as between the plaintiff’s reservoirs known as Nos. 1 and 5, or respectively as “Rocky Ridge” and “Long Pond” reservoirs, and that of the defendant reservoir company, the priority was awarded to the latter.

It is practically conceded that the work of construction of the Windsor reservoir (that of the defendant) was begun in July, 1890, and substantially completed in May, 1893. Work upon the Long Pond and the Rocky Ridge reservoirs of the [325]*325plaintiff was commenced about the first day of September, 1891 (about one year after the initiation of defendant’s enterprise), and was finished before that of the defendant.

The proper solution of the respective rights of the litigating parties with respect to these reservoirs depends very largely upon the fact whether reasonable diligence was used by the defendant in prosecuting work. It would serve no useful purpose to detail the evidence upon this disputed point, and we content ourselves with the statement that, after a careful examination of the entire evidence, we are satisfied that the finding of the trial court was correct, and that, in the circumstances disclosed by the record, considering the magnitude and cost of the work, and the obstacles put in its way, the defendant reservoir company was diligent in the prosecution of such construction, and that its priority should, by relation, date from the beginning, and not from the completion, of the work. From this it follows as a matter of law that the priority was properly awarded by the district court to the defendant company as between these three reservoirs in question.

By the decree of 1882 there was awarded to the Larimer and Weld irrigation canal five several priorities, the first by original construction, and the other four by successive enlargements. The decree, after specifying the several amounts to which the canal was entitled by construction and the first three enlargements, proceeds as follows with respect to the fourth:

“ And further, as to said appropriation by fourth enlargement—priority No. 79—in said findings and herein above mentioned, it having been found in manner and form aforesaid that said fourth enlargement of said ditch No. 9 has been, in fact, made, commencing on the month of September, A. D. 1878, by means of which said ditch is actually enlarged to a carrying capacity of 43,200 cubic feet of water per minute of time (i. e., 720 cubic feet per second), the same having been made at great expense and in good faith, for use for said purpose of irrigation, without the fact that actual [326]*326appropriation by use of water bad. been made of increased quantity intended to be carried by means of said fourth enlargement, it is further adjudged and decreed that nothing in said findings or in this decree contained shall prejudice the right of said claimant or other party or parlies interested in said ditch or in appropriations of water from said river by means thereof, in or concerning said fourth enlargement, if the said appropriation of water intended to be made thereby has been, or shall be, in fact, made, or any part thereof, with due diligence according to the nature of the work of said enlargement, within a reasonable time from the commencement thereof, and said priority shall stand as Ho. 79, to cover any such actual appropriation so made or to be made until further order and judgment of this court in that behalf.”

From the findings of fact, as well as by the express language of the decree, it will be seen that the fourth enlargement had actually been made at the time the decree was rendered, though the increased supply of water thus secured had not been applied to a recognized use. An opportunity and a right, however, were given to the owner of the canal, or other interested party, within a reasonable time, by proper application, to present proof of, or disprove, the actual application of the enlarged supply of water to a beneficial use, when the original decree would be supplemented and perfected to comply with the facts. Based upon this express order of the court, and in virtue of the irrigation statutes so providing, such application for further proceedings was made, and thereupon an order of the court was entered in March, 1883, for the further hearing of evidence; and on the 11, of April, 1884,- a supplemental decree of the district court was entered, the portions of which that are material to the present discussion are as follows:

“ It is * * * decreed that everything in this decree shall be subject to the provisions of the original decree in said matter, as to everything that is and as to everything that is not decided in this decree.”

The taking of the additional evidence in this further pro[327]*327ceeding necessitated a renumbering of the priorities, as well as certain changes in other respects. That portion of the supplemental decree affecting the Larimer and Weld Irrigation Company is as follows :

“No. Nine.

“ Larimer and Weld Irrigation Canal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crow v. Carlson
690 P.2d 916 (Idaho Supreme Court, 1984)
Meyring Livestock Co. v. Wamsley Cattle Co.
687 P.2d 955 (Supreme Court of Colorado, 1984)
Holbrook Irrigation District v. Fort Lyon Canal Co.
269 P. 574 (Supreme Court of Colorado, 1928)
Riverside Reservoir & Land Co. v. Bijou Irrigation District
176 P. 117 (Supreme Court of Colorado, 1918)
Fruitland Irrigation Co. v. Kruemling
162 P. 161 (Supreme Court of Colorado, 1916)
Consolidated Home Supply Ditch & Reservoir Co. v. Town of Evans
149 P. 834 (Supreme Court of Colorado, 1915)
Ironstone Ditch Co. v. Ashenfelter
57 Colo. 31 (Supreme Court of Colorado, 1914)
Alamosa Creek Canal Co. v. Nelson
42 Colo. 140 (Supreme Court of Colorado, 1908)
O'Brien v. King
41 Colo. 487 (Supreme Court of Colorado, 1907)
MacRae v. Small
85 P. 503 (Oregon Supreme Court, 1906)
Platte Valley Irrigation Co. v. Central Trust Co.
32 Colo. 102 (Supreme Court of Colorado, 1904)
Fort Lyon Canal Co. v. Chew
1 Colo. N. P. 490 (Otero County District Court, 1902)
Clipper Mining Co. v. Eli Mining & Land Co.
29 Colo. 377 (Supreme Court of Colorado, 1902)
Orman & Crook v. Ryan Bros.
25 Colo. 383 (Supreme Court of Colorado, 1898)
Cache La Poudre Reservoir Co. v. Windsor Reservoir & Canal Co.
25 Colo. 53 (Supreme Court of Colorado, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
24 Colo. 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/water-supply-storage-co-v-larimer-weld-irrigaton-co-colo-1897.