Water Power Co. v. Pacificorp

781 P.2d 860, 99 Or. App. 125
CourtCourt of Appeals of Oregon
DecidedOctober 25, 1989
Docket8607-04185; CA A46977
StatusPublished

This text of 781 P.2d 860 (Water Power Co. v. Pacificorp) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Water Power Co. v. Pacificorp, 781 P.2d 860, 99 Or. App. 125 (Or. Ct. App. 1989).

Opinion

NEWMAN, J.

Plaintiffs (Water Power) appeal a judgment for defendant (Pacific) in an action for damages for breach of an electric power purchase agreement.1 The jury returned a general verdict for Pacific. Water Power makes ten assignments of error challenging the court’s giving or refusing to give instructions, its ruling that the Public Utility Commission (PUC) had primary jurisdiction and certain rulings on evidence and damages. We affirm.

The jury could have found that Water Power, a small power producer, wished to build a project on Mill Creek in Douglas County and generate, sell and deliver power to Pacific, a regulated utility. Water Power commenced negotiations with Pacific in late 1982. Pacific notified Water Power, whose production facilities were not connected to Pacific’s electric power grid,2 that, before it would execute a power purchase agreement, it would require a “wheeling” or transmission agreement that would detail how Water Power would send power from Mill Creek to Pacific’s grid.

Pacific buys power according to an avoided cost schedule that is subject to approval by PUC.3 In August, 1983, PUC approved a new schedule with lower rates than the 1982 schedule. Pacific notified Water Power that a power purchase agreement executed after September 30, 1983, would use the lower rates.

Water Power could deliver its power to Pacific at several locations, including Cottage Grove, in Lane County, and Fairview, in Coos County. In either case, Water Power would have to send its power over lines of the Bonneville [128]*128Power Administration (BPA) and the Douglas Electric Cooperative, Inc. (Douglas).4 Douglas’s lines run from Mill Creek to BPA’s system, BPA lines connect with Pacific’s grid at several points. Accordingly, it was necessary that Douglas, BPA, Water Power and Pacific all be parties to a transmission agreement. Both BPA and Douglas had expressed their willingness to do so.

To take advantage of Pacific’s higher 1982 purchase rates, Water Power proposed a power purchase agreement at the 1982 rates with a provision that, unless a transmission agreement were executed by a certain date, Pacific could terminate the agreement. Pacific rejected the proposal. In October, 1983, Water Power asked PUC, as an arbitrator, former OAR 860-29-005(3), to decide whether Pacific was required to sign a power purchase agreement at 1982 rates. PUC ruled that Pacific had to sign a power purchase agreement at 1982 rates, if Water Power would submit a written plan for transmitting power to Pacific’s grid. In December, 1983, Water Power submitted a plan to use the systems of BPA and Douglas to deliver its power to Pacific at Cottage Grove.

On June 5, 1984, Pacific expressed a willingness to execute a power purchase agreement under which Water Power would have until December 31,1984, to obtain a transmission agreement executed by Water Power, Pacific, Douglas and BPA. Pacific and Water Power disagreed, however, about the point of delivery. Pacific wanted Cottage Grove; Water Power wanted to leave the point of delivery open. On August 17,1984, the parties asked PUC to decide that dispute. It ruled that Pacific could require that Cottage Grove be the point of delivery, but that the deadline for completion of the transmission agreement would be November 1,1985.

Water Power and Pacific executed the power purchase agreement on November 28,1984, and PUC approved it. Article II of the agreement provides:

“This Agreement shall not become effective until Sellers, Utility, BPA, and Pacific have entered into the Transmission Agreement providing for firm transmission of electric power [129]*129from the Facility to Pacific’s system pursuant to, and under the constraints contained in, Article IX; provided, that if the Transmission Agreement has not been executed by all four parties prior to November 1, 1985, or if the Transmission Agreement has not been approved by the Rural Electrification Administration prior to November 1, 1986, this Agreement shall be null and void.” (Emphasis in original.)

Article I defines “Point of Delivery” as

“the location where Net Delivered Output is delivered to Pacific’s system at BPA’s Cottage Grove Substation, as specified in the Transmission Agreement, or at such other location as may reasonably be required by Pacific to allow Pacific to accept Net Delivered Output from BPA.”

Article XVII provides, in part:

“As used in this Agreement, ‘Force Majeure’ means unforeseeable causes beyond the reasonable control of and without the fault or negligence of the party claiming Force Majeure.”

BPA distributed a draft transmission agreement to Douglas, Pacific, and Water Power on October 10, 1984. Pacific responded with comments in June, 1985. The parties continued to disagree about the point of delivery. Water Power wanted Fairview as the primary point of delivery; Pacific wanted it only as a backup point to Cottage Grove. They referred the dispute to PUC. On October 7,1985, PUC ruled that Pacific’s position was reasonable in terms of its needs and consistent with the power purchase agreement.

On October 22,1985, BPA circulated another draft of a transmission agreement with new provisions. Pacific telephoned BPA on October 25, hand-delivered a marked-up copy of the draft to BPA on October 28, and sent it a letter, dated October 30, discussing its concerns about the new provisions. Pacific stated that it wanted Cottage Grove as the point of delivery. The letter ended with an assurance that “Pacific is willing to discuss the resolution of these issues to achieve an acceptable agreement within the time-frame stated in the Power Purchase Agreement.” BPA responded to Pacific on February 28, 1986. It rejected Cottage Grove as the point of delivery and suggested its Alvey substation instead.

On November 12,1985, Water Power notified Pacific that it had been willing to sign the BPA draft transmission [130]*130agreement of October 21, 1985, with one change in the environmental review provision, and that the condition in the power purchase agreement that required a transmission agreement by November 1,1985, should be excused under the force majeure article, because Water Power had no control over the other three parties. Pacific replied on December 13,1985, that, under Article II, the power purchase agreement was null and void, because the transmission agreement had not been executed by the four parties by November 1,1985. On July 14, 1986, Water Power brought this action.

Water Power assigns as errors that the court instructed the jury, in substance, that Pacific (1) was not required to enter into a transmission agreement that it reasonably believed was not in its best interests; and (2) had a right to insist that the transmission agreement designate Cottage Grove as the point of delivery. Water Power argues that the federal Public Utilities Regulatory Policy Act (PURPA), 16 USC § 824a-3, imposes on Pacific a statutory obligation to purchase electric power from it and that Pacific’s best interests, or preference as to a delivery point, are irrelevant.

Water Power relies on Snow Mt. Pine Company v. Maudlin, 84 Or App 590, 734 P2d 1366, rev den 303 Or 591 (1987), and asserts that “the obligation to purchase power is imposed by law on a utility; it is not voluntarily assumed.” 84 Or App at 599. In Snow Mt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snow Mountain Pine Co. v. Maudlin
734 P.2d 1366 (Court of Appeals of Oregon, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
781 P.2d 860, 99 Or. App. 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/water-power-co-v-pacificorp-orctapp-1989.