Water Quality Insurance Syndicate v. United States

632 F. Supp. 2d 108, 171 Oil & Gas Rep. 300, 2009 A.M.C. 1943, 2009 U.S. Dist. LEXIS 64185, 2009 WL 2032065
CourtDistrict Court, D. Massachusetts
DecidedJune 29, 2009
DocketCivil Action 08-10130-RWZ
StatusPublished
Cited by6 cases

This text of 632 F. Supp. 2d 108 (Water Quality Insurance Syndicate v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Water Quality Insurance Syndicate v. United States, 632 F. Supp. 2d 108, 171 Oil & Gas Rep. 300, 2009 A.M.C. 1943, 2009 U.S. Dist. LEXIS 64185, 2009 WL 2032065 (D. Mass. 2009).

Opinion

MEMORANDUM AND ORDER

ZOBEL, District Judge.

Plaintiff Water Quality Insurance Syndicate (“WQIS”) seeks judicial review under the Administrative Procedures Act, 5 U.S.C. § 551 et seq. (“APA”), of the final agency action by the United States Coast Guard National Pollution Funds Center (“NPFC”). The NPFC denied plaintiffs claim under the Oil Pollution Act of 1990, 33 U.S.C. § 2701, et seq. (“OPA”), for reimbursement of damages and removal costs incurred in connection with an oil spill in Massachusetts Bay on September 6, 2003. Both parties have moved for summary judgment based on the administrative record.

I. Legal Standard

The standard for reviewing the NPFC’s decision is defined by section 706(2)(A) of the APA, which provides that a “reviewing court shall ... hold unlawful and set aside agency action, findings, and conclusions found to be ... arbitrary, capricious, an abuse or discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2). As the Supreme Court recently explained,

Under what we have called this “narrow” standard of review, we insist that an agency examine the relevant data and articulate a satisfactory explanation for its action. We have made clear, however, that a court is not to substitute its judgment for that of the agency, and should uphold a decision of less than ideal clarity if the agency’s path may reasonably be discerned.

F.C.C. v. Fox Television Stations, Inc., — U.S. -, 129 S.Ct. 1800, 1810, 173 L.Ed.2d 738 (2009) (internal quotation marks and citations omitted). “Accordingly, our review under section 706(2)(A) is highly deferential, and the agency’s actions *110 are presumed to be valid.” River Street Donuts, LLC v. Napolitano, 558 F.3d 111, 114 (1st Cir.2009) (noting that agency’s decision must be affirmed if it has a rational basis).

II. Background 1

On September 6, 2003, at approximately 6:00 p.m., the Tug VICTORIA ROSE HUNT (“Tug”) capsized in the Massachusetts Bay three nautical miles southeast off the coast of Massachusetts. The Tug sank during an attempt to move an anchor belonging to the non-self propelled dredge barge SEI 03 (the “Anchor”). Though the Tug had successfully raised the lighter anchors of another dredge earlier that day, it was not successful in raising the Anchor despite repeated efforts.

Captain Thomas K. Toolis (“Toolis”) was the master of the Tug. He had not worked at sea for over three years prior to the day of the capsizing and had never previously worked on the Tug. He had no experience with some of the Tug’s apparatus, including a roller guide in a “cage design” which was used to guide lines from the water to the winch. (Administrative Record (Docket # 6) (“A.R.”) 019-021.) He had been hired by the owner (“Hunt”) the day before and first arrived at the Tug at approximately 8:30 p.m. on September 5, 2003. That evening Toolis and Hunt spent approximately three hours going over the Tug and its equipment. Hunt left around 11:30 p.m., and Toolis slept on the Tug from approximately midnight until 4:30 a.m.

On September 6, 2003, after Toolis awoke at 4:30 a.m. he worked on the Tug in preparation for getting underway. The Tug left the dock around 5:15 a.m. to go to the barge EXCALIBUR. Toolis, Engineer Edward Adams and deckhand Daniel Masterson were aboard. Around 8:30 a.m. the Tug began assisting the EXCALIBUR to move to a work location off Beverly, Massachusetts. They arrived there around 10:30 that morning. At the work site the Tug helped raise and move the EXCALIBUR’s anchors, which Toolis was told weighed about 5,000 pounds each. This work ended at approximately 2:30 p.m., and Toolis took a nap while the Tug proceeded to the SEI 03 barge, and arrived at around 4:00 p.m.

During its work with the SEI 03, the Tug was asked to raise the starboard bow anchor of the SEI 03 (the Anchor). The Anchor’s weight was (and is) unknown, although Toolis stated that he was told by Hunt and either the SEI 03’s captain or winch operator that it weighed 10,000 pounds. A spokesperson for Hunt subsequently told the Boston Globe that it weighed 14,000 pounds. In any event, it was at least twice the weight of the EXCALIBUR’s anchors. The Tug hooked onto the Anchor at approximately 4:30 p.m. Using the full power of both of the Tug’s engines, Toolis was able to pull the Anchor free and started dragging it along the bottom. Toolis called the SEI 03 and advised that the Anchor was free and had been moved. The SEI 03 told Toolis that it did not want him to drag the Anchor. 2 At that point Toolis called Hunt to discuss *111 how to lift the Anchor. They decided to take more wire off the winch and increase the hydraulic pressure to it. After a detour of approximately an hour to help move the barge, the Tug returned to the Anchor. (A.R. 033-34.) Toolis made the changes he had discussed with Hunt and again tried to lift the Anchor, to no avail. Toolis paid off more cable and gave the Tug’s engines more throttle. The wire was on the starboard side of the stern cage, which pulled the Tug starboard. At that point, the Tug rolled to the starboard side about five or ten degrees and became partially submerged at the stern. 3 The water had come through the Tug’s scuppers and up against its wheel house.

The Tug started to correct itself but quickly rolled again, more violently, to the starboard side with its throttles still in the ahead position.' At around 6:00 p.m., it flipped completely onto its starboard side and sank in over 100 feet of ‘water. It contained around 8,000 gallons of fuel oil and an unknown quantity of other pollutants at the time it sank. Although some of the oil escaped, a large portion remained aboard. The Tug was salvaged approximately one and one-half months later.

WQIS, the Tug’s insurer, paid for the cleanup of the oil spill and the salvage. In October 2005 it filed a claim for partial reimbursement with the NPFC for $492,233.68, the amount it expended above the $500,000 limitation of liability amount set out in the OPA. The NPFC denied the claim and the request for reconsideration. The denial of reconsideration constitutes the final agency action. 4

III. Discussion

A. The OPA

In 1989, the supertanker EXXON VALDEZ ran aground in Alaska, causing the largest oil spill in United States history. Congress responded by enacting the OPA, which establishes a comprehensive federal scheme for oil pollution liability. The OPA imposes strict liability for pollution removal costs and damages on the “responsible party” for a vessel or a facility from which oil is discharged. See 33 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Water Quality Insurance Syndicate v. United States
225 F. Supp. 3d 41 (District of Columbia, 2016)
United States v. BP Exploration & Production, Inc.
21 F. Supp. 3d 657 (E.D. Louisiana, 2014)
Great American Insurance v. United States
55 F. Supp. 3d 1053 (N.D. Illinois, 2014)
Bean Dredging, LLC v. United States
773 F. Supp. 2d 63 (District of Columbia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
632 F. Supp. 2d 108, 171 Oil & Gas Rep. 300, 2009 A.M.C. 1943, 2009 U.S. Dist. LEXIS 64185, 2009 WL 2032065, Counsel Stack Legal Research, https://law.counselstack.com/opinion/water-quality-insurance-syndicate-v-united-states-mad-2009.